Doña Ana County

Pro-Data Center Policies

Doña Ana County has enacted project-specific support for Project Jupiter, including long-term property-tax relief, financing, tax-revenue sharing, and reduced permit fees. These benefits depend on job, investment, and other commitments, but do not create broad operating rules for data centers.

Incentives

Tax benefits
4

Conditionally proposes leases under which all ad valorem (property) taxes will be abated during the term of the Bonds, subject to negotiated PILOT payments, and authorizes agency purchases using Type 9 Nontaxable Transaction Certificates for eligible project equipment and tangible property. Bond issuance and continued certificate benefits depend on later ordinance approval; the resolution specifies affiliate-funded bonds, not subsidized borrowing terms.

The executed participation agreement provides the Project Jupiter companies with 50% of the net receipts from specified County and State general-fund gross-receipts-tax increments generated by taxable construction expenses through October 23, 2035. The companies must first dedicate $50,000,000 of their proceeds back to County water and wastewater improvements before retaining subsequent distributions.

The attached Project Jupiter MOU describes the IRB package's full (100%) abatement of real and personal property taxes for 30 years, offset by PILOT payments, and support for gross receipts tax exemptions for eligible property. These terms are described in the conditional MOU, which makes the approved IRB documents controlling; no preferential borrowing terms are established by the reviewed attached texts.

Conditionally proposes a return of 50% of the gross receipts and compensating taxes collected by the County from Project Jupiter construction to reimburse the developer's qualifying expenses, alongside proposed State tax sharing. Assistance remains subject to the approval and authorization by the Board pursuant to the LEDA Ordinance, rather than an unconditional grant.

Fee waivers

Provides Red Chiles and Yucca Growth with a reduced fee schedule for County building permits related to the Project, with scheduled payments totaling $4,500,000.

current law · County project: Unincorporated areas outside incorporated municipalities, including the 16 OUT tax district; certain measures are limited to the Project Jupiter site, data center facilities, and related infrastructure or easements
This resolution declares the county’s intent to consider issuing up to $165 billion in taxable industrial revenue bonds for Project Jupiter, including a microgrid and four anticipated data-center facilities.Doña Ana County Resolution No. 2025 — intent to issue Project Jupiter industrial revenue bonds

What this means

The measure would strongly encourage data center development through financing, long-term property-tax relief, and reduced fees and taxes. These benefits are tied to conditions such as job commitments, water-use limits, and payments to the County, and some assistance still needs approval.

People behind it

  • Proposed issuer and administrator of the industrial revenue bonds, leases, tax abatements, and related project documents.

  • Governing body that introduced, considered, and adopted the resolution and subsequent bond ordinances.

  • Series 2025A Company that proposed and would develop the power-generation, battery-storage, and microgrid project.

Show 10 more peopleShow fewer people
  • Series 2025B Company that proposed and would develop one of the data-center projects.

  • Series 2025B Company that proposed and would develop one of the data-center projects.

  • Series 2025B Company that proposed and would develop one of the data-center projects.

  • Series 2025B Company that proposed and would develop one of the data-center projects.

  • Series 2025C Company that proposed and would equip the four data-center projects.

  • Collective project entity, acting through affiliated development entities, that proposed the hyperscale data-center campus and related infrastructure.

  • Chief Legal & Administrative Officer who executed the Project Jupiter memorandum of understanding on behalf of the project.

  • Authorized agent for the Series 2025B Companies in acquiring project equipment and tangible personal property and administering related nontaxable transaction certificates.

  • County official authorized to negotiate payments in lieu of taxes and oversee related implementation steps.

  • County Clerk who was authorized to issue required notices and signed the published notice forms.

Restrictions & requirementsHide restrictions & requirements17
  • Project construction and operation remain subject to Doña Ana County land-use regulation and approval.

  • Construction requires applicable permits, industrial revenue bond approval, and related LEDA approvals; construction was expressly conditioned on obtaining those approvals.

  • Before construction begins, the project must complete environmental reviews required by state and local law, including reviews of water use, air quality, noise, stormwater, and overall environmental impacts.

  • The project must fund the design, permitting, and construction of any required public-water-main extensions connecting the site to existing infrastructure.

  • The project must fund the design, permitting, and construction of required wastewater force-main extensions and an onsite lift station to connect with regional infrastructure.

  • The project must fund the design and construction of a roadway extension from the Highway 136 and Highway 9 intersection to provide site access.

