The Data Center Divide

Frederick County

This restriction takes precedence while in effect. The rating below excludes temporary restrictions.

Slightly Anti-Data Center Policies

Frederick County limits data centers to a small share of land and has paused new applications until July 1, 2027, while requiring registration and additional reviews.

current law · County measure
Excludes data centers and related substations located in the Critical Digital Infrastructure Overlay Zone from county new-jobs tax credits.Frederick County Bill 26-01 — New Jobs Tax Credit Reform (2026)

What this means

The bill would remove new-jobs tax credits for Critical Digital Infrastructure facilities and substations in the overlay zone, making those projects somewhat less financially attractive. It does not ban construction or add general operating rules, so the likely effect is minor.

People behind it

  • Council President and bill sponsor, introducing the measure on behalf of County Executive Fitzwater.

  • The measure was proposed on the County Executive’s behalf.

  • Responsible for administering the tax credit, including determining eligibility and verifying continued compliance.

Restrictions & requirementsHide restrictions & requirements3
  • To qualify for the new jobs tax credit, a business must employ at least 25 new permanent full-time workers at the new or expanded premises, paying at least the Frederick Workforce Region’s 50th-percentile wage, within 24 months after occupancy. This limits access to the tax credit; it is not a construction ban. At least 25 persons in new permanent full-time positions

  • To continue receiving the new jobs tax credit, a business must maintain at least 25 permanent full-time positions at the new or expanded premises for three years after each year it receives the credit. Maintain at least 25 persons

  • Critical Digital Infrastructure facilities and substations located within a Critical Digital Infrastructure Overlay Zone are ineligible for the new jobs and enhanced jobs tax credits. This restriction applies to those facilities within the overlay zone, not all data centers. Facilities and substations located within a Critical Digital Infrastructure Overlay Zone

Sources

current law · County measure
Restricts where data centers and their dedicated substations can be built and requires measures to limit noise, visual impacts, and other effects on nearby communities.Maryland CB 25-05 (2025)

What this means

The measure would limit eligible sites to specific industrial and growth areas and require applicants to address environmental, visual, and community impacts (siting and review requirements). It also adds operating rules for noise, generators, and fuel tanks, creating significant hurdles, though it does not ban data centers outright.

People behind it

  • Council Member and co-sponsor of Bill 25-05

  • County Council President and co-sponsor of Bill 25-05

Restrictions & requirementsHide restrictions & requirements27
  • Critical digital infrastructure facilities may be located only in the Limited Industrial or General Industrial zoning districts, within a designated Community Growth Area, and within 2 miles of existing 69 kV-or-greater high-voltage transmission lines.

  • Critical digital infrastructure facilities are barred from Priority Preservation Areas, Rural Legacy Areas, Treasured Landscape Management Areas, and land designated No Planned Service in the Water and Sewerage Plan.

  • A critical digital infrastructure facility generally may not abut residentially zoned or residentially designated land. An exception allows such siting only if the front, side, and rear setbacks are increased to 200 feet from property lines.

  • The measure imposes specified minimum lot-area, lot-width, and front-, side-, and rear-yard requirements for critical digital infrastructure facilities, including larger minimum setbacks and lot standards than some other industrial uses.

  • Critical digital infrastructure facilities are subject to site-plan review, including submission of architectural renderings or plans and a viewshed analysis for review by County staff and the Planning Commission.

  • Applicants must demonstrate that impacts on scenic, rustic, historic, environmental, recreational, residential, institutional, educational, and other nearby uses will be avoided or minimized to the maximum extent practicable, and that the project will not disproportionately negatively affect overburdened or underserved communities.

  • Critical digital infrastructure facilities must screen ground-level and rooftop mechanical and electrical equipment, generators, cooling and storage facilities, utility substations, and related infrastructure from adjacent roads and properties.

