The Data Center Divide

Clark County

Pro-Data Center Policies

Clark County’s enacted ordinance is described as a proposal that would ease data-center expansion on one 51.5-acre site, allowing warehouses and waiving some standards, subject to staff conditions.

current law · County project: The NV LAS DEC data center with electric substation at Maule and Jones, and the NV LAS NAP 14-16/NV LAS DEC data center complex north of Badura Avenue and east of Jones Boulevard within Enterprise
Considers adopting a development agreement with NV LAS NAP 14-16 LLC and NV LAS DEC, LLC for a data center complex on 51.5 acres in Enterprise.Clark County, Nevada Ordinance No. 23-900352 (2023)

What this means

The proposal would make it easier to expand a data center on a specific 51.5-acre site by allowing data center warehouses and waiving several development standards. Staff conditions still apply, so the benefit is meaningful but limited.

Restrictions & requirementsHide restrictions & requirements1
  • The data center warehouse project required waivers of development standards and design reviews for signage and the warehouses, with approval subject to staff conditions.

Benefits & exceptionsHide benefits & exceptions7
  • Approved, subject to staff conditions, a waiver allowing outside storage for the data-center project. Waiver for outside storage%20outside%20storage)

  • Approved, subject to staff conditions, a waiver allowing alternative building design standards. Alternative building design standards%20alternative%20building%20design%20standards)

  • Approved, subject to staff conditions, a waiver allowing alternative lighting standards. Waiver for lighting%20lighting)

  • Approved, subject to staff conditions, a waiver allowing alternative trash enclosures. Alternative trash enclosures%20alternative%20trash%20enclosures)

  • Approved, subject to staff conditions, a waiver eliminating parking-lot landscaping requirements. Eliminate parking lot landscaping%20eliminate%20parking%20lot%20landscaping)

  • Approved, subject to staff conditions, design reviews for signage and data-center warehouses. Design reviews for signage and data center warehouses%20signage%3B%20and%202)%20data%20center%20warehouses)

  • Approved, subject to staff conditions, a tentative map creating one industrial lot on the 51.5-acre site. Tentative map consisting of 1 industrial lot

Sources

Specific to Clark County only.

pending · County project: Unincorporated Enterprise
Proposes a site-specific development agreement for NV LAS DEC’s 30-acre data center and electric substation in Enterprise, with zoning changes and waivers from certain development standards.Clark County ORD-23-900338 (2023)

What this means

The measure would help a specific 30-acre data center project move forward by adopting a development agreement for the facility and its electric substation (development agreement for a data center with electric substation). Related zoning and design applications were approved, but this is a project-specific approval, not a general incentive or protection for data centers (approved per staff conditions).

People behind it

  • Applicant and party to the proposed Development Agreement for the 30-acre data center and electric substation.

  • Responsible body for introducing and conducting the public hearing on the proposed ordinance.

Restrictions & requirementsHide restrictions & requirements5
  • The project requires a zone change for 1.3 acres from Rural Estates Residential, including the AE-60 overlay, to Designed Manufacturing zoning.

  • The project requires use permits for the electric substation and for eliminating the required trash enclosure.

  • The project requires waivers of development standards for exterior accent colors, horizontal rooflines, wall height, monotonous block walls, ground-mounted up-lighting, street landscaping without trees, signage, and modified driveway design standards.

  • The project requires design reviews for modifications to the previously approved data center, the electric substation, signage, and finished grade across the 30-acre site.

  • The project requires consideration and adoption of a development agreement through a county ordinance and public hearing.

Benefits & exceptionsHide benefits & exceptions6
  • Rezoning: The measure would reclassify 1.3 acres from Rural Estates Residential zoning, including the AE-60 airport-overlay portion, to Designed Manufacturing zoning, including the corresponding AE-60 designation, supporting the data-center project on the 30-acre site. reclassify 1.3 acres

  • Electric-substation authorization: The measure includes a use permit for an electric substation, providing project-specific approval for power infrastructure needed by the data center. electric substation%20eliminate%20trash%20enclosure%3B%20and%202)%20electric%20substation)

  • Development-standard waivers: The measure would waive or modify requirements for exterior accent colors, roofline articulation, wall height, block-wall design, ground-mounted uplighting, street landscaping, signage, and driveway design, reducing site-design constraints on the data center and substation. WAIVERS OF DEVELOPMENT STANDARDS

  • Project design approvals: The measure includes design reviews for modifications to a previously approved data center, a communications tower, the electric substation, signage, and finished grade, allowing the project to proceed through a consolidated project-specific review. modifications to a previously approved data center

  • Site and access-rights changes: The measure includes vacation of specified easements and portions of Bronco Street and Pama Lane, clearing identified private-site and right-of-way interests for the data-center development. VACATE AND ABANDON easements

  • Industrial-lot subdivision approval: The associated tentative map would create one industrial lot and common lots on the 30-acre site, providing the approved parcel configuration for the data-center project. TENTATIVE MAP consisting of 1 industrial lot

Sources

pending · County project: Data center complex generally located north of Badura Avenue and east of Jones Boulevard within Enterprise
Considers approving a development agreement for a 51.5-acre data center complex in the Enterprise area.Clark County ORD-23-900352 (2023)

People behind it

  • Party to the proposed Development Agreement for the 51.5-acre data center complex.

  • Party to the proposed Development Agreement for the 51.5-acre data center complex.

Benefits & exceptionsHide benefits & exceptions3
  • Establishes a development agreement with NV LAS NAP 14-16 LLC and NV LAS DEC, LLC for development of a data center complex on approximately 51.5 acres in Enterprise.

  • Provides vested development rights during the agreement term, limiting the County’s ability to apply later zoning or land-use changes that would conflict with the approved project, subject to the agreement’s conditions and applicable health and safety requirements.

  • Sets the development agreement’s approved terms and conditions as the framework for reviewing subsequent development applications, including site, building, and infrastructure permits for the data center complex.

Sources

Data provided by Regbase · Cookie preferences · Report missing data