  • Operational water use for the full campus is limited to an average of 20,000 gallons per day and a maximum peak use of 60,000 gallons per day.

  • The onsite microgrid must comply with HB 93, including the requirement that qualified-microgrid power come from net-zero-carbon resources by 2045, and all systems must meet or exceed federal and state air-quality standards.

  • The project must make fixed annual payments in lieu of property taxes of $12 million for 30 years, beginning in the first year of data-center operations, instead of receiving a property-tax abatement without payments.

  • The project must make scheduled permit-related payments totaling $4.5 million from 2025 through 2028, in place of standard county building-permit fees.

  • The project commits to contribute $50 million through New Mexico's LEDA GRT Share program for water and wastewater infrastructure.

  • The project proposes additional community contributions totaling $6.9 million, including workforce development, community, desalination, regional connectivity, and habitat-restoration funds; these payments are contingent on execution of the MOU and approval of the related IRB documents.

  • Issuance of the industrial revenue bonds requires county ordinances adopted after public notice and a public hearing; the notice must generally be published at least 14 days before final consideration.

  • Taxing entities and the county assessor must receive certified-mail notices at least 30 days before the meeting at which final action on the bond ordinances is taken.

  • The county's consideration of the bond ordinances requires public-meeting notice, including at least 72 hours' advance notice of the meeting and agenda availability under county procedures.

  • The bonds must be issued within five years of adoption of the inducement resolution, with Series 2025A expected within two years; otherwise the resolution's stated inducement intent does not apply.

  • The bonds are intended to be purchased only by a parent or affiliate of the project companies, preventing sale to unrelated investors and limiting the available financing structure.

Benefits & exceptionsHide benefits & exceptions1
  • [ { "provision": "Industrial revenue bonds of up to $165 billion": "The County agreed to support taxable industrial revenue bonds totaling up to $165 billion, issued in stages for construction and later equipment upgrades. The bonds are subject to the governing body’s approval and related bond documents." }, { "provision": "Thirty-year property-tax abatement": "The County agreed to abate 100% of qualifying real and personal property taxes for 30 years, offset by negotiated annual payments in lieu of taxes." }, { "provision": "Fixed annual PILOT payments": "Instead of ordinary property taxes, the project would make fixed annual PILOT payments of $12 million, for 30 payments totaling $360 million. Payments begin when the first data-center building operates and continue through the applicable bond and abatement term." }, { "provision": "Gross-receipts-tax exemptions through Type 9 certificates": "The County authorized the project companies and their agents to obtain and use Type 9 nontaxable transaction certificates for eligible capital equipment and tangible personal property. The certificates may be used only for project purchases and not after project completion; the companies must cover resulting taxes or penalties." }, { "provision": "LEDA GRT Share contribution of $50 million": "The project committed $50 million through New Mexico’s LEDA GRT Share program for water and wastewater infrastructure, subject to the program’s approval and requirements." }, { "provision": "Reduced and alternative permit fees": "The project receives an agreed permit-fee schedule totaling $4.5 million for 2025–2028 and is exempt from the County’s standard building permit fees, which are replaced by that alternative payment structure." }, { "provision": "County assistance with permitting and approvals": "The County agreed to facilitate interactions with permitting offices, utilities, and other agencies; assist with permitting procedures; coordinate with state and federal agencies for accelerated review; and support applications for state incentives and workforce assistance." }, { "provision": "Support for off-site easements and rights-of-way": "The County agreed to provide reasonable assistance in obtaining required off-site easements and rights-of-way, including use of public authorities or eminent domain where legally permissible." }, { "provision": "Project-funded water, sewer, and road infrastructure": "The project agreed to fund required public-water-main extensions, wastewater force-main extensions, and the roadway extension connecting the site to Highway 136 and Highway 9. The project may also fund or upsize related infrastructure for broader regional needs." }, { "provision": "Protection from disproportionate future taxes, fees, and utility rates": "The County agreed not to impose special assessments, taxes, fees, or utility rates that are disproportionate to those imposed on similarly situated developments." }, { "provision": "On-site microgrid and project-paid power": "The project may use an on-site microgrid with natural-gas generation and large-scale battery storage, with the project paying for the microgrid and its electricity. The systems must meet or exceed applicable federal and state air-quality standards and comply with the stated HB93 requirements." }, { "provision": "Supplemental community and workforce contributions": "The project proposed $6.9 million in additional payments for workforce education, community projects, desalination evaluation, regional connectivity, and habitat restoration. These payments are outside the IRB documents and are contingent on execution of the MOU and approval of the associated IRB ordinance and documents." } ]

Sources

current law · County project: Project Jupiter-related county actions and funding proceeds, and the Red Chiles/Yucca data center project at the site described in Exhibit A
Project-specific LEDA construction gross-receipts-tax assistance, not a generally applicable data-center zoning law.Doña Ana County Ordinance No. 368-2025 — Project Jupiter LEDA assistance

People behind it

  • Commission chairman who signed the final Project Jupiter agreements on October 30, 2025, according to reporting.

