Athens has enacted a temporary pause of up to one year on receiving or processing data-center permit applications, delaying new construction and permitted expansions; officials may extend it another year. Existing centers are not expressly required to close.

Rating from Athens County as there are no scored current or future laws outside temporary restrictions for City of Athens.

current law · City of Athens
The City of Athens' published notice confirms Ordinance 0-70-26 imposes a temporary moratorium not to exceed one year on granting or issuing any permits for data centers within city limits.Ohio Athens Ordinance 0-70-26 (2026)

What this means

The measure would pause new data centers in Athens for one year, covering AI facilities and large-scale data storage, which would substantially delay development. The mayor or service-safety director could extend the pause by another year, making this a severe but temporary restriction, not a permanent ban. one-year temporary moratorium option to extend the moratorium by another year

Timing

Initial term not to exceed one year; mayor and/or service-safety director may extend another year. Exact end date not verified.

People behind it

  • Authorized by Ordinance 0-71-26 to enter and extend the agreement for Public Defender’s Office services.

  • Authorized by Ordinance 0-73-26 to advertise and accept bids and enter contracts for the Community Pavilion project.

Restrictions & requirementsHide restrictions & requirements1
  • Pauses granting or issuing any permits for data centers within city corporate limits for up to one year.

Sources

current law · Corporate limits of the City of Athens
Temporarily prohibits Athens from accepting or processing permit applications or issuing permits for data centers for up to one year.City of Athens Ordinance 70-26 (2026)

What this means

The measure would stop data-center permit applications from being received or processed and block permits for up to one year, making new construction and permitted expansion substantially harder (moratorium of up to one year). It does not expressly require existing data centers to shut down.

Timing

Ends
not to exceed one year after passage and approval by the Mayor

The ordinance states that the moratorium is [not to exceed one year](https://athensoh.api.civicclerk.com/v1/Meetings/GetMeetingFileStream(fileId=3991,plainText=false#:~:text=temporary%20moratorium%20not%20to%20exceed%20one%20year) and takes effect upon passage and mayoral approval. No specific expiration date or extension condition is stated.

People behind it

  • Introduced the ordinance as Chair of the Finance & Personnel Committee.

  • Imposed the moratorium and is assigned to review and study data center impacts and possible regulations.

  • Assigned to participate in the review and study of data centers and their impacts.

Restrictions & requirementsHide restrictions & requirements2
  • For up to one year, the city may not receive or process permit applications for proposed data centers within its corporate limits, or grant or issue permits for them. The ordinance defines “Data Center” broadly to include facilities such as server farms, cloud computing hubs, and colocation centers. [Moratorium and definition](https://athensoh.api.civicclerk.com/v1/Meetings/GetMeetingFileStream(fileId=3991,plainText=false#:~:text=The%20Council%20of%20the%20City%20of%20Athens%20imposes%20a%20temporary%20moratorium)

  • While the moratorium is in effect, applicable deadlines for city departments or officials to act on permit applications or site-plan reviews are suspended and tolled. [Suspension of time periods](https://athensoh.api.civicclerk.com/v1/Meetings/GetMeetingFileStream(fileId=3991,plainText=false#:~:text=This%20temporary%20moratorium%20suspends%20and%20tolls%20any%20time%20periods)