  • The measure requires extensive landscaping, buffering, and screening, including multilayer evergreen and deciduous plantings, minimum planting sizes, maintenance in living condition, preservation of existing forest or hedgerows where practicable, and installation before occupancy; occupancy may not be granted if required screening is not installed.

  • Security fencing for critical digital infrastructure facilities must be screened from public view with vegetation, and chain-link or similar woven metal or plastic fencing may not be used.

  • Lighting must comply with specified standards, pole-mounted and building-mounted lights may not exceed 18 feet, and lighting must include measures such as amber or yellow tints, timers, motion detectors, or light-sensitive switches to reduce impacts on wildlife and circadian rhythms.

  • Applications must comply with County parking, loading, signage, bicycle-rack, and other applicable industrial development requirements.

  • Each site-plan application must include a registered engineer's certification that the facility complies with the performance standards. Repeated violations may lead to suspension or revocation of the zoning certificate and certificate of occupancy and cessation of operations.

  • Noise from critical digital infrastructure facilities, including electrical equipment, air handlers, generators, and other mechanical devices, is limited to 70 decibels at industrial property lines, 64 decibels at commercial property lines, and 55 decibels at residential, institutional, and other property lines.

  • Applicants must submit an environmental-acoustics sound study covering assessment methods, equipment specifications, predicted operating and generator-testing levels, emergency operation, construction phases, and recommended controls. Actual sound levels must be measured within 6 months of occupancy and biennially thereafter, with corrective action required within 180 days if limits are exceeded.

  • Critical digital infrastructure facilities may not produce vibration discernible without instruments beyond the property line or particle velocity exceeding 2 inches per second, and applications must include a vibration-impact study followed by measurements and biennial reporting, with corrective action required within 180 days for violations.

  • Generators must meet EPA Tier 4 or equivalent emission standards, be installed at ground level, and generally may be tested only Monday through Friday from 8:00 a.m. to 5:00 p.m.; only one generator per building, or the minimum operational number, may be tested at once and generally for no more than 60 minutes.

  • Stand-alone fuel-storage tanks are limited to one per critical digital infrastructure building, a maximum capacity of 20,000 gallons, and a minimum 100-foot setback from property lines and wells, subject to applicable fire-code, containment, alarm, and wellhead-protection requirements.

  • Fuel tanks attached to stationary equipment are limited to 10,000 gallons per attached tank and generally must be at least 100 feet from property lines and wells, with containment, alarms, and applicable regulatory compliance required.

  • Where multiple lots are proposed, a private street may satisfy frontage requirements only with Planning Commission approval and compliance with requirements for public-street connection, limited public access, County street-design standards, maintenance arrangements, and recorded easements, agreements, and covenants.

  • A critical digital infrastructure electric substation may be established only in the Limited Industrial or General Industrial districts, within a Community Growth Area, within 2 miles of existing 69 kV-or-greater transmission lines, and outside Priority Preservation Areas, Rural Legacy Areas, Treasured Landscape Management Areas, and No Planned Service areas.

  • A critical digital infrastructure electric substation may be constructed only to provide power to a critical digital infrastructure facility that has received Planning Commission site-plan approval. The substation application may be processed concurrently with the facility application.

  • A critical digital infrastructure electric substation may connect to another regional electrical system, but expansion to support other uses or users must comply with the rules and procedures for nongovernmental electric substations.

  • Substation applications must document adjoining-property conditions within 1,000 feet and address environmental and ecological effects, electromagnetic-field impacts, safety and reliability, emergency operations and shutdowns, preservation-area visual impacts, and mitigation of waste, air-quality, visual, and noise impacts.

  • Electric substations must meet specified landscaping, screening, buffering, lighting, and fencing requirements, including 18-foot maximum light-pole height, installation of required screening before occupancy, and prohibitions on chain-link or similar woven fencing.

