The Data Center Divide

Calvert County

This restriction takes precedence while in effect. The rating below excludes temporary restrictions.

Neutral Data Center Policies

Calvert County’s enacted measures impose a six-month pause on data-center site-plan approvals and permits, delaying new projects and expansions but not directly stopping existing centers from operating; descriptions conflict on whether one measure was proposed.

Rating from Maryland statewide as there are no scored current or future laws outside temporary restrictions for Calvert County.

Incentives

Tax benefits

Proposed, not enacted: authorizes negotiated PILOT agreements providing a county property-tax exemption.

Specific to Calvert County only.

current law · Unincorporated areas
Restricts data centers to industrial areas, requires them to meet rules for location, design, noise, water, infrastructure and emissions and hold a public meeting, and temporarily pauses site-plan applications and approvals for six months.Calvert County Zoning Ordinance § Z-18-11F (2025)

What this means

A six-month moratorium would temporarily stop the county from accepting or approving data-center site plans. Afterward, data centers would still face significant siting and operating rules, although changing the approval process could make permission easier to obtain.

Timing

Ends
six months after 2026-08-28

The six-month moratorium became effective on 2026-08-28 and expires after six months. No extension condition is stated. Other cited documents describe related measures as not establishing a moratorium.

People behind it

  • Recommended revisions to the zoning ordinance, official zoning maps, and comprehensive rezoning; administers the zoning ordinance; and reviews and approves Data Center Water Services Plans.

  • Conducted the public hearing, deliberated on proposed revisions, and conveyed its recommendation to the Board of County Commissioners.

  • Introduced, enacted, and adopted the zoning ordinance, comprehensive rezoning, official zoning maps, and the six-month data center site-plan moratorium.

Show 3 more peopleShow fewer people
  • Administers the data center moratorium by refusing to accept or approve data center site-plan applications during its duration.

  • Administers the zoning ordinance, issues zoning approvals, grants authorized administrative variances, and interprets its provisions.

  • Administers and implements the ordinance’s floodplain regulations as Floodplain Administrator.

Restrictions & requirementsHide restrictions & requirements23
  • A six-month moratorium, effective August 28, 2026, bars the County from accepting data-center site-plan applications or approving pending or new site plans proposing a data center.

  • Outside Town Centers, data centers require Special Exception approval with conditions and Board of Appeals review in the I-1 Light Industrial District; they are permitted with conditions in the I-2 Heavy Industrial District.

  • Data centers must be set back 200 feet from all property lines and 400 feet from any lot or parcel containing a residential building or active residential building permit, except for adjacent properties under common ownership.

  • Primary building facades must include at least two design treatments: fenestration, recessed facade areas, or changes in building materials, patterns, textures, colors, or accent materials.

  • Data-center noise, including noise from accessory mechanical equipment, must comply with Chapter 80 of the County Noise Control Ordinance; in industrial zones, the stated limits are 75 dBA during the day and 70 dBA at night.

  • Noise violations may result in civil fines of up to $1,000 for a first offense and up to $10,000 for each subsequent offense.

  • Before any applicable Planning Commission meeting, the applicant must hold at least one public meeting in the election district where the data center is proposed, advertise it once a week for at least two consecutive weeks, and submit the attendance sign-in sheet and minutes at least two weeks before the Planning Commission meeting. The first advertisement may be no more than 30 days before the meeting.

  • Groundwater wells may not be drilled or used to supply water for data-center cooling or humidification.

  • A data center must obtain approval of a Water Services Plan prepared by a Maryland-licensed professional engineer, addressing projected water demand, evaporation, water and wastewater arrangements, non-potable sources, cooling systems, potable-water reduction measures, metering, annual reporting, sustainability, and impacts on public utilities and ratepayers.

  • The Water Services Plan must be updated and reapproved before a material expansion or operational change that increases projected average daily cooling-water demand by more than 10 percent over the approved plan.

  • Inefficient evaporative cooling systems, including continuous cooling towers and once-through cooling, are prohibited; evaporative cooling may be used only through highly efficient systems.

  • The applicant or owner must pay the full cost of designing, permitting, constructing, and inspecting required on-site and off-site public infrastructure improvements, including water, wastewater, stormwater, and roadway improvements.

  • Stationary diesel generators serving server rooms, including emergency and standby generators, must meet U.S. EPA Tier 4 Final standards or equivalent successor performance where available for the applicable engine size or class, and must comply with Maryland Department of the Environment air-quality permitting requirements.

  • The Department of Planning and Zoning may require third-party review of a data-center plan or application when it determines review is necessary, and the applicant must pay the associated costs under the approved fee schedule.

  • Commercial or industrial projects that fill wetlands or affect wetland buffers require Planning Commission conceptual site-plan approval and applicable federal, State, and County permits; subdivision may not require wetland filling except for access to otherwise inaccessible property or stormwater management outside wetlands, and filling wetlands for single-family detached homes is prohibited.

  • Development near nontidal wetlands must maintain a 50-foot buffer, potentially expanded under State requirements, plus a 10-foot building setback from the buffer edge; the buffer must remain undisturbed, and enhanced sediment and erosion controls are required for disturbance within 100 feet of the buffer edge.

  • Development activities and other disturbances in designated habitat protection areas are prohibited unless the applicant demonstrates they will not adversely affect the habitat, and required Habitat Protection Plans must be approved before specified development plans or permits.

  • Buildings in designated Chesapeake Bay, Patuxent River, and tributary cliff areas must meet setbacks of 300 feet or the ER50 line in Category 1, 200 feet or the ER50 line in Category 2, and 100 feet or the ER50 line in Category 3; subdivisions must be set back 300 feet in Category 1 and 200 feet in Category 2.

  • Development in a special flood hazard area requires a County permit before work begins, along with required State, federal, or local approvals; nonresidential buildings generally must be elevated to the required flood-protection elevation, and new nonresidential floodproofing is prohibited in nontidal State waters and Coastal A Zones.

  • Buildings and structures generally may not exceed 40 feet in height; in the I-2 District, the limit is 75 feet, but the building must be set back from property lines by twice its height, except from commonly owned adjoining property.

  • Nonresidential development must provide sidewalks or multi-use paths, comply with County road standards, provide loading and trash-collection facilities, and meet specified arterial-road, cross-access, and emergency-access requirements; roads must be completed or bonded before building permits are issued.

  • Certain commercial, industrial, and institutional properties must comply with outdoor-lighting controls, including full-cutoff, downward-aimed luminaires and a limit of 0.1 horizontal footcandle on adjacent residential property.

  • Subdivisions and site-plan developments must address historic and archaeological resources; buildings at least 50 years old may require historic assessment, preservation, or documentation before removal, archaeological surveys or preservation may be required, and known cemeteries require a 25-foot construction-avoidance area, an easement, and a 15-foot access right-of-way.

Benefits & exceptionsHide benefits & exceptions15
  • Data centers are permitted with conditions in the I-2 Heavy Industrial District, subject to the applicable requirements in Section 18-11.F.

  • Data centers may be approved through conditional-use or special-exception approval in the I-1 Light Industrial and Mixed-Use District, providing an additional zoning pathway. (Data Center)

  • A data center may consist of multiple buildings arranged as a unified campus.

  • The 400-foot separation from residential lots or parcels does not apply to adjacent properties under common ownership, allowing more flexible siting or expansion across commonly owned land. (except for adjacent properties under common ownership)

  • In the I-2 District, buildings may be up to 75 feet high instead of the general 40-foot maximum, provided they are set back twice their height from property lines other than commonly owned adjoining properties. (In the I-2 District, no building or structure shall exceed 75 feet)

  • Industrial Districts are intended to provide infrastructure required by targeted industries, including high-technology and research firms. (infrastructure they require)

  • A Community Enhancement District may include uses listed in Article 18, including qualifying industrial uses, when consistent with the Comprehensive Plan and ordinance; the land must be under unified control and the district requires Planning Commission and Board of County Commissioners approval. (Any use within the use tables of Article 18)

  • A Community Enhancement District may provide relief from strict base-district development standards and allow creative approaches to access, lighting, open space, and amenities, subject to the required approval process. (Provide for relief from the strict application)

  • The Community Enhancement District framework applies public improvements such as sewer laterals, roads, and sidewalks to the development as a whole and is intended to reduce the burden of new development on utility and infrastructure systems. (Decrease the burden created by new development on utilities)

  • Roads serving a development do not have to be completed before building permits are issued if they are bonded with the required financial security and meet applicable road standards. (All roads shall be constructed)

  • A data center designed to operate without water for cooling may satisfy the water-planning requirement with a sealed certification instead of a full Water Services Plan; domestic and plumbing water use is excluded from this option.

