Chardon’s commercial or industrial site limits and requirements for underground utilities and noise and emissions controls may constrain data center projects, but their classification is unclear.
current law · City of ChardonSets general zoning and development rules for commercial and industrial uses that could apply to a data center, but does not specifically regulate data centers.Chardon Ohio
What this means
The rules do not mention data centers specifically, but projects treated as commercial or industrial would face meaningful site limits, including minimum lot sizes, setbacks, and building-height caps (industrial district standards). They also require new buildings to put utility services underground and control noise and emissions (performance standards). The code does not say how a data center is classified, so the exact effect is uncertain; overall, these rules could make development harder, without expressly banning data centers.
Restrictions & requirementsHide restrictions & requirements8
Where a data-center use is permitted in a commercial or industrial district, it must meet district lot-area, lot-width, and building-coverage limits. C-3 and C-4 require at least 20,000 square feet and 100 feet of width; I-1 requires at least 1 acre and 150 feet of width. Maximum building coverage is 30% in C-3, 40% in C-4 and I-1, and 100% in C-2. (minimum lot requirements)
Buildings must meet district setbacks from streets and neighboring lots. For example, the minimum street setback is 30 feet in C-3, 50 feet in C-4, and 40 feet in I-1; setbacks are greater next to residential districts. (minimum building and parking setbacks)
Building height is limited by district: 50 feet in C-2, 45 feet in C-3, C-4, and I-1; C-2, C-3, and C-4 also have a three-story maximum. (maximum building height)
Off-street parking must comply with Chapter 1151 and district parking setbacks. In C-2, accessory parking may not be placed between the principal building’s front and the street; a Planning Commission variance is possible in specified circumstances and requires screening. (C-2 accessory parking rules)
Operations must be conducted inside an enclosed building unless specifically permitted otherwise; solid waste must be removed, stored in a building, or kept in a fully enclosed container in a side or rear yard and screened. (enclosure requirement)
Outdoor lighting must meet Chapter 1153 requirements, and uses may not create dangerous or objectionable noise or emissions and must comply with Chapter 1147. (lighting and noise standards)
New buildings must have utility services, including electric, telephone, and cable TV, installed underground. (underground utility lines)
Stormwater detention or retention facilities visible from a public street must be integrated into a landscaped area. (stormwater facilities)