Washington Township
Mixed Data Center Policies
Michigan offers equipment tax breaks to qualifying data centers, but some require major investment, job, water, and clean-energy commitments. Large electricity users also face separate rates, fees, and cost reviews; some must accept long contracts and minimum payments.
Rating and summary from Michigan statewide as there are no scored current or future laws outside temporary restrictions for Washington Township.
pending · Washington TownshipDiscusses exploring a moratorium on data centers, but does not adopt one.Washington Township Battery Storage/Data Center Moratorium
Timing
The August 20, 2026 meeting minutes state that the board approved a moratorium for BESS, but the sources do not specify an expiration date or ending condition.
People behind it
- Eric Whitford
Moved to approve the moratorium for battery energy storage systems (BESS).
- Kevin Whaley
Seconded the motion to approve the BESS moratorium.
Sources
Data provided by Regbase · Cookie preferences · Report missing data