  • A Water Services Plan must be updated and reapproved only when a material expansion or operational change increases projected average daily cooling-water demand by more than 10 percent over the approved plan.

  • Highly efficient evaporative cooling systems are allowed for heat rejection, while inefficient continuous cooling towers and once-through cooling are prohibited.

  • Stationary diesel generators, including emergency and standby generators serving server rooms, are allowed if they meet the applicable U.S. EPA Tier 4 Final or equivalent emissions standard and Maryland air-quality permitting requirements.

  • Applications submitted before adoption of the ordinance and accepted for site-plan, subdivision, road-plan, or permit review by February 18, 2025, may remain subject to the superseded regulations for up to 12 months after the March 1, 2025 effective date; if the project advances to the next required review or approval during that period, the former regulations continue while the resulting approval remains valid and does not expire. (grandfathered under the superseded regulations)

Sources

current law · County measure
Prohibits Calvert County from approving data center site plans or issuing permits for new data centers for six months while it reviews its regulations.Calvert County Ordinance 42-26 (2026)

What this means

The proposed measure would block pending and new data-center site plan approvals for up to six months, and prevent permits for new data centers during that period. It would not directly stop existing centers from operating, but the pause would substantially delay new projects and expansions needing site plan approval.

Timing

Ends
The earlier of six months after the effective date (2027-02-28, based on the stated effective date of 2026-08-28) or the date the Board terminates the moratorium by resolution.

The ordinance is automatically repealed when the moratorium period ends. Any extension or other substantive change requires the same public notice, hearing, and adoption process.

People behind it

  • Unanimously enacted the six-month moratorium.

  • Presented the moratorium for public hearing and provided the associated agenda materials.

Restrictions & requirementsHide restrictions & requirements2
  • During the moratorium, the County will not accept data center site plan applications or approve site plans, including pending or new applications. The moratorium takes effect Aug. 28, 2026, and lasts up to six months, but may end earlier by Board resolution. Applications will not be accepted; pending or new site plan requests are covered.

  • During the moratorium, the County may not issue a grading permit, building permit, or any other County permit for a new data center. Permits for a new Data Center are barred.

Benefits & exceptionsHide benefits & exceptions1
  • The moratorium is temporary: it automatically expires after six months, or earlier if the Board terminates it by resolution after finding its conditions have been satisfied. This ends the ordinance’s bar on site plan approvals, but does not guarantee approval or exempt projects from other requirements.

Sources

pending · County measure
Would limit data centers to Heavy Industrial zones and, if adopted, require water-use planning, prohibit cooling wells, make developers pay for required infrastructure, and require cleaner backup generators.Calvert County Text Amendment Case #26-23 (2026)

What this means

The proposed amendment would limit data centers to Heavy Industrial zones and add requirements for water planning, infrastructure costs, and cleaner backup generators, creating significant added expense and narrowing where projects can be built (proposed zoning and operating conditions). It does not ban data centers, but these requirements would make new projects and expansions harder.

Timing

Ends
six months after its effective date (2026-08-28)

People behind it

  • Directed staff to draft additional data-center conditions and considered the proposed text amendment.

  • Prepared and presented Text Amendment #26-23 for the Board’s consideration.

  • Reviewed the draft and recommended provisions and other considerations for the Board to consider.

Restrictions & requirementsHide restrictions & requirements13
  • A six-month moratorium, effective August 28, 2026, bars the County from accepting data-center site-plan applications or approving pending or new data-center site plans. six-month moratorium

  • Proposed Text Amendment 26-23 would allow data centers only in the I-2 Heavy Industrial District; under the existing zoning described in the sources, data centers can also be considered in I-1, but require conditional-use approval and a Board of Appeals special exception. only permit data centers in the I-2 Special Exception from the Board of Appeals

  • Data centers must be at least 200 feet from property lines and 400 feet from a lot or parcel with a residential building or active residential building permit, except for adjacent properties under common ownership. setback 200 feet

  • Before Planning Commission consideration, an applicant must hold a public meeting in the election district where the project is proposed, advertise it weekly for at least two consecutive weeks, and submit the sign-in sheet and minutes at least two weeks before the Commission meeting. Prior to any applicable Planning Commission meeting

