Town of Wells
Neutral Data Center Policies
Maine has no general data-center ban, but enacted rules remove certain tax and business incentives for facilities operating from August 2026, with some expansions affected. A narrow electricity-provider limit applies at certain sites, and state agencies are directed to develop ways to make data centers cover costs they cause.
Rating and summary from Maine statewide as there are no scored current or future laws outside temporary restrictions for Town of Wells.
pending · Town of WellsProposes a 180-day pause on new or expanded data centers in Wells, applying to applications pending since June 16, 2026.Wells temporary data center moratorium
What this means
If enacted, the measure would temporarily stop new data centers, expansions, and related approvals, including applications pending since June 16, 2026 (moratorium provisions). It would last 180 days, creating a major delay, though the draft leaves the size threshold blank, making the exact scope uncertain (180-day duration).
Timing
- Ends
- 180 days from the Date of Applicability (June 16, 2026)
The moratorium may be extended, repealed, or modified in accordance with applicable law.
People behind it
- Town of Wells
The ordinance states that the Town ordains and enacts the moratorium.
- Code Enforcement Officer
Named as the official responsible for enforcing the ordinance.
Restrictions & requirementsHide restrictions & requirements4
For 180 days from the Date of Applicability, the ordinance bars siting, installing, constructing, establishing, or operating a Data Center, and expanding an existing facility or operation so that it becomes a Data Center. The definition requires an aggregate Data Center Area of at least a square-foot threshold, but that threshold is left blank in the measure. The moratorium and definition
The Town may not accept, process, or act on applications or other requests for a new or expanded Data Center, or issue related permits, licenses, approvals, or decisions, including for applications pending on or after the Date of Applicability. The application and approval restrictions
The moratorium applies retroactively to Data Center proceedings and applications pending at any time on or after June 16, 2026. To the extent permitted by state law, it also nullifies final municipal approvals for new or expanded Data Centers issued within 45 days of the ordinance’s effective date. The retroactive application and 45-day provision
A person who violates the ordinance is subject to civil penalties and other remedies under 30-A M.R.S.A. § 4452. The enforcement and penalty provision