McDowell County
This restriction takes precedence while in effect. The rating below excludes temporary restrictions.
Slightly Pro-Data Center Policies
McDowell County has enacted a six-month pause on data center development while it studies possible rules. The pause delays projects but is not a permanent ban.
Rating from North Carolina statewide as there are no scored current or future laws outside temporary restrictions for McDowell County.
Specific to McDowell County only.
current law · County measureOn August 31, 2026, McDowell County commissioners adopted a six-month data-center moratorium by a 5–0 vote.McDowell County Board of Commissioners Six-Month Data Center Moratorium (2026)
What this means
The six-month moratorium would temporarily stop data center development while the county studies possible rules, delaying projects that might otherwise proceed. It is not a permanent ban, but the pause is a substantial short-term barrier.
Timing
The Board adopted a six-month moratorium on August 31, 2026. Exact effective date and calendar sunset, early termination, extensions and exemptions are not verified without the standalone ordinance; no expiration date has been calculated or invented.
People behind it
- David Walker
Commissioner who moves to enact the six-month moratorium.
- Lynn Greene
Vice-Chair who seconds the moratorium motion.
- Ashley Wooten
County Manager who presents staff recommendations.
Restrictions & requirementsHide restrictions & requirements1
Six-month data-center development moratorium gives staff and the Planning Board time to study concerns and prepare proposed regulatory parameters. Specific permitting coverage and exceptions cannot be verified from the motion alone.