Town of Wendell
This restriction takes precedence while in effect. The rating below excludes temporary restrictions.
Slightly Pro-Data Center Policies
Wendell’s status listing marks a temporary moratorium as enacted, though its description says “if enacted”; it would pause permits for data centers through year-end.
Rating from North Carolina statewide as there are no scored current or future laws outside temporary restrictions for Town of Wendell.
current law · Town of WendellThe Town of Wendell adopted a temporary moratorium on data-center development through December 31, 2026, or an earlier date if the town ends it.North Carolina Wendell Data Center Moratorium (2026)
What this means
If enacted, the temporary moratorium would stop the Town from accepting, processing, or approving permits for data centers and related facilities, delaying new construction and expansion. The source describes it as lasting through the end of the year, a substantial short-term barrier, though it would not permanently ban data centers.
Timing
- Ends
- through year's end
The measure is a temporary moratorium on applications related to data centers, data processing facilities, and cryptocurrency mining. The available source describes it as lasting through year's end; no exact calendar date is stated.
People behind it
- Town of Wendell Board of Commissioners
Voted to hold the public hearing and adopted the temporary moratorium.
- Town of Wendell
Proposed and administers the temporary moratorium while updating its Unified Development Ordinance.
Restrictions & requirementsHide restrictions & requirements2
Temporary moratorium halting the acceptance, processing, and approval of development-permit applications for data centers, data processing facilities, and cryptocurrency-mining operations.
A public hearing is required for a moratorium lasting more than 61 days, creating an additional procedural step before such a moratorium can take effect.