Warsaw Township
Mixed Data Center Policies
Minnesota keeps tax breaks for qualifying data-center equipment and software, but electricity is taxable, adding operating costs. Qualifying large centers also face annual fees and labor and building conditions; projects meeting general thresholds may require environmental review.
Rating and summary from Minnesota statewide as there are no scored current or future laws outside temporary restrictions for Warsaw Township.
current law · Warsaw TownshipProhibits data centers unless Warsaw Township amends its zoning rules to expressly allow them.Warsaw Township Zoning Map and Zoning Regulations
People behind it
- Warsaw Township Board of Supervisors (Town Board)
Ordained and adopted the zoning ordinance.
- Warsaw Township
Responsible for administering and enforcing the ordinance.
- Zoning Administrator
Responsible for administering and enforcing the ordinance, including processing permits and issuing violation notices.
Restrictions & requirementsHide restrictions & requirements6
A use not listed as allowed in the applicable zoning district is not allowed. If a data center is not allowed in the applicable district, an ordinance or zoning-map amendment may be required before it can proceed. A use not listed as being allowed
An amendment to allow a use or change zoning requires a Planning Commission public hearing, at least 10 days’ published notice, and a final Town Board decision. After denial, a similar property-owner amendment application generally cannot be considered for one year, unless the Planning Commission allows reconsideration based on new evidence or changed circumstances. At least 10 days’ published notice
Construction, alteration, expansion, or placement of a building or structure with an anticipated cost exceeding $1,000 requires both a Township building permit and a permit from the County Building Official. Cost exceeding $1,000
A building-permit application requires a site plan showing existing and proposed structures and specified site features. For a project costing more than $25,000 or involving at least 2,000 square feet of improved area, the site plan must be prepared by a Minnesota-licensed surveyor and building corners staked, unless the Town Board approves an alternative. Prepared by a Minnesota licensed surveyor
Applicants must pay applicable fees and may have to deposit funds and reimburse the Township for processing costs, including engineering, planning, legal, administrative, and inspection expenses. Permits cannot be issued and construction or development cannot begin until fees and expenses are paid in full; unpaid costs may result in a lien or other collection action. All expenses incurred by the Township shall be immediately payable
Township approval does not replace permits or permissions required by other governments, and projects must comply with both Township and County regulations. Complies with both this Ordinance and the County’s regulations
Benefits & exceptionsHide benefits & exceptions1
A data-center use or structure that lawfully existed when the ordinance took effect may continue despite being nonconforming, and normal maintenance is allowed. Generally, it cannot expand; protection ends if a nonconforming use is discontinued for one year, and a structure destroyed beyond 50% of its assessed fair market value must conform if rebuilt. Lawfully existing nonconforming uses and structures may be continued.