Town of Selma
Anti-Data Center Policies
Selma town’s enacted data-center rules require studies and town review, limit cooling methods, and make applicants pay for needed utility upgrades and a decommissioning bond. Renewable-energy projects may qualify for extra height and some landscaping flexibility.
current law · Town of SelmaRequires data centers to obtain special-use approval and meet rules for screening, electricity and water studies, closed-loop cooling, noise limits, decommissioning guarantees, and paying for needed utility upgrades.Ordinance No. 2026-10-06 — Data Center Development Regulations
What this means
The measure would make development and operation significantly harder: it requires studies and town review, restricts cooling methods, and makes the applicant pay for necessary utility upgrades and a substantial decommissioning bond (utility upgrades at full cost). Renewable-energy projects could qualify for extra height and some landscaping flexibility, but those conditional benefits do not outweigh the added burdens (renewable energy incentives).
People behind it
- Town of Selma staff
Initiated the text amendments to the Town Code.
Restrictions & requirementsHide restrictions & requirements15
The permitted-use table marks data centers as allowed in one zoning district and prohibited in the others shown. Data Centers
A data center must obtain a Special Use Permit approved by the Town Council before proceeding to zoning-compliance certification. approval of the Special Use Permit by the Town Council
Ground-mounted and rooftop mechanical equipment outside enclosed structures must be screened from public roads and residential properties; a category C landscape buffer is required around the property, except where adjoining land is zoned I-1 or I-2. A category “C” landscape buffer
Applicants must submit an electrical-load study for review by Town engineers and verify that the grid can serve the facility at peak demand without impairing service to other users or causing electrical interference or voltage fluctuations. The verification must be updated annually or when the Town requests it, and may be approved or denied based on grid feasibility. An electrical load study is required
Groundwater may not be used for cooling, and the facility must use a geothermal closed-loop cooling system. A water-and-sewer demand study and compliance with CDC Legionella-prevention standards are also required. The use of groundwater for cooling is prohibited
A site-lighting photometric plan must be submitted for review and meet the town’s lighting standards. A site lighting (photometric) plan is required
The facility must meet the town’s manufacturing/processing performance standards for noise, vibration, odor, and other environmental impacts. Follows the standards under ARTICLE V
A noise study certified by a licensed acoustical engineer, including mitigation proposals, is required before the Town Council decision and again one year after the certificate of occupancy. Noise must stay within the decibel limits set in the Special Use Permit, measured from any lot line. A noise study is required
The Zoning Administrator may require third-party acoustical studies at the applicant’s expense, limited to two in a calendar year unless the property is found in violation. If a study finds noise above the limit, the owner incurs the fee-schedule civil penalty for each such study until the violation is abated. limited to two (2) within one (1) calendar year
Generator testing and maintenance are restricted to weekdays from 10:00 a.m. to 4:00 p.m. only be performed on weekdays
Rooftop equipment must use sound-attenuating technology and be screened from public-street view by a parapet wall or another screening method. appropriate sound attenuating technology
Before zoning-compliance certification, the applicant must provide an Administrator-approved decommissioning cost estimate and automatically renewing surety or performance bond from a Treasury-listed company. The bond must be at least one and one-half times estimated decommissioning cost minus salvage value, or $50,000, whichever is greater; updated estimates and bond certificates are due annually, and the bond remains in force through decommissioning and site restoration. one-and-one half (1½) times the decommissioning cost
If a site is abandoned, the owner must notify the Planning Department and ensure hazardous materials are remediated within 12 months of the final day of operations. within (12) months of the final day of operations
The decommissioning plan must be recorded with the Town Clerk before zoning-compliance certification; approved plan changes or ownership changes require an updated signed plan to be recorded within 30 days of the ownership change. recorded with the Town Clerk
The applicant must pay the full cost of utility-infrastructure upgrades needed for the data center, including items such as sewer capacity, transformers, electric-line extensions, and water and sewer system development. provided at full cost by the applicant
Benefits & exceptionsHide benefits & exceptions3
The permitted-use table marks data centers “P” in one listed zoning district and “X” in the others, allowing them in the district marked P. The supplied table text does not identify the district names. Data Centers
Projects supplying at least 25% of projected annual energy use through on-site renewable generation or energy storage may qualify for regulatory flexibility: Tier 1 allows a maximum building height of 70 feet and Type B landscaping next to business or industrial uses. At 50% or more, Tier 2 allows a 75-foot maximum and also bases Table 3 calculations on plants per 125 linear feet of landscape area. Tiered system
The ordinance provides for utility upgrades needed to accommodate a data center, including sewer capacity, transformers, electric-line extensions, and water and sewer system development. The applicant must pay the full cost of those upgrades. All necessary upgrades