Freeborn County
This restriction takes precedence while in effect. The rating below excludes temporary restrictions.
Mixed Data Center Policies
Freeborn County’s temporary moratorium blocks data-center permits in unincorporated areas through August 19, 2027, delaying covered projects but not permanently banning them. It does not cover incorporated municipalities.
Rating from Minnesota statewide as there are no scored current or future laws outside temporary restrictions for Freeborn County.
Specific to Freeborn County only.
current law · Unincorporated areasExtends the moratorium on accepting, processing, or approving data center permits in unincorporated Freeborn County through August 19, 2027.Freeborn County Temporary Interim Zoning Ordinance No. 25-244 (2025)
What this means
The measure extends a temporary moratorium on data-center permits in Freeborn County’s unincorporated areas through August 19, 2027, [continuing the original restrictions](https://freeborncomn.api.civicclerk.com/v1/Meetings/GetMeetingFileStream(fileId=915,plainText=false#:~:text=extends%20the%20moratorium%20in%20Ordinance%20No.%2025-244%20for%20one%20year). That blocks covered projects from moving through the county’s permit process during the extension, a substantial temporary barrier, though it is not a permanent ban.
Timing
- Ends
- Aug 19, 2027
The data-center moratorium was extended for one year through this date, continuing the restrictions in the original ordinance. The extension is authorized for up to one additional year while the County conducts, or in good faith intends to conduct, studies to adopt or amend land-use controls; County staff are directed to complete the study and publish the resolution.
People behind it
- Steve Rick
Submitted agenda requests for the Decision Points and Coffee Connections grant acceptances, the vacant Probation Officer position, Sara Pardoe’s collaborative appointment, and the preliminary 2027 tax levy.
- Sara Pardoe
Submitted the agenda request to fill the vacant Probation Officer position.
- Sue Yost
Submitted the Public Health agenda requests for the Medica agreement, Oakwood Sober Living funding, and Amber Converse’s WIC services agreement.
Show 20 more peopleShow fewer people
- Amy Conner
Submitted the Auditor-Treasurer agenda requests concerning the erroneous forfeiture and the CD 68 hearing.
- Lisa Peterson
Submitted the Public Works agenda requests for the final payments and five-year bridge plan.
- Suzanne Nerison
Submitted the Human Services agenda request to fill the vacant case-manager position.
- Ryan Shea
Submitted the Sheriff’s Office agenda requests to accept the teddy-bear donation and fill a vacant patrol deputy position.
- Trevor Bordelon
Prepared the Planning Commission report and proposed amendment materials for the Energy Storage Systems ordinance.
- Amanda Johnson
Submitted and signed Oakwood Sober Living’s application for the Supportive Housing Pilot funding.
- Commissioner Eckstrom
Introduced the Steele conditional-use permit, data-center moratorium extension, forfeiture cancellation, Avenu tax-software ratification, and MCAPS contract renewal measures.
- Commissioner Severson
Introduced measures concerning the vacant Human Services position, the vacant Probation Officer position, the Medica agreement, final payment for CP 026-M-002, the Community Health Worker grant, the freight grant application, and the Crime Victims Crisis Center grant.
- Commissioner Kaasa
Introduced measures concerning the Broadway Avenue no-parking zone, medical examiner agreement, Sara Pardoe’s appointment, final payment for CP 026-M-004, the initial data-center and energy-storage moratoria, the Family Home Visiting grant, and the local emergency declaration.
- Commissioner Shoff
Introduced the Coffee Connections grant acceptance and the motion requesting quarterly Shared Resources Committee meetings.
- State of Minnesota
Jointly petitioned with the Shell Rock River Watershed District for the County Ditch 55 modification, impoundment, and partial abandonment.
- Shell Rock River Watershed District
Jointly petitioned with the State of Minnesota for the County Ditch 55 modification, impoundment, and partial abandonment.
- James and Mary Steele
Applied for the conditional-use permit for a stand-alone accessory building.
- Ulland Brothers, Inc.
Applied for the conditional-use permit for sand and gravel extraction on property owned by Houg Brothers LLC.
- Freeborn County Planning Commission
Directed County staff to draft the Energy Storage Systems ordinance and reviewed its proposed amendments.
- Oakwood Sober Living
Proposed the Supportive Housing Pilot for which the County was asked to award opioid settlement funds.
- County Administrator
Was assigned authority to design, implement, and manage the Employee Recognition Program policy.
- City of Albert Lea
Named joint-resolution party urging completion of the Blazing Star State Trail.
- City of Hayward
Named joint-resolution party urging completion of the Blazing Star State Trail.
- Freeborn County
Named joint-resolution party urging completion of the Blazing Star State Trail.
Restrictions & requirementsHide restrictions & requirements1
A temporary moratorium bars accepting, processing, or approving permits for data centers in unincorporated Freeborn County. It was extended through August 19, 2027, with the original restrictions continuing during the extension (moratorium on the acceptance, processing, and approval of permits).
Sources
current law · Unincorporated areasExtends the moratorium on accepting, processing, or approving data center permits in unincorporated Freeborn County through August 19, 2027.Freeborn County Resolution No. 26-224 (2026)
What this means
The measure would extend a moratorium that restricts accepting, processing, and approving data-center permits in [unincorporated Freeborn County](https://freeborncomn.api.civicclerk.com/v1/Meetings/GetMeetingFileStream(fileId=915,plainText=false#:~:text=instituted%20a%2012-month%20temporary%20moratorium%20on%20the%20acceptance%2C%20processing%2C%20and%20approval%20of%20permits%20for%20Data%20Centers) through August 19, 2027. That blocks new projects during the moratorium and causes substantial delay, though the restriction is temporary and does not cover incorporated municipalities.
Timing
- Ends
- Aug 19, 2027
Expressly extends the moratorium for one year, through August 19, 2027; this is a stated end date, not a calculated expiration.
People behind it
- Commissioner Eckstrom
Offers the resolution; first name not established by the reviewed minutes.
- Commissioner Severson
Seconds the resolution.
Restrictions & requirementsHide restrictions & requirements2
Continues the pause on acceptance, processing, and approval of permits for Data Centers in unincorporated Freeborn County.
Extends the moratorium through August 19, 2027, continuing all restrictions in the original ordinance.
Benefits & exceptionsHide benefits & exceptions1
None identified in the reviewed resolution; its operative clause extends the moratorium.