Town of Thurston

This restriction takes precedence while in effect. The rating below excludes temporary restrictions.

Pro-Data Center Policies

Thurston has enacted a two-year pause on accepting applications or issuing permits for data centers, including AI and large-scale data-processing facilities, making construction or expansion harder during that period.

Rating from New York statewide as there are no scored current or future laws outside temporary restrictions for Town of Thurston.

current law · Town of Thurston
Establishes a two-year moratorium on commercial cryptocurrency mining operations and data processing centers in the Town of Thurston, covering facilities used for cryptocurrency mining, blockchain authentication, artificial-intelligence processing, and other large-scale data processing or storage.New York Local Law No. 5 (2026) — Town of Thurston, Steuben County

What this means

The measure would stop the Town from accepting applications or issuing permits for data centers, including facilities used for AI and large-scale data processing (permit restrictions). The pause would last two years unless ended earlier, making building or expanding a data center substantially harder during that period (two-year duration).

Timing

Ends
two (2) years from the effective date

The moratorium takes effect immediately upon filing with the New York Department of State and may be terminated earlier by the Town Board.

People behind it

  • Moved the resolution to adopt Local Law #5 establishing the two-year moratorium.

  • Seconded the resolution to adopt Local Law #5.

  • Enacted and adopted Local Law #5 establishing the moratorium.

Show 1 more peopleShow fewer people
  • Designated as the enforcement officer responsible for interpreting and enforcing Local Law #5.

Restrictions & requirementsHide restrictions & requirements7
  • A two-year moratorium prohibits commercial cryptocurrency mining operations and data processing centers in the Town, unless the Town Board ends it earlier. moratorium imposed for two years

  • During the moratorium, the Code Enforcement Officer may not accept an application for a commercial cryptocurrency mining operation or data processing center. shall not accept an application

  • During the moratorium, the Code Enforcement Officer may not grant a permit for a commercial cryptocurrency mining operation or data processing center. shall not grant any permit

  • Violations may result in a fine of up to $250, imprisonment for up to 15 days, or both; each additional week of violation is a separate violation. fine of not more than $250

  • A civil penalty of up to $2,500 may be imposed for each day or part of a day that a violation continues. civil penalty of not more than $2,500 for each day

  • The Town may seek court-ordered injunctive relief to prevent, restrain, correct, or abate a violation, with Town Board authorization required before starting the action. prevent, restrain, correct, or abate any violation

  • The Town Board may seek reimbursement for costs incurred in identifying and remedying violations, including reasonable attorney fees. reasonable attorney fees