City of Cuyahoga Falls

Strongly Pro-Data Center Policies

Summit County’s enacted agreement provides public funding and a site for a large data center for the city to operate, benefiting this project specifically without broadly easing development for others.

Rating and summary from Summit County as there are no scored current or future laws outside temporary restrictions for City of Cuyahoga Falls.

pending · City of Cuyahoga Falls
Limits data centers to one building of up to 5,000 square feet per property, caps power use at 5 megawatts subject to city approval, and sets water-use, noise, and pollution requirements.Cuyahoga Falls Ohio Temporary Ordinance A-60 (2026)

People behind it

  • Presented the ordinance and is identified as its proposer.

  • Recommended approval of the amendments.

Restrictions & requirementsHide restrictions & requirements8
  • The ordinance states that it limits the zoning districts where data centers may be located. The provided text does not identify which districts; it applies the listed standards in districts where data centers are designated as Limited Uses subject to specific conditions.

  • A data center building may be no larger than 5,000 square feet, and a property may have no more than one data center building.

  • Electric power draw may not exceed 5 MW at any time and is subject to Electric Department approval and additional requirements. Expanding the facility or increasing its power draw requires prior approval from that department.

  • Water use for cooling is subject to Water Department approval and any additional requirements.

  • Noise at the property line may not exceed 70 dBA from 8:00 a.m. to 5:00 p.m.; at other times, noise must comply with the cited city noise regulations.

  • Dust and particulate emissions must comply with current Ohio Environmental Protection Agency air-pollution standards.

  • Discharges of solids, liquids, or other matter into or onto bodies of water, streams, or the ground must comply with Ohio Environmental Protection Agency water-pollution standards and have a valid discharge permit.

  • Data centers may not emit or discharge toxic or noxious matter that may harm public health, safety, or welfare, or endanger the natural environment. Hazardous or regulated materials must be reported to the City Fire Department, and their storage, use, and disposal must meet Ohio Environmental Protection Agency requirements.

Benefits & exceptionsHide benefits & exceptions3
  • The code identifies data centers as a manufacturing use and provides a limited-use pathway in districts where that use is allowed, subject to the measure’s conditions (“Data Center”; “In districts where a Data Center”).

  • A data center may draw up to 5 MW of electric power at any time, subject to Electric Department approval and any additional requirements. Expansions of the facility or increases in power draw require prior approval (“Maximum electric power draw”).

  • The measure sets a daytime noise limit of 70 dBA at the data-center property line from 8:00 a.m. to 5:00 p.m.; noise at other times is governed by the cited noise regulations (“shall not exceed 70 decibels”).