Anti-Data Center Policies

East Liverpool requires qualifying data centers in B-3 or M-1 districts to submit development plans for public review and meet site and building standards, which can add cost and delay but do not ban them.

current law · City of East Liverpool
Requires qualifying data centers treated as office, research, or restricted-industrial developments to undergo planning review and meet site-design, access, parking, and approval requirements; data centers are not specifically named.CHAPTER 1131 Special Provisions for Commercial and Industrial Uses — 1131.02 Integrated Office, Research and Restricted Industrial Centers

What this means

For data centers that qualify as office, research, or restricted industrial uses in B-3 or M-1 districts, the rule requires a development plan and public review, plus limits such as building-height, setback, lot-coverage, parking, and landscaping requirements (at least four acres and a preliminary plan; development standards). Those requirements can add cost and delay, but they do not prohibit development, so the overall effect is meaningfully restrictive rather than a ban.

People behind it

  • Adopted and enacted the codified ordinances through Ordinance No. 51, 2009.

  • Entered into the contract to have the ordinances recodified.

  • Contracted to prepare and publish the recodification.

Restrictions & requirementsHide restrictions & requirements12
  • Conditional applicability: these rules cover integrated office, research, and restricted-industrial developments in B-3 and M-1 districts; a data center would be subject to them only if treated as one of those permitted uses. The tract must be at least four acres and near an area for that use shown on the future Land Use Plan. At least four acres

  • A preliminary development plan must be submitted to the Planning Commission for review and recommendations to Council. The Commission must be satisfied that the proponents can finance the project, will start construction within one year after approval, and will finish within a reasonable time it determines. Start construction within one year

  • The development must provide reasonably direct access from principal thoroughfares and address congestion through projected road improvements, proper entrances and exits, and internal traffic and parking arrangements. Its design and landscaping must fit harmoniously with surrounding development and have no adverse effects on it. No adverse effects upon adjoining or surrounding development

  • Permitted uses are limited to the offices, research buildings, restricted-industrial uses, and related uses listed for B-3 and M-1 districts in Chapter 1123. Uses listed in Chapter 1123

  • Dimensional limits include a maximum height of three stories or 45 feet, except as modified by Section 1125.05; buildings must be at least 30 feet from tract boundaries; and buildings may cover no more than 30% of the tract. No building shall exceed three stories or forty-five feet

  • Loading and storage must be screened from adjoining R-district properties by building walls, a solid wall, or a compact evergreen hedge at least six feet high. Street-side and intervening areas between buildings, drives, parking, and improved areas must be landscaped and maintained. Loading and storage shall be permanently screened

  • Parking must provide one off-street space for every two employees on the maximum working shift. Parking areas must be at least 25 feet from adjoining lot lines in R or B districts and 30 feet from the street right-of-way, and must be properly drained and have a durable, dust-free surface. One off-street space for each two employees

  • Off-street loading or unloading space must be sufficient in area and vertical clearance for the maximum number of trucks and tractor-trailers anticipated at one time. Maximum number of trucks and tractor-trailers

  • Access drives must be spaced at least 300 feet apart. Parking-area lighting must be arranged to reflect light away from adjoining R-district premises. Minimum interval of 300 feet

  • Signs are generally limited to wall signs on the principal building, with a small freestanding identification or directional sign of no more than 15 square feet allowed at entrances. If illuminated, the light source must not be visible. Small free-standing identification and directional sign

  • After the preliminary plan is found to appear compliant, proponents must submit a final development plan incorporating Commission-requested or suggested changes. The Commission forwards a compliant plan to Council, which must hold a public hearing; Council may modify the plan and authorize a zoning certificate. Council shall hold a public hearing

  • Operations must not create dangerous or objectionable conditions affecting surrounding areas, subject to the section’s safeguards and standards. These include noise limits that vary by frequency and neighboring district, no vibration discernible without instruments on adjoining property, limits on smoke, and restrictions on harmful air pollution, offensive odors, glare, erosion, and water pollution. No vibration shall be permitted which is discernible without instruments

Benefits & exceptionsHide benefits & exceptions2
  • If a data center qualifies as an office, research, or restricted industrial use permitted under Chapter 1123, it may use the integrated-development review process in B-3 or M-1 districts. The tract must be at least four acres and near an area shown for that purpose on the Future Land Use Plan; the proposal requires Planning Commission review and Council action after a public hearing. The regulations apply to development of groups of properties.

  • After Council approves the final development plan, proponents may request rearrangements of buildings, parking areas, entrances, heights, or yards. The Planning Commission may authorize them if they conform to the approved plan’s standards and the zoning ordinance. Adjustments or rearrangements may be authorized by the Commission.