The Data Center Divide

Big Rapids Charter Township

This restriction takes precedence while in effect. The rating below excludes temporary restrictions.

Mixed Data Center Policies

Big Rapids charter township’s enacted ordinance pauses data-center permits, approvals, construction, and related reviews for one year; extensions of up to six months may continue the pause until regulations are adopted.

Rating from Michigan statewide as there are no scored current or future laws outside temporary restrictions for Big Rapids Charter Township.

current law · Big Rapids Charter Township
Prohibits Big Rapids Charter Township from accepting or acting on data center proposals for one year, unless it adopts data-center regulations sooner.Big Rapids Charter Township Data Center Temporary Moratorium Ordinance

What this means

The measure would pause data-center permitting, approvals, construction, and related review in Big Rapids Township for one year, making new projects and expansions substantially harder during that period (“temporary moratorium” for one year). The pause could be extended in periods of six months or less until data-center regulations are adopted, so its practical effect is a major delay rather than a permanent ban.

Timing

Ends
One year after passage and publication, or earlier upon the Township’s implementation of regulations governing Data Centers

The Township may extend the moratorium by resolution for periods of six months or less. If an extension exceeds 12 months, a landowner may apply for a waiver upon demonstrating immediate and irreparable harm.

People behind it

  • Township Board member who offered the moratorium ordinance

  • Township Board member who supported the offered moratorium ordinance

  • Legislative body that adopted the moratorium ordinance

Show 2 more peopleShow fewer people
  • Township Supervisor who called the special meeting and signed the adopted ordinance

  • Township Clerk who certified the adopted measure

Restrictions & requirementsHide restrictions & requirements3
  • Imposes a temporary one-year moratorium on permitting, consideration, approval, location, erection, construction, review, and installation of all data centers in Big Rapids Charter Township, including like operations and associated infrastructure such as cooling systems, generators, water facilities, battery storage, and utility substations.

  • Allows the Township to extend the moratorium by resolution for periods of six months or less, until data-center regulations are adopted.

  • For an extension lasting more than 12 months, a landowner must submit a written waiver request, attend a public hearing, and prove immediate and irreparable harm; any waiver may be limited to what is necessary to avoid that harm.

Benefits & exceptionsHide benefits & exceptions3
  • The moratorium lasts for one year or ends earlier when the Township adopts regulations governing data centers, allowing permitting and development to resume once either condition occurs.

  • Any extension must be approved by resolution and may last no more than six months at a time, limiting the duration of additional restrictions.

  • If the Township extends the moratorium beyond 12 months, a landowner may apply in writing for a waiver by showing immediate and irreparable harm at a public hearing. The Township Board may grant a waiver to the extent necessary to prevent that harm.