  • Electric substations are subject to maximum sound levels of 70 decibels at industrial property lines, 64 decibels at commercial property lines, and 55 decibels at residential, institutional, and other property lines, with required sound studies, measurements within 6 months of operation, biennial reporting, and corrective action within 180 days for exceedances.

  • Electric substations may not produce vibration discernible without instruments beyond the property line or particle velocity exceeding 2 inches per second, and applications must include a vibration-impact study.

  • The Planning Commission may approve an electric-substation height increase only after finding no adverse impact on nearby properties; for every 3 feet above the normal maximum height, front, side, and rear setbacks must increase by 1 foot.

Benefits & exceptionsHide benefits & exceptions11
  • Existing Critical Digital Infrastructure Facilities and electric substations are exempt from the new requirements if they had submitted a site plan to the Division of Planning and Permitting by the bill’s effective date. This protects projects already in the approval process from future restrictions. submitted a site plan

  • A Critical Digital Infrastructure Electric Substation may be approved specifically to provide power to a Critical Digital Infrastructure Facility, and the substation application may be processed concurrently with the facility application. may be processed concurrently

  • A Critical Digital Infrastructure Electric Substation may be connected to another electrical system within the region, supporting regional interconnection and operational reliability. connected to another electrical system within the region

  • The Planning Commission may reduce, but not eliminate, required yard setbacks between adjoining Critical Digital Infrastructure Facilities when the reduction improves open space, buffers, environmental protection, or compliance with the design criteria. may approve a reduction to, but not elimination of

  • Critical Digital Infrastructure may be established next to residentially zoned or designated land if the front, side, and rear setbacks are increased to 200 feet, providing an alternative to an outright prohibition on such sites. so long as the designated setbacks are increased to 200 feet

  • For multiple lots proposed for Critical Digital Infrastructure, a private street may satisfy lot-frontage requirements if it connects to a public road, serves limited nonpublic uses, meets County street-design rules, and is properly maintained and documented. the lot frontage requirement

  • The Planning Commission may approve an alternative landscaping, buffering, and screening plan that meets the purpose and intent of the requirements, giving projects flexibility in how screening obligations are satisfied. an alternate landscaping, buffering, and screening plan

  • Substation height may exceed the normal maximum if the Planning Commission finds that the additional height will not adversely affect nearby properties. The required setbacks increase by one foot for each three feet of additional height. may approve an increase in the maximum height

  • Critical Digital Infrastructure Facilities may use generators meeting Tier 4 or equivalent emission standards, with generator testing allowed Monday through Friday from 8:00 a.m. to 5:00 p.m.; testing is generally limited to one generator per building, or the minimum necessary, for no more than 60 minutes at a time, subject to legal or utility restrictions. Generators must meet or exceed Tier 4

  • The measure expressly allows fuel storage for facility operations, including one above-ground standalone tank per building with a capacity up to 20,000 gallons, or attached storage tanks up to 10,000 gallons each, subject to containment, setbacks, fire-code, wellhead-protection, and other regulatory requirements. capacity not to exceed 20,000 gallons

  • Sound and vibration compliance reports for Critical Digital Infrastructure Facilities are required biennially after the initial post-occupancy measurement, rather than annually, reducing the frequency of recurring monitoring obligations. biennially

Sources

current law · County measure
Allows data centers in limited and general industrial zones with site plan approval, subject to specific design, screening, noise, and vibration requirements.Maryland CB 22-05 (2022)

What this means

The measure creates a path for data centers, but limits them to industrial districts and requires site-plan approval. It also adds practical costs and steps, including landscaping and screening rules and an engineer’s certification of noise and vibration standards, so the net effect is a meaningful but not severe added burden.

People behind it

  • County Council President who introduced the bill on behalf of County Executive Jan Gardner

  • County Executive on whose behalf the bill was introduced

Restrictions & requirementsHide restrictions & requirements17
  • Critical Digital Infrastructure Facilities are subject to minimum bulk standards in the LI and GI Districts, including an 80,000-square-foot lot, 200-foot lot width, 50-foot front, side, and rear yards, and a 60-foot height limit.

