St. Charles Parish

Neutral Data Center Policies

St. Charles Parish allows data centers in M-1 and M-2 zones at least 300 feet from residential districts, with landscaping, screening, and noise limits; continuous onsite power is allowed only in M-2.

current law · County measure
Regulates data centers by allowing them in designated industrial zones based on their power setup and requiring setbacks, landscaping, equipment screening, and noise limits.Louisiana St. Charles Parish Ordinance 2026-0170 (2026)

What this means

The measure clearly allows data centers in M-1 and M-2 zones, giving developers more certainty, but adds setbacks, landscaping and screening, and noise limits; facilities with continuous onsite power are limited to M-2. Since data centers were already not prohibited, the new requirements slightly outweigh the added clarity. Permitted in M-1 and M-2 300 feet from residential districts

People behind it

  • Parish President who introduced and requested the measure.

  • Department identified with the introduction and administration of the measure; it recommended approval.

Restrictions & requirementsHide restrictions & requirements10
  • Data centers without onsite primary energy-generating facilities that provide continuous normal-operation power may be located in M-1, while data centers with such onsite generation are limited to M-2; M-2 energy-generation equipment and fuel storage must also comply with the district’s special provisions. [M-1 and M-2 use restrictions](https://mcclibraryfunctions.azurewebsites.us/api/ordinanceDownload/11599/1433382/pdf?forceDownload=true#:~:text=Data%20Centers%20(without%20onsite%20primary%20energy,Special%20Provisions%20outlined)

  • Primary data-center buildings and equipment must be at least 300 feet from residential zoning districts, school and daycare sites, assisted-living or nursing-home facilities, and parks. Lesser-intensity accessory offices and parking may be located within the setback. 300-foot setback

  • A landscape buffer is required where a data center is adjacent to residential districts, schools or daycares, assisted-living or nursing-home facilities, or parks. The buffer must generally be at least 25 feet deep, contain no structures or parking, and meet specified year-round screening, plant-size, species-diversity, and evergreen-coverage requirements. landscape-buffer requirements

  • A fully planted buffer may be replaced only with a qualifying earthen berm or solid wall at least six feet above adjacent average ground level, with proper slopes, ground cover, and supplemental evergreen trees. berm or wall alternative

  • Landscape plans must be stamped by a licensed landscape architect or horticulturalist for permitting, and a signed completion certification must be submitted after installation. landscape-plan and completion-certification requirement

  • Required visual buffers must be continuously maintained, and failure to maintain them constitutes a zoning-ordinance violation. buffer-maintenance violation

  • Cooling, ventilation, backup-generator, and other ground- or roof-mounted operating equipment must be screened from public roads, residential districts, schools or daycares, assisted-living or nursing-home facilities, and parks using approved enclosures, buildings, solid screens, or qualifying landscape buffers. equipment-screening requirement

  • Noise produced by a data center may not exceed 55 dBA at any property line adjacent to residential or noise-sensitive areas; this standard supersedes less restrictive conflicting laws or ordinances. 55 dBA noise limit

  • Backup generators and similar equipment may be tested only on weekdays between 7:00 a.m. and 6:00 p.m. generator-testing time limit

  • For applying the setback, buffer, screening, and noise rules, a site is treated as adjacent not only when lots share a property line, but also when they would share one except for an undivided road, street, rail line, or drainage conveyance, provided no other parcel lies between them. expanded adjacency definition

Benefits & exceptionsHide benefits & exceptions9
  • Data centers are expressly permitted in M-1 light manufacturing districts when they do not use onsite primary energy-generating facilities supplying continuous power during normal operations.

  • Data centers with onsite primary energy-generating facilities supplying continuous power during normal operations are expressly permitted in M-2 heavy manufacturing districts, subject to the district’s special provisions for energy-generating facilities and fuel storage.

  • Emergency, backup, or redundant generators may independently power an M-1 data center during a primary-power loss or disruption, provided they comply with the ordinance’s requirements.

  • The definition excludes data-processing, storage, retrieval, or communications equipment customarily incidental to an otherwise permitted use, such as servers in an office building, so those ordinary business installations are not regulated as standalone data centers.

  • Accessory uses of lesser intensity, including offices and parking facilities, may be located within the 300-foot setback otherwise required between primary data-center buildings or equipment and specified sensitive uses.

  • Existing vegetation may be used for all or part of the required landscape buffer when it adequately fulfills the buffer’s purpose.

  • A data center may use an earthen berm or solid wall instead of a fully planted buffer if it meets the specified six-foot height, slope, ground-cover, and evergreen-tree requirements.

  • The ordinance provides multiple permissible methods for screening cooling, ventilation, and backup-power equipment, including full enclosures, buildings, solid fences or walls, and qualifying landscape buffers.

  • The required 25-foot landscape buffer may be counted as part of the required minimum setback, allowing the same area to satisfy both requirements.

Sources

Specific to St. Charles Parish only.

failed · County measure
Allows data centers in industrial zones—M-1 if they lack continuous onsite power generation and M-2 if they have it—and requires setbacks, landscaping, screening, and noise limits to protect nearby homes and sensitive places.Louisiana St. Charles Parish File 2026-0114 — Proposed Data Center Moratorium (2026)

What this means

The ordinance would create a clear path for data centers in industrial zones, with data centers permitted in M-1 and M-2. But it also sets significant conditions, including a 300-foot setback near homes and sensitive sites, landscaping and screening rules, and noise limits. Overall, the permitted-use pathway is a modest benefit, partly offset by the requirements.

People behind it

  • Introduced and requested the data-center zoning amendment as Parish President.

  • Identified in connection with the amendment’s introduction and request; the department recommended approval.

  • Listed as a sponsor of the proposed data-center moratorium, which failed.

Show 2 more peopleShow fewer people
  • Listed as a sponsor of the proposed data-center moratorium, which failed.

  • Listed as a sponsor of the proposed data-center moratorium, which failed.

Restrictions & requirementsHide restrictions & requirements8
  • Data centers with onsite primary energy generation supplying continuous power during normal operations are limited to M-2; those without that type of generation may be located in M-1. Emergency, backup, or redundant generation is allowed in M-1 if it meets the section’s requirements. M-2 energy-generating facilities and related equipment, including fuel storage, are also subject to the district’s special provisions. limited to the M-2

  • Primary buildings and equipment must be at least 300 feet from residential zoning districts and the property boundaries of schools, including day-care centers, assisted-living facilities or nursing homes, and parks. Lower-intensity accessory uses, such as offices and parking, may be within the setback area. minimum of three hundred feet

  • A landscape buffer is required where a development is adjacent to residential zoning districts, schools, assisted-living facilities or nursing homes, or parks. It must be at least 25 feet deep, clear of structures and specified uses, and generally consist of layered native trees and shrubs forming a dense, opaque, four-season barrier, subject to detailed planting requirements. Adequate existing vegetation may count toward the buffer. at least 25 feet deep

  • A berm and/or solid wall may replace the fully planted buffer if it is at least six feet above adjacent average ground level, appropriