Mixed Data Center Policies

Lyon Charter Township has enacted a temporary pause on data-center permits and approvals through September 8, 2026, while it studies zoning and related issues.

Rating from Michigan statewide as there are no scored current or future laws outside temporary restrictions for Lyon Charter Township.

current law · Charter Township of Lyon
Pauses Lyon Township approvals and permits for data centers and other large land uses through September 8, 2026, while the township reviews zoning and related issues.Lyon Township Data Center Moratorium (2026)

What this means

The measure would temporarily pause approvals and permits for data processing centers until September 8, 2026, creating a substantial delay for new projects or expansions. The pause is limited in time, but the Township also plans to study zoning and other issues before it ends (moratorium through September 8, 2026).

Timing

Ends
Sep 8, 2026

Resolution No. 2026-07 imposes a moratorium on issuing approvals and permits for data processing centers and extends it through 2026-09-08.

Restrictions & requirementsHide restrictions & requirements1
  • A moratorium prohibits the issuance of approvals and permits for data processing centers and large land users through September 8, 2026. The measure also directs a review of related zoning, safety, environmental, noise, construction, decommissioning, and other issues before approvals resume. Moratorium on the issuance of approvals and permits

Benefits & exceptionsHide benefits & exceptions1
  • Data centers are permitted uses in Lyon Township’s industrial district, allowing them to be proposed and approved on industrially zoned property, subject to applicable review and conditions.

Sources

Data provided by Regbase · Cookie preferences · Report missing data