  • Site plans must include architectural renderings or plans, and publicly visible building facades must use specified design features to avoid long, plain, undifferentiated walls.

  • Mechanical equipment, generators, cooling and storage facilities, substations, and related utility infrastructure must be screened from adjacent roads and properties using a principal building or an approved opaque screen.

  • Staff must refer Critical Digital Infrastructure Facility site plans to the Architectural Review Committee before the plans are scheduled for Planning Commission review. This requirement is delayed until the Committee has been appointed and confirmed.

  • Facilities must provide landscaped buffers along road-facing front yards and, except where adjoining another Critical Digital Infrastructure use, along side and rear yards, with specified multi-layer vegetation and minimum planting sizes.

  • Existing forests and hedgerows must be preserved to the maximum extent practicable where screening or buffering is required, and all required landscaping, screening, and buffering must be maintained.

  • A landscape, buffering, and screening plan must be submitted with the site plan, and occupancy may not be granted unless the approved screening and buffering have been installed.

  • Parking, loading, signage, lighting, and bicycle facilities must meet specified zoning requirements; light poles may not exceed 18 feet, subject to potentially more restrictive Planning Commission requirements.

  • Subdivision of property for Critical Digital Infrastructure uses must comply with County subdivision rules. Private streets may be used to satisfy frontage requirements only with Planning Commission approval and subject to conditions concerning public-road connection, limited access, design, maintenance, and recorded easements and agreements.

  • Site plan applications must include certification by a registered engineer that the facility complies with the applicable performance standards. Continued or frequent violations can result in suspension or revocation of the Zoning Certificate and Certificate of Occupancy and immediate cessation of operations.

  • Facilities must meet maximum sound-pressure levels measured at adjacent property lines: 70 decibels for industrial uses, 64 for commercial uses, and 55 for residential, institutional, and all other uses, with air handlers, generators, and other mechanical devices included.

  • Facilities may not produce ground-transmitted vibration discernible without instruments beyond the property line or vibration exceeding 2 inches per second at or beyond the property line, except between adjoining Critical Digital Infrastructure Facilities.

  • Critical Digital Infrastructure Electric Substations may be built only to provide power to a Critical Digital Infrastructure Facility and only after that facility has received Planning Commission site plan approval; the applications may be processed concurrently.

  • Expanding a Critical Digital Infrastructure Electric Substation to support other uses or users must follow the rules and procedures applicable to nongovernmental electric substations.

  • Substation applications must provide information about adjoining properties within 1,000 feet and assess environmental effects, electromagnetic fields, safety and reliability, impacts on designated preservation or historic areas, and methods to mitigate waste, air-quality, visual, and noise impacts.

  • Critical Digital Infrastructure Electric Substations are subject to landscaping, screening, lighting, noise, and vibration requirements, including an 18-foot lighting-pole limit and the same 70-, 64-, and 55-decibel sound limits.

  • The Planning Commission may approve a substation height increase only after finding no adverse impact on nearby properties; for every 3 feet above the applicable height limit, required front, side, and rear setbacks must increase by 1 foot.

Benefits & exceptionsHide benefits & exceptions8
  • Adds Critical Digital Infrastructure Facilities as a permitted subject-to-site-plan use in the Limited Industrial and General Industrial districts, allowing data centers to seek approval in those districts. The use table lists Critical Digital Infrastructure Facility as “PS PS”.

  • Defines accessory components that may be included in a data center, including offices, air handlers, generators and storage, cooling and water-storage facilities, and supporting utility infrastructure. The facility may also include customary accessory uses.

  • Allows a Critical Digital Infrastructure Electric Substation to be constructed to serve an approved data center, with the substation application processed at the same time as the facility application. An application for a Critical Digital Infrastructure Electric Substation may be processed concurrently.

