Loading map…
Regbase

The Data Center Divide

Talbot County

This restriction takes precedence while in effect. The rating below excludes temporary restrictions.

Neutral Data Center Policies

Talbot County’s enacted measure pauses approval of new and pending data-center applications and permits for 12 months, with a possible 12-month extension. It does not expressly halt existing operations.

Rating from Maryland statewide as there are no scored current or future laws outside temporary restrictions for Talbot County.

Specific to Talbot County only.

current law · Unincorporated areas
Prohibits Talbot County from reviewing or approving new or pending data center applications and permits for 12 months while it develops regulations.Talbot County Resolution No. 395 (2026)

What this means

The measure would pause approval of data center applications and permits for 12 months, including pending applications, making new construction and expansion substantially harder during that time. It could be extended by up to another 12 months, but it does not expressly shut down data centers that are already operating.

Timing

Ends
twelve (12) months after adoption

The County Council may extend the moratorium for up to two additional six-month periods as it deems necessary to protect public health, safety, and welfare and further the resolution’s purposes.

People behind it

  • Introduced Resolution 395 and Bills 1653 and 1654 and Resolutions 396, 397, and 398.

  • Introduced Resolution 395 and Bills 1653 and 1654 and Resolutions 396, 397, and 398.

  • Introduced Resolution 395 and Bills 1653 and 1654 and Resolutions 396, 397, and 398; requested Bill 1653.

Show 7 more peopleShow fewer people
  • Introduced Bills 1653 and 1654 and Resolutions 396, 397, and 398; requested Bill 1654.

  • Introduced Bills 1653 and 1654 and Resolutions 396, 397, and 398.

  • Introduced Resolutions 396–398 and Bills 1653 and 1654.

  • Filed the application underlying Resolution 396 to reclassify a property's water and sewer priority status.

  • Filed the application underlying Resolution 397 to reclassify a property's water and sewer priority status.

  • Designated as the Community Reinvestment and Repair Commission to guide local use of CRRF funding.

  • Tasked with administering the Talbot County Community Repair and Reinvestment Fund.

Restrictions & requirementsHide restrictions & requirements2
  • For 12 months from its adoption on September 8, 2026, the County may not process, review, or approve applications, site plans, permits, or other authorizations for locating, constructing, or operating data centers. The moratorium covers pending and later-filed applications, including zoning text amendments and zoning, occupancy, and building approvals. It does not cover equipment accessory and subordinate to a lawful principal use on the same property that serves only that use.

  • The County Council may extend the moratorium for up to two additional six-month periods.

Benefits & exceptionsHide benefits & exceptions1
  • The moratorium does not prohibit data-center equipment and related infrastructure that are accessory and subordinate to a lawful principal use on the same property and serve only that property’s occupant.

Sources

Data provided by Regbase · Cookie preferences · Report missing data