  • Primary building facades must include at least two specified design treatments: fenestration, facade recesses, or changes in materials, pattern, texture, color, or accent materials. at least two of the following treatments

  • Data-center noise, including noise from accessory mechanical equipment, must comply with Chapter 80 of the County Noise Control Ordinance. must comply with Chapter 80

  • Proposed Text Amendment 26-23 prohibits drilling or using groundwater wells to supply cooling or humidification. No groundwater well shall be drilled or used

  • The proposed amendment requires a Water Services Plan prepared by a Maryland-licensed professional engineer and reviewed and approved by Planning & Zoning in consultation with Public Works and, where applicable, the Health Department. The plan must address water demand, supply and disposal, feasible non-potable sources, cooling systems, and metering and annual reporting. Water Services Plan

  • If a project’s material expansion or operational change increases projected average daily cooling-water demand by more than 10% over the approved plan, the Water Services Plan must be updated and reapproved. A facility designed to use no water for cooling, excluding domestic or plumbing use, may submit a sealed certification instead of a full plan. more than ten percent

  • Cooling systems may use evaporative heat rejection only if they are highly efficient; continuous cooling towers and once-through cooling are prohibited. Inefficient evaporative systems

  • The applicant or owner must pay the full cost of required on-site and off-site public infrastructure design, permitting, construction, and inspection, including water, wastewater, stormwater, and roadway improvements. full cost of design, permitting, construction, and inspection

  • Stationary diesel generators serving server rooms, including emergency and standby generators, must meet U.S. EPA Tier 4 Final emissions standards or equivalent where certification is available for the engine size or class, and must comply with Maryland air-quality permitting requirements. Tier 4 Final emission standards

  • If Planning & Zoning determines that third-party review is necessary to ensure compliance with applicable requirements, the review is required and the applicant pays the associated costs under the approved fee schedule. third-party review is necessary

Benefits & exceptionsHide benefits & exceptions3
  • A data center designed to operate without water for cooling, apart from domestic or plumbing use, may submit a sealed certification instead of a full Water Services Plan: “in lieu of a full Water Services Plan”.

  • A Water Services Plan must be updated and reapproved for a material expansion or operational change only if it increases projected average daily cooling-water demand by more than 10% over the approved plan: “by more than ten percent”.

  • The draft allows cooling systems to use water evaporation for heat rejection if they are highly efficient; continuous cooling towers and once-through cooling are prohibited: “may utilize water evaporation”.

Sources

Specific to Calvert County only.

failed · County measure
Allows Calvert County to negotiate payments with data centers instead of county property taxes, while requiring them to pay their fair share of electricity-system costs.Maryland HB 949 (2025)

What this means

The measure would let Calvert County negotiate agreements that could lower property-tax costs for qualified data centers, making building or operating there more attractive. The benefit is limited to that county and is not guaranteed, since the county does not have to offer an agreement; the measure adds no new data center restrictions.

People behind it

  • Sponsored and proposed HB 949, authorizing Calvert County to enter into payment-in-lieu-of-taxes agreements with owners of qualified data centers.

Restrictions & requirementsHide restrictions & requirements4
  • Allows Calvert County to require the owner of a qualified data center to make payments in lieu of county property taxes under an agreement, creating an additional cost for participating data centers; the agreement is optional.

  • Requires a data center to obtain approval from the Public Service Commission before it may be constructed, expanded, or connected to the electric system.

  • Requires the approval process to evaluate the data center’s effects on electric-system capacity, reliability, rates, and infrastructure needs before service is provided.

  • Requires the data center or its owner to pay costs associated with studies, interconnection, and electric-system upgrades needed to serve the facility, rather than shifting those costs to other utility customers.

Benefits & exceptionsHide benefits & exceptions4
  • Allows Calvert County’s governing body to enter into a negotiated payment-in-lieu-of-county-property-taxes agreement with the owner of a qualified data center located or locating in the county.

  • Allows the agreement to require a specified annual payment for a specified term instead of county property taxes on covered real, operating real, operating personal, or qualified data center personal property.

  • Provides that, for the agreement’s specified term, all or a specified part of the covered property may be exempt from county property tax.

  • Requires the Calvert County supervisor of assessments, upon the county governing body’s written request, to assess the covered property of a qualified data center that has entered into a payment-in-lieu-of-taxes agreement.

Sources