  • Permits a qualifying electric substation to connect to another electrical system in the region, supporting power reliability and interconnection. Any expansion intended to support other uses or users must instead comply with the rules for a nongovernmental electric substation. A Critical Digital Infrastructure Electric Substation may be connected to another electrical system within the region.

  • Allows the Planning Commission, during site-plan review, to reduce—but not eliminate—required yard setbacks between adjoining Critical Digital Infrastructure Facilities when the reduction improves open space, buffers, environmental protection, or compliance with design criteria. Building-code-required separation still applies. The Planning Commission may approve a reduction to, but not elimination of, the required yard setbacks.

  • Allows multiple lots used for Critical Digital Infrastructure to satisfy lot-frontage requirements through an approved private street, provided the originating parcel has public-street frontage, the street connects to a public road, serves no uses frequented by the general public, meets subdivision standards, and is maintained by an owners’ association or similar organization. The lot frontage requirement may be met by construction of a private street.

  • Allows the Planning Commission to approve an electric-substation height increase above the normal district maximum if the increase will not adversely affect nearby properties. For every three feet above the maximum, front, side, and rear setbacks must increase by one foot. The Planning Commission may approve an increase in the maximum height.

  • Temporarily delays the Architectural Review Committee review requirement for data-center site plans until the committee has been appointed by the County Executive and confirmed by the County Council, allowing applications to proceed without that review during the interim. The requirements regarding review by the Architectural Review Committee shall not take effect until the Committee has been appointed.

Sources

current law · County measure
Requires data center developers to prove they are registered with Maryland’s large-load customer registry before their projects can proceed through county development review.Maryland Frederick County Executive Order — Large-Load Registry Requirement (2026)

What this means

Requires proof of registration before Planning Commission review, or interim energy disclosures before registry establishment. Adds review conditions rather than imposing EO 04-2026’s separate application hold.

Timing

Ends
Jul 1, 2027

EO 03-2026 is effective July 1, 2026, and terminates July 1, 2027 unless changed by further executive order. This registry/disclosure order is distinct from the separate temporary application hold.

People behind it

  • Frederick County Executive who issued EO 03-2026.

  • Must verify registration or required interim disclosures before advancing covered site-development plans.

Restrictions & requirementsHide restrictions & requirements1
  • Covered CDI facility and electric-substation site-development plans cannot move to Planning Commission consideration without proof of PSC large-load registry registration. Before registry establishment, project energy and capacity needs and energy characteristics must be disclosed.

Benefits & exceptionsHide benefits & exceptions2
  • Properties with an approved APFO Letter of Understanding before the order’s effective date are exempt.

  • Before the PSC registry exists, applicants can provide energy and capacity information instead.

Sources

current law · County measure
Requires data centers that discharge non-domestic wastewater into Frederick County’s sewer system to meet applicable pretreatment, permitting, monitoring, and reporting requirements; it contains no data-center-specific rules.Maryland Ordinance 26-06-006 (2026)

What this means

The ordinance does not target data centers, but it applies to businesses that discharge non-domestic wastewater and may require surveys, permits, monitoring, and pollution controls. These could add some operating costs or delay, especially for facilities discharging cooling-related wastewater, but the document does not show a major data-center-specific barrier.

People behind it

  • Enacted the ordinance and established its objectives and requirements.

  • Administers, implements, and enforces the ordinance and Frederick County’s pretreatment program.

Restrictions & requirementsHide restrictions & requirements16
  • A data center connecting to the County sewer system must submit an Industrial Waste Survey before connection; the Division may require the survey to be updated, and requested survey information is due within 30 days.

  • A data center classified as a Significant Industrial User, subject to categorical pretreatment standards, or otherwise directed by the Division must obtain an individual wastewater discharge permit before discharging. A new source must apply at least 90 days before beginning or recommencing discharge.