  • Commissioner who cast the only vote against the agreements on September 19 because she was unwilling to approve drafts, according to reporting.

  • Judge who denied the County’s motion to dismiss the incentive challenge on March 20, 2026, according to plaintiff counsel.

Restrictions & requirementsHide restrictions & requirements4
  • Conditions on assistance, not a development ban: dedicates the first $50 million of company GRT proceeds to southern Doña Ana County water/wastewater improvements, including $10 million for a partner grant program.

  • Requires repayment equal to 100% of GRT-share distributions if construction investment is below $350 million by October 23, 2035, subject to the separate $400 million waiver.

  • Requires quarterly employment reports and withholds State disbursements without current job reporting; requires annual economic-impact data sheets beginning in 2027, with a 10% clawback for failure to complete by April 15.

  • Requires annual performance review beginning June 30, 2026, and permits County termination of assistance by ordinance if requirements are not met.

Benefits & exceptionsHide benefits & exceptions3
  • Distributes 50% of net receipts from eligible County and State general-fund GRT increments generated by taxable construction expenses through October 23, 2035.

  • Waives GRT-share clawback penalties if construction investment reaches $400 million at any time after December 31, 2027; this does not release other clawbacks.

  • Prohibits the County from offsetting internal review or processing costs against disbursement requests or the State increment.

Sources

current law · County project: Project Jupiter data center campus and associated facilities in Santa Teresa
This ordinance authorizes up to $165 billion in taxable industrial revenue bonds for Project Jupiter, including power-generation, battery-storage and microgrid facilities and four anticipated data centers.Doña Ana County Ordinance No. 367-2025 — Project Jupiter industrial revenue bonds

What this means

The package offers major support for data center development, including a 30-year, full property-tax abatement and sharing some gross receipts tax revenue with the project. In return, the companies take on job and investment commitments, reporting duties, and possible repayment penalties, so the benefits are substantial but conditional.

People behind it

  • County party to the agreements responsible for supporting and authorizing the Project Jupiter economic-development measures, including the IRBs and LEDA arrangements.

  • State party to the Project Participation Agreement responsible for administering or coordinating the LEDA GRT Share contributions, reporting, and performance review.

  • Project proposer, through its affiliated development entities, for the hyperscale data-center campus, microgrid, and related economic-development commitments.

Show 5 more peopleShow fewer people
  • Company party to the Project Participation Agreement and an affiliated entity proposing and undertaking the Project.

  • Company party to the Project Participation Agreement and an affiliated entity proposing and undertaking the Project.

  • Company party to the Project Participation Agreement and an affiliated entity proposing and undertaking the Project.

  • Company party to the Project Participation Agreement and an affiliated entity proposing and undertaking the Project.

  • Company party to the Project Participation Agreement and an affiliated entity proposing and undertaking the Project.

Restrictions & requirementsHide restrictions & requirements13
  • Construction and operation are contingent on obtaining permits, industrial revenue bond approval, and related LEDA agreements; the MOU creates no enforceable project rights before definitive agreements are executed. pending approval of permits and industrial revenue bonds

  • The project must complete all environmental reviews required by state and local law, including analyses addressing water use, air quality, noise, stormwater, and overall environmental impacts, before construction begins. Environmental reviews are a required part of the permitting process

  • The project must fund the design, permitting, and construction of required public-water extensions and any force-main extensions needed to connect the site to existing infrastructure. fund the design, permitting and construction

  • The project must fund the design and construction of a roadway extension from the Highway 136 and Highway 9 intersection along the northern site boundary to provide site access. responsible for funding the design and construction of a roadway extension

  • The data center must use an onsite microgrid, including natural-gas generation and large-scale battery storage, and must comply with applicable federal and state air-quality standards; qualified microgrids must obtain all power from net-zero-carbon resources by 2045 under HB93. onsite microgrid

  • Operational potable-water use for the full campus is limited to an average of 20,000 gallons per day, with peak use capped at 60,000 gallons per day, and the project must use a closed-loop cooling system. maximum peak use capped at 60,000 gallons per day

  • The project is subject to a permit-fee payment structure totaling $4.5 million for 2025 through 2028: $500,000 in 2025, $1.5 million in 2026, $1.5 million in 2027, and $1 million in 2028. Total Payments to County

  • The project must make fixed annual PILOT payments of $12 million for 30 years, totaling $360 million, beginning in the first year of data-center operations. fixed annual Payment in Lieu of Tax

  • The project must contribute $50 million through the LEDA GRT Share program for water and wastewater improvements, with the Project Participation Agreement requiring the first $50 million of GRT proceeds to be dedicated to a separate water and wastewater fund before remaining distributions are paid to the companies. dedicate the first fifty million dollars

  • The companies must invest approximately $50 billion by October 23, 2035, create approximately 750 qualifying full-time jobs by December 31, 2031, and continue operating until October 23, 2035 or until $350 million in construction expenses subject to GRT has been spent. capital investments

  • Failure to reach $350 million in construction investment by October 23, 2035 triggers a penalty equal to 100% of the GRT Share Distribution received, unless the specified $400 million investment threshold is reached after December 31, 2027 and the related clawback is waived. penalty equal to 100% of the GRT Share Distribution

  • The companies must submit quarterly employment reports and annual economic-impact data; state contributions cannot be disbursed without current job reporting, and failure to submit the annual data sheet by April 15 subjects the companies to a 10% clawback of all funds received. Failure to complete EIA data sheet by April 15th

  • The project must satisfy an annual performance review by the County or EDD beginning June 30, 2026; if the agreement's requirements are not met, the County may terminate the assistance by ordinance. annual performance review

Benefits & exceptionsHide benefits & exceptions12
  • The County will support Industrial Revenue Bonds for the Project with an aggregate principal amount of up to $165 billion. The bonds may be issued in stages for initial construction and later equipment refreshes, with the County taking record title to the project property upon each issuance. IRBs with a maximum principal amount of $165 billion

  • The County will provide a 100% abatement of qualifying real and personal property taxes for 30 years, offset by fixed annual PILOT payments of $12 million. A full (100%) abatement of real and personal property taxes

  • The County will support obtaining New Mexico non-taxable transaction certificates to provide gross-receipts-tax exemptions for eligible project property. Gross Receipts Tax Deduction

  • The County and State will distribute 50% of specified County and State gross-receipts-tax increments generated by taxable project construction expenses through October 23, 2035. The Companies must provide required tax documentation, and the first $50 million of proceeds must be dedicated to a County water and wastewater fund before later distributions go to the Companies. distribute to the Companies 50% of the net receipts

  • The Project is exempt from the County's standard building permit fees and instead pays the agreed alternative schedule: $500,000 in 2025, $1.5 million in 2026, $1.5 million in 2027, and $1 million in 2028. exempt from standard building permit fees

  • The County will actively facilitate engagement with permitting offices, utilities, and public agencies; assist with permitting; support offsite easements and rights-of-way, including use of eminent domain where legally permissible; and collaborate with state and federal agencies on accelerated review. actively facilitate engagement

  • The Project may fund and construct extensions of public water mains and wastewater force mains needed to serve the site, with the parties considering upsizing facilities to address broader regional needs. fund the design, permitting and construction

  • The Project will fund a roadway extension from the Highway 136 and Highway 9 intersection along the site's northern boundary, providing site access. funding the design and construction of a roadway extension

  • The Project may operate using an onsite microgrid with natural-gas generation, battery storage, and potential renewable-energy integration. The Project pays for the microgrid and energy it uses, and the campus may not affect existing customers' power reliability or costs; systems must meet federal and state air-quality standards and comply with the stated HB93 requirements. power itself with an onsite microgrid

  • The County will not impose special assessments, taxes, fees, or utility rates on the Project that are disproportionate to those imposed on similarly situated developments. Non-Discriminatory Treatment

  • The County will support the Project's applications for state statutory incentives, including tax credits and workforce-training assistance. support Project team applications for state statutory incentives

  • If the Companies reach at least $400 million in total construction investment after December 31, 2027, the County and State will waive clawback penalties related to the gross-receipts-tax share distributions. waive any and all Clawback penalties

