Allamuchy Township

Mixed Data Center Policies

New Jersey requires large data centers to cover much of their electricity costs and offer demand flexibility; reporting and construction rules add paperwork and costs. Tax incentives are available only to qualifying projects, while regulators study possible electricity-cost effects.

Rating and summary from New Jersey statewide as there are no scored current or future laws outside temporary restrictions for Allamuchy Township.

current law · Allamuchy Township
Allamuchy Ordinance 2026-06 adds a definition of data center and provides that data centers are specifically prohibited in all zones in the township.Allamuchy Township Ordinance 2026-06 (2026)

People behind it

  • Municipal Clerk named in adoption notice.

  • Mayor named in adoption notice.

Restrictions & requirementsHide restrictions & requirements2
  • Adds §190-106C: Data centers are specifically prohibited in all zones.

  • Definition covers facilities used primarily for the storage, management, and processing of digital data and their supporting equipment.