City of Randolph Town
Mixed Data Center Policies
Massachusetts requires covered data-center projects above 25 megawatts to meet community-benefit and environmental conditions for permits, while qualifying large projects may receive 20-year tax exemptions. The exemptions have investment, size, and job requirements, and applications are not currently being accepted.
Rating and summary from Massachusetts statewide as there are no scored current or future laws outside temporary restrictions for City of Randolph Town.
pending · Town of RandolphProhibits data centers in every zoning district in Randolph and defines which facilities count as data centers.Randolph Council Order 2026-061 — Proposed Data Center Zoning Amendment
What this means
If enacted, it would ban operating data centers in every zoning district, effectively preventing their development and expansion too. The definition covers facilities where more than 25% of floor area serves data-center functions or where that is the facility’s primary purpose (data centers are prohibited in all zoning districts).
People behind it
- Planning Board
Identified as the introducer of the data center zoning amendment in Council Order 2026-061; the Board recommended the prohibition to the Town Council.
- Mrs. Tyler
Prepared the draft ordinance prohibiting data centers that the Planning Board reviewed.
Restrictions & requirementsHide restrictions & requirements1
Prohibits operating any data center in every Randolph zoning district. The ban covers facilities primarily designed or used for servers and related infrastructure, including facilities where more than 25% of gross floor area is devoted to that equipment, or where the Building Commissioner or designee determines that housing and operating servers is the facility’s primary purpose, regardless of floor area.
Sources
pending · Town of RandolphProposes prohibiting data centers in Randolph, but the Planning Board only asked staff to draft a ban; no prohibition was adopted in these minutes.Randolph Draft Zoning Ordinance § 9.12 — Data Centers
What this means
The Board asked staff to draft zoning language that would prohibit data centers, which would prevent building or operating them in Randolph if enacted. Although an earlier draft would have allowed some small facilities with permits, the meeting’s stated direction was a ban.
People behind it
- Michelle Tyler
Planning Director who began drafting the data center zoning language and was asked to prepare proposed language prohibiting data centers for the Planning Board’s review.
Restrictions & requirementsHide restrictions & requirements11
Tier I data centers, defined as having a maximum projected electrical demand of 2 MW or less, are limited to special-permit review in the BRHD, GBHD, and ID districts. The use table bars Tier II facilities (over 2 MW through 10 MW) and Tier III facilities (over 10 MW) in all listed districts. The use table lists the permitted districts and tiers
An allowed data center requires a Special Permit from the Planning Board and must undergo Article XI Site Plan Review as well as the ordinance’s additional performance review. Data Centers shall be permitted only by Special Permit
Applicants must document maximum electrical demand at full build-out, load profiles, phasing, and available electric capacity; identify needed infrastructure upgrades; and may be subject to an approved maximum-demand limit and compliance monitoring. The applicant shall submit an estimate of maximum electrical demand
Applicants must estimate average and peak daily water use, provide DPW documentation that the system can accommodate it, and identify cooling technology and efficiency measures. Potable-water evaporative cooling as the primary method is strongly discouraged and requires a showing that no practicable lower-water alternative exists. Cooling systems shall be designed to minimize the use of potable water
Continuous operational noise is capped at 50 dBA from 7 a.m. to 10 p.m. and 45 dBA from 10 p.m. to 7 a.m., measured at the specified compliance point. The Board may require noise studies and post-construction monitoring; generator testing is limited to Board-approved days and hours, with emergency operation during outages exempt. Continuous operational sound shall not exceed
Applicants must identify backup generators’ number, size, fuel, and location. Generators are limited to emergency operation and scheduled testing, subject to applicable codes, and the facility must demonstrate compliance with state and federal emissions standards. Backup generators shall be limited to emergency operation
The facility must meet applicable dimensional rules and be designed to limit visual and operational impacts; mechanical equipment, generators, and substations must be screened, and exterior lighting must prevent spillover. Applicants must also show the facility will not unduly burden municipal services and infrastructure, and estimate the cost and identify responsibility for any needed mitigation or capital improvements. The applicant shall demonstrate that the proposed facility will not create an undue burden
The Board may impose operating safeguards, including maximum electrical-load limits, water-use caps, noise monitoring or reporting, generator-testing restrictions, and phasing tied to demonstrated infrastructure capacity. The Planning Board may impose conditions necessary
The permit requires operations reporting on a set schedule: monthly during months 1–3, twice during months 4–12, and annually from year 2 onward. Reports may include electricity demand, water use, compliance with limits, relevant discharges, and operational changes; the Board may reduce reporting frequency after sustained compliance. Startup Monitoring Months 1–3 Monthly
A data-center Special Permit lasts five years and must be renewed for continued operation. The renewal application is due at least 90 days before expiration and must document ongoing compliance and any operational or infrastructure changes; failure to apply on time causes the permit to lapse. A Special Permit issued for a Data Center shall be valid for a period of five years
Any increase beyond the permitted electrical-demand threshold requires a Special Permit modification. The permit binds successors and operators, and a new owner or operator must give written notice before a change; the draft leaves the required notice period unspecified. Any increase in approved electrical demand
Benefits & exceptionsHide benefits & exceptions5
Tier I data centers with a maximum projected electrical demand of 2 MW or less may seek a Planning Board special permit in the BRHD, GBHD, or ID districts. They must also undergo site plan review and meet the ordinance’s performance standards. Tier I – Low-Impact Data Center
An approved data center may seek renewal to continue operating after its five-year special permit term. Renewal requires a timely application and review; the Board may renew the permit unchanged, modify conditions, or require a new application for substantial changes. Renewal Required
A special permit runs with the land and binds successors, assigns, and operators; a change in ownership or operator does not end the permit obligations. The new operator must give advance written notice, with the notice period left unspecified in the draft. shall run with the land
A data center may increase its approved electrical demand by seeking a special permit modification; exceeding the permitted megawatt threshold requires that modification. shall require modification
The Planning Board may reduce operations-reporting frequency if it finds that the facility has demonstrated sustained compliance with its approved operational limits. may modify the reporting frequency