Regbase

The Data Center Divide

Carroll County

This restriction takes precedence while in effect. The rating below excludes temporary restrictions.

Neutral Data Center Policies

Carroll County has enacted a one-year pause on accepting, reviewing, processing, and approving data center plans, delaying new construction and expansion; existing operations may continue.

Rating from Maryland statewide as there are no scored current or future laws outside temporary restrictions for Carroll County.

Specific to Carroll County only.

current law · Unincorporated areas
Temporarily pauses Carroll County’s acceptance, review, processing, and approval of data center plans for one year beginning February 19, 2026.Maryland Ordinance 2026-02 (2026)

What this means

The measure would pause acceptance, review, processing, and approval of data center plans in the county for one year, making new construction and expansion substantially harder during that period. It does not ban ongoing operations, but the year-long moratorium is a major delay.

Timing

Ends
one year after the effective date, 2026-02-19

The temporary deferral applies to acceptance, processing, reviewing, and approval of all data processing center plans in Carroll County. No extension condition is stated.

People behind it

  • Moved the motion to approve a one-year deferral of data processing centers and close the public hearing.

  • Seconded the motion to approve a one-year deferral of data processing centers and close the public hearing.

  • Approved the one-year temporary deferral and enacted the related zoning ordinance.

Restrictions & requirementsHide restrictions & requirements2
  • A one-year deferral prohibits the acceptance, processing, review, and approval of all plans for data processing centers in Carroll County. The deferral begins February 19, 2026, and applies to data processing centers as defined in § 158.002. one year starting with the effective date

  • The deferral required approval by the Board of County Commissioners following a public hearing; the Board approved the one-year deferral by unanimous vote. approve a deferral of data centers for 1 year

Benefits & exceptionsHide benefits & exceptions4
  • Adds data centers as an allowed use in the County’s industrial zoning districts, allowing development there without requiring rezoning to a new district.

  • Allows data-center development through the County’s site-plan review process, subject to specified development standards and approvals.

  • Allows supporting infrastructure and equipment—including electrical substations, emergency generators, cooling systems, support buildings, and related utility facilities—to be developed and operated as part of or accessory to the data-center use.

  • Establishes a defined zoning framework for classifying and reviewing data centers, expansions, and related site improvements, reducing regulatory uncertainty.