  • Permit applications may require detailed operational information, process diagrams, site and plumbing plans, sewer and floor-drain locations, discharge points, flow data, pollutant sampling, and information about raw materials and chemicals.

  • A data center must obtain written Division approval before implementing planned significant process, facility, flow, or wastewater changes. Written notice is generally required at least 30 days before a scheduled change, including a 10 percent or greater increase in flow or pollutant concentration.

  • Noncontact cooling water, condensate, groundwater, stormwater, sump-pump discharge, and similar flows may not be discharged to the POTW unless specifically authorized by Frederick County.

  • Wastewater with a pH below 5.0 or above 12, wastewater above 140°F, or wastewater that causes the treatment plant temperature to exceed 104°F is prohibited.

  • A data center must install, operate, and maintain any required pretreatment, flow-control, equalization, containment, interception, monitoring, or gas-detection facilities at its own expense. Pretreatment plans and later facility or process changes require Division review and approval.

  • Permits may impose pollutant limits, flow limits, discharge timing restrictions, flow equalization requirements, monitoring locations and frequencies, sampling methods, reporting obligations, spill-control requirements, slug-discharge controls, and waste-minimization measures.

  • Significant Industrial Users must conduct self-monitoring at least twice annually, while categorical users must monitor at least as frequently as the applicable federal standard requires. The Division may increase monitoring from semiannual to quarterly, quarterly to monthly, or more frequently.

  • The Division may conduct at least one compliance-monitoring event per calendar year for each Significant Industrial User and may conduct unannounced inspections, sampling, flow verification, and records reviews. The user must provide access and maintain sampling and flow-monitoring facilities.

  • Users must retain monitoring records for at least three years, submit required compliance reports, and immediately report treatment failures, slug discharges, hazardous-waste discharges, and certain violations, generally followed by written reports within five days or, for unauthorized hazardous-waste discharges, within 15 days.

  • Industrial users may incur fees for permits, monitoring, inspections, sampling, report review, spill or upset responses, appeals, and enforcement-related administrative or legal costs. Users must also pay for required flow meters, pretreatment facilities, monitoring equipment, maintenance, and calibration.

  • High-strength wastewater may trigger surcharges. The surcharge thresholds are 300 mg/l for BOD or TSS and 100 mg/l for fats, oils, and grease; concentrations at or above the applicable violation limits of 600 mg/l for BOD or TSS and 250 mg/l for FOG are violations.

  • Violations may result in notices, compliance or cease-and-desist orders, administrative fines of up to $1,000 per violation per day, civil infractions, criminal penalties, permit revocation, termination of discharge, sewer-service termination, or water-service severance.

  • A discharge permit may not be transferred to another user or location without prior written approval. A change in facility ownership or control requires at least 30 days advance written notice, and failure to provide that notice voids the permit upon transfer.

  • Individual wastewater discharge permits may last no longer than five years, and a renewal application must be submitted at least 90 days before expiration.

Benefits & exceptionsHide benefits & exceptions10
  • The Division may enter into a specific agreement with a User establishing special discharge terms, although the agreement may not waive National Pretreatment Standards.

  • Individual wastewater discharge permits may be issued for up to five years, providing a defined permit term for facility operations.

  • A categorical Industrial User may obtain a monitoring waiver for a pollutant that is not present or expected to be present in its discharge. The waiver may last for the permit term but no longer than five years, requires supporting sampling and certification, and must be included in the permit.

  • A permitted User may apply to modify its permit when it believes some permit requirements no longer apply to its facility.

  • A User may appeal permit terms to the Division Director within 30 days of permit issuance. The appeal must identify the challenged provisions and requested alternatives, although the permit generally remains effective while the appeal is pending.

  • If an on-site monitoring facility would be impractical, the User may apply for a right-of-way or permission to construct the monitoring facility on public property, subject to Division approval and at the User’s expense.

