City of Utica
This restriction takes precedence while in effect. The rating below excludes temporary restrictions.
Mixed Data Center Policies
Utica has enacted a temporary 180-day pause on building data centers, which may delay or prevent new projects during that period; it is not a permanent ban.
Rating from Michigan statewide as there are no scored current or future laws outside temporary restrictions for City of Utica.
current law · City of UticaExtends Utica’s temporary moratorium on data centers for another 180 days, pausing data-center construction in the city during that period.City of Utica data-center moratorium (2026)
What this means
The measure would extend a 180-day pause on building data centers in Utica, delaying or preventing new projects during that period (“moratorium on the building of data centers”). This is a major temporary barrier, though it is not a permanent ban.
Timing
- Ends
- 180 days after adoption of the extension
The February 10, 2026 resolution established a 180-day moratorium, and the July 14, 2026 resolution extended the data-storage moratorium for an additional 180 days. The sources do not state an explicit calendar expiration date.
People behind it
- Brad O’Donnell
Moved the resolutions approving and extending the 180-day moratorium on building data centers in the City of Utica.
- Faith Terenzi
Seconded the resolutions approving and extending the 180-day moratorium on building data centers in the City of Utica.
Restrictions & requirementsHide restrictions & requirements1
The City of Utica imposed a moratorium on building data centers within the city for 180 days and later extended the data-storage moratorium for an additional 180 days.