City of Somerville

Anti-Data Center Policies

Somerville allows data centers only in the Commercial Industry district, where they require a special permit; they are not permitted in other listed districts. Review considers visual impacts and employment opportunities.

current law · City of Somerville
Restricts data centers to the Commercial Industry district by special permit, with reviewers considering their visual impacts and contribution to local jobs.Somerville Zoning Ordinance § 9.2.8.b and Table 9.1.1 (Ord. 2024-14)

What this means

Data centers would be allowed only in the Commercial Industry district, and there they would need a special permit; the table marks them not permitted in the other listed districts (Data Center). The permit review must consider visual impacts and employment opportunities, creating a meaningful hurdle, though not an outright ban (data center review criteria).

Restrictions & requirementsHide restrictions & requirements6
  • Data centers are not permitted in NR, UR, MR3, MR4, MR5, MR6, HR, FAB, R&D, CC, CB, or CIV districts. They are allowed only in the CI district, where a special permit is required. The table lists data centers as requiring a special permit in CI.

  • A CI data center needs a special permit before it can proceed. In deciding whether to grant one, the review board considers the general special-permit criteria and, specifically, mitigation of aesthetic impacts from security measures or limits on views into the building, and the use’s contribution to local employment opportunities. Data-center special-permit criteria.

  • The special-permit process for a use requires a pre-submittal meeting and neighborhood meeting before the application is submitted, followed by application review, public notice, and a public hearing. Required special-permit procedures.

  • A building permit or certificate of occupancy cannot be issued for development requiring a special permit until the permit has been granted. Permit prerequisite.

  • A development-review application is not complete until required fees are paid, including costs the City incurs for public notice. Application fee requirement.

  • A special permit is generally valid for three years from the date the decision is filed with the City Clerk, excluding time awaiting an appeal decision. The review board may shorten that period; an extension requires a finding that demonstrated hardship prevented use of the permit rights. Special-permit duration and extension.

Benefits & exceptionsHide benefits & exceptions1
  • A data center may be established in the Commercial Industry (CI) district with a special permit; the table lists it as not permitted in the other districts shown. The table lists Data Center as SP in CI.