  • A User may use water-consumption data or process-flow estimates instead of actual wastewater-flow measurements for SIU reporting if the Division gives prior approval.

  • An anticipated bypass may be approved by the Division after consideration of its adverse effects, and bypasses necessary for essential maintenance are allowed if they do not violate Pretreatment Standards or Requirements and are necessary for proper and efficient treatment-facility operation.

  • An Industrial User may assert an upset as an affirmative defense to an enforcement action for noncompliance with categorical Pretreatment Standards if the upset was beyond its reasonable control, the facility was operated prudently and according to applicable procedures, and the User provides the required notices and corrective-action information.

  • A User may assert an affirmative defense to enforcement for prohibited discharges if it lacked knowledge or reason to know that the discharge would cause Pass Through or Interference and either complied with applicable Local Limits or did not substantially change its discharge under the conditions specified in the ordinance.

Sources

current law · County measure
Identifies a 2026 Frederick County executive order, but its purpose, requirements, affected parties, and implementation status are not specified.Frederick County Executive Order 03-2026 (2026)

What this means

The county says it cut the land zoned for data centers in half and that they cannot be built on 99 percent of county land. That significantly limits where new centers can be built or expanded, though it does not ban them countywide.

People behind it

  • Identified as the measure’s sponsor.

Restrictions & requirementsHide restrictions & requirements1
  • Data centers are barred from 99% of County land, and the acreage zoned for them was cut in half, according to the County Executive’s page (“cut the number of acres zoned for data centers in half”).

Benefits & exceptionsHide benefits & exceptions1
  • Provides a personal-property tax credit for qualifying data centers, subject to the measure’s eligibility requirements. Personal-property tax credit

Sources

Specific to Frederick County only.

current law · County measure
Pauses new data center and related substation applications in Frederick County until July 1, 2027, and requires developers to show they are registered with the state’s large-load customer registry before proceeding through county review.Maryland Frederick County Executive Order — July 1, 2026 Data Center Application Pause (2026)

What this means

The county’s pause on accepting and processing new data center applications, extended until July 1, 2027, would temporarily block new projects from moving forward (pause on data center applications). Developers would also have to provide proof of state registration before advancing through county review (proof of registration), adding a further step.

Timing

Ends
Jul 1, 2027

The pause on data center applications was extended until July 1, 2027.

People behind it

  • Signed the executive order pausing acceptance and processing of new data-center applications, then extended the pause until July 1, 2027 (signed an executive order to pause the acceptance and processing; extending the pause on data center applications until July 1, 2027).

Restrictions & requirementsHide restrictions & requirements3
  • The County’s zoning decision restricts data center development to an area north of Adamstown; the decision could not be put on the fall ballot. restricted to an area north of Adamstown

  • The County paused acceptance and processing of new applications for Critical Digital Infrastructure facilities or substations, extending the pause through July 1, 2027. extending the pause on data center applications until July 1, 2027

  • Before advancing through County development review, data center developers must provide proof of registration with the Public Service Commission’s large-load customer registry, which requires disclosure of how power needs will be served and projected annual usage. provide proof of registration

Sources

expired · County measure
Temporarily prohibits Frederick County from considering new data center applications and applications for substations that support them.Maryland Executive Order 03-2025 (2025)

What this means

The measure would pause consideration of new data center applications and related substations while the County Council considers zoning rules (“temporarily prevents the consideration of any new applications”). That could significantly delay new projects, but the source gives no fixed end date and does not say existing centers must stop operating.

Timing

The order temporarily pauses consideration of new data-center applications and supporting substations, but the sources provided do not specify when the pause ends.

People behind it

  • Frederick County Executive who issued the executive order temporarily pausing consideration of new data center and related substation applications.

Restrictions & requirementsHide restrictions & requirements1
  • A temporary hold prevents consideration of new data center applications and applications for electrical substations that support data centers while the County Council considers zoning regulations and new standards. The order applies to new data center applications and supporting substations.