Mason Township

This restriction takes precedence while in effect. The rating below excludes temporary restrictions.

Neutral Data Center Policies

Mason Township’s enacted ordinance pauses acceptance and processing of data center applications for up to 12 months, though the pause may end sooner if new rules take effect. It does not directly ban existing data centers from operating.

Rating from Cass County as there are no scored current or future laws outside temporary restrictions for Mason Township.

current law · Mason Township
Temporarily prohibits Mason Township from accepting or processing data center applications for up to 12 months, unless new township or state rules take effect sooner.Mason Township Ordinance 2026-01 (2026)

What this means

The ordinance would pause acceptance and processing of data center applications for up to 12 months, making new development and expansion applications wait while the township studies possible rules (“temporary moratorium on the acceptance and/or processing”). It may end sooner if new township or state rules take effect, and the text does not impose a direct ban on operating existing data centers.

Timing

Ends
Twelve (12) months from the effective date of the ordinance, or when amended or new Township ordinances or State regulations addressing Data Centers become effective, whichever occurs first.

The Township Board may extend the moratorium by resolution before it expires to allow time to complete ordinance or regulatory amendments.

People behind it

  • Moved adoption of the ordinance establishing the temporary moratorium on data centers.

  • Seconded the motion to adopt the temporary data-center moratorium.

  • Adopted and administered the temporary moratorium on accepting or processing data-center applications.

Show 4 more peopleShow fewer people
  • Moved for the township attorney to draft a temporary data-center moratorium.

  • Seconded the motion for the township attorney to draft the temporary data-center moratorium.

  • Proposed development of the moratorium and is responsible for working with the township attorney on related zoning ordinances.

  • Responsible for drafting the temporary moratorium and related data-center zoning ordinances.

Restrictions & requirementsHide restrictions & requirements3
  • A temporary moratorium prohibits the Township from accepting or processing any applications for data centers.

  • The moratorium lasts 12 months from the ordinance’s effective date, unless new or amended Township ordinances or state regulations addressing data centers take effect earlier.

  • Before the moratorium expires, the Township Board may extend it by resolution to allow more time to complete ordinance or regulatory changes.