Sources

current law · County project: Unincorporated areas, including the Project Jupiter site
This resolution declares the county’s intent to provide LEDA assistance for Project Jupiter, described as a hyperscale AI data-center campus with a collocated microgrid and related facilities.Doña Ana County Resolution No. 2025 — intent to provide LEDA assistance for Project Jupiter

What this means

The measure would strongly encourage Project Jupiter by offering a 30-year property-tax abatement, industrial revenue bonds, and a share of construction tax receipts (100% property-tax abatement). In return, the project must meet investment, job, and other commitments, but these are project-specific conditions rather than broad new limits on data centers.

People behind it

  • Proposed and administers the County’s LEDA assistance, acts as the State’s fiscal agent for disbursements, oversees project compliance, and is the issuer of the proposed industrial revenue bonds.

  • Governing body that adopted the intent resolutions and is responsible for considering and authorizing the LEDA ordinance and industrial revenue bond ordinances.

  • Proposed provider of State LEDA assistance, including the State GRT Share and any State grant.

Show 8 more peopleShow fewer people
  • Project proposer and development undertaking, acting through its affiliated development entities.

  • Series 2025A project proponent for the power-generation, battery-storage, and microgrid facilities; also a Project Jupiter company and CBA party.

  • Series 2025B project proponent for one anticipated data center facility and a Project Jupiter company.

  • Series 2025B project proponent for one anticipated data center facility and a Project Jupiter company.

  • Series 2025B project proponent for one anticipated data center facility and a Project Jupiter company.

  • Series 2025B project proponent for one anticipated data center facility and a Project Jupiter company.

  • Series 2025C project proponent for equipping the data centers; also a Project Jupiter affiliate and guarantor of specified community-benefit payments.

  • Authorized agent for the County and the Series 2025B companies in acquiring project equipment and using Type 9 nontaxable transaction certificates.

Restrictions & requirementsHide restrictions & requirements12
  • Project construction is conditioned on obtaining all required permits, industrial revenue bond approvals, and related LEDA agreements; construction is only expected to begin in Q4 2025 after those approvals. pending approval of permits, industrial revenue bonds (IRBs) and related LEDA agreements

  • The project must comply with applicable county land-use regulations unless the County and the Companies agree otherwise. subject to land use regulation and approval by the County

  • The Companies must submit all environmental analyses required by state and local law, and complete required reviews covering matters such as water use, air quality, noise, stormwater, and overall environmental impacts before construction begins. Environmental reviews are a required part of the permitting process

  • The onsite microgrid must meet or exceed federal and New Mexico air-quality permitting standards, and qualified microgrid power must come from net-zero-carbon resources by 2045 under HB93. by 2045, all power from qualified microgrids must come from net zero carbon resources

  • The full campus's operational potable-water use is limited to an average of 20,000 gallons per day, with a maximum peak use of 60,000 gallons per day. average of 20,000 gallons per day with a maximum peak use capped at 60,000 gallons per day

  • The Companies must fund the design, permitting, and construction of required public-water-main extensions, wastewater force-main extensions, and the roadway extension connecting the site to Highway 136. fund the design, permitting and construction

  • Construction and operation through the IRB structure require County approval of one or more bond ordinances, execution of leases and related bond documents, and public notice before the County may issue the bonds. subject to the approval and authorization by the Governing Body pursuant to the Bond Ordinance or Bond Ordinances

  • The IRB ordinance process requires publication of notice at least two weeks before final consideration, and notices to the County Assessor and taxing entities must be sent at least 30 calendar days before the meeting at which final action is taken. published at least two weeks prior and at least thirty calendar days prior

  • LEDA assistance requires a later County ordinance after normal County review, with notice of intent published at least two weeks before the public meeting; failure or refusal to adopt the ordinance voids benefits under the Act. subject to a review of the Project by the County in the normal course and at least two weeks prior

  • The project must create at least 750 onsite full-time-equivalent jobs and 50 part-time jobs within three years after operations begin, with average annual wages between $75,000 and $100,000; the jobs may not be remote. minimum of 750 new full-time equivalent jobs and 50 part-time jobs

  • The Companies must maintain a local-participation program, including a Doña Ana County First hiring strategy, a project job board, informational sessions, and a local vendor registry. Doña Ana County First hiring strategy

  • The project must make specified community and County payments, including $4.0 million for workforce development, $1.5 million for community initiatives, $250,000 for desalination evaluation, $150,000 for regional connectivity, $1.0 million for habitat restoration, and $4.5 million in County project or permit-fee payments. Supplemental Community Investment Funds are generally due by December 31, 2026, while habitat payments continue through December 31, 2036. the last payment occurring on December 31,2036

Benefits & exceptionsHide benefits & exceptions15
  • The County may issue up to $165 billion in taxable industrial revenue bonds for power generation, battery storage, microgrid facilities, four data centers, and data-center equipment. The bonds may finance project costs and reimburse temporary capital advances, subject to later bond ordinances and related documents. maximum aggregate face amount of the Bonds

  • The County is expected to acquire project property and lease it to the companies, with company lease payments covering bond debt service. The bonds are payable from project revenues and are not County debt or a charge against the County's taxing power. shall not constitute a debt or indebtedness of the County

  • The County agrees to a 100% abatement of qualifying real and personal property taxes for 30 years, offset by fixed annual PILOT payments. full (100%) abatement of real and personal property taxes

  • The project will make fixed annual PILOT payments of $12 million for 30 payments, totaling $360 million, subject to the allocation described in the MOU. Total Payments to County (30 Years = 30 Payments)

  • The County will support obtaining State-issued Type 9 Nontaxable Transaction Certificates for eligible capital equipment and tangible personal property. The companies may use the certificates only for project purchases and must indemnify the County for related taxes or penalties. apply to the Taxation and Revenue Department for Type 9 Nontaxable Transaction Certificates

  • The County and State plan to participate in the LEDA GRT Share program by returning 50% of qualifying State and local gross receipts and compensating taxes from construction expenditures, subject to LEDA approval and project agreements. return of 50% of the gross receipts and compensating taxes

  • The Project will contribute $50 million through the LEDA GRT Share program for drinking-water and wastewater infrastructure intended to support regional water security. contribute $50,000,000 through New Mexico's Local Economic Development Act

  • The Project will fund design, permitting, and construction of required public-water-main extensions from Highway 136 to the site. fund the design, permitting and construction

  • The Project will fund design, permitting, and construction of required wastewater force-main extensions and an onsite lift station, with possible upsizing for regional needs. offsite extension of force main

  • The Project will fund design and construction of a roadway extension from the Highway 136 and Highway 9 intersection along the northern site boundary, or another access route agreed by the parties. responsible for funding the design and construction of a roadway extension

  • The County will facilitate engagement with permitting offices, utilities, and other agencies; assist with permitting procedures; support offsite easements and rights-of-way, including legally permissible eminent-domain assistance; and seek accelerated State and federal reviews. support in securing any required offsite easements or rights-of-way

  • The Project receives an alternative permit-fee structure totaling $4.5 million for 2025 through 2028 and is exempt from standard County building-permit fees, subject to the agreed replacement payments. exempt from standard building permit fees

  • The County will not impose special assessments, taxes, fees, or utility rates on the Project that are disproportionate to those imposed on similarly situated developments. will not impose special assessments, taxes, fees, or utility rates

  • The Project may operate with an onsite microgrid using natural-gas generation, battery storage, and potential renewable-energy integration; the Project pays for the microgrid and its energy, and the agreement states it will not affect existing customers' power reliability or costs. power itself with an onsite microgrid

  • The County will support Project applications for State statutory incentives, tax credits, and workforce-training assistance. support Project team applications for state statutory incentives

Sources

current law · County project: Project Jupiter facilities and site
Project-specific LEDA permit-fee incentive, not a generally applicable building-code change.Doña Ana County Ordinance No. 369-2025 — Project Jupiter permit-fee LEDA assistance

What this means

The ordinance gives Project Jupiter a direct financial benefit by replacing standard building-permit fees with a special payment schedule totaling $4.5 million (reduced fee schedule). It applies to the data center project and adds no new data-center operating restrictions, though the benefit is project-specific and the companies must follow their agreement.

People behind it

  • Named petitioner in the October 2025 challenge to the Project Jupiter ordinances.

  • Named petitioner in the October 2025 challenge to the Project Jupiter ordinances.

Benefits & exceptionsHide benefits & exceptions2
  • Approves project-specific LEDA assistance through a reduced County building-permit fee schedule, with total County payments of $4,500,000.

  • Approves and authorizes execution of the project participation agreement to provide assistance to the companies.