current law · City of New Bedford
Defines data centers as a land use, permits them in the Mixed Use Business and industrial districts, prohibits them in residential and transit-oriented districts, and requires site-plan review to address visual impacts from security measures.New Bedford Zoning Ordinance, Chapter 9: Comprehensive Zoning — Data Center Provisions

What this means

Data centers are permitted in several business and industrial districts, but larger new or expanded projects can require site plan review, and applicants must address visual effects from security measures. These are modest added requirements, not a ban or a data-center-specific special permit, so the overall effect is slightly restrictive (data centers are listed as permitted uses; site plan review thresholds).

Timing

Ends
through 2018-09-30 or until the City adopts a zoning ordinance relating to marijuana establishments, whichever occurs first

The moratorium applies to non-medical marijuana establishments and related uses. It ends on the earlier of the stated date or adoption of the zoning ordinance, so it may have ended before 2018-09-30. The moratorium shall be in effect through September 30, 2018.

People behind it

  • The ordinance assigns administration to the Inspector of Buildings (“This ordinance shall be administered by the Inspector of Buildings”).

Restrictions & requirementsHide restrictions & requirements5
  • Data centers are not permitted in every zoning district: the use table lists them as permitted in the Mixed Use Business and Industrial A, B, C, and Waterfront Industrial districts, and marks them prohibited in other listed districts. The table identifies “Data Center” by district.

  • New or expanded commercial or industrial data-center uses may require site plan review. Administrative review applies to projects of 2,000–5,000 square feet with no more than five additional parking spaces, and to smaller projects that add a curb cut or substantially affect internal circulation; Planning Board review applies above 5,000 square feet or when more than five additional parking spaces are required. The thresholds distinguish administrative and Planning Board review.

  • During site plan review, an applicant must address negative aesthetic impacts that may result from data-center security measures and limits on visibility into the building at ground level. The data-center standard requires mitigation.

  • Site plan approval lapses if substantial use under the approved plans has not begun within three years of final approval, unless the Planning Board extends it for good cause upon a timely written request. Site plan approval shall lapse after three years.

  • A data center cannot deviate from an approved site plan without a modification; City Planning determines whether the modified plan must return for further review. No deviation from an approved site plan.

Benefits & exceptionsHide benefits & exceptions4
  • Data centers are permitted by right in the Mixed Use Business and Industrial A, B, C, and Waterfront Industrial districts; they are prohibited in the other districts shown in the use table. The Data Center use-table row identifies where the use is permitted.

  • Some new or expanded commercial or industrial projects can receive administrative rather than Planning Board site-plan review: projects between 2,000 and 5,000 square feet with no more than five additional parking spaces, or projects under 2,000 square feet that do not add a curb cut or driveway or substantially affect internal circulation. Projects over 5,000 square feet or requiring more than five additional spaces require Planning Board review. The site-plan review thresholds apply to new or expanded industrial or commercial uses.

  • A lawfully existing data-center use may continue despite zoning rules that would otherwise prohibit it, as long as the use or structure is not modified without authorization. The continuation rule for prior lawful uses provides this protection, subject to those limits.

  • A building or special permit is generally protected from later zoning amendments if the authorized use or construction begins within six months of permit issuance; construction must also continue to completion as continuously and expeditiously as reasonable. The amendment-conformance provision sets these conditions.

Sources

pending · City of New Bedford
Proposes defining data centers and classifying their land use under New Bedford’s zoning ordinance.New Bedford City Council proposed data center prohibition / Chapter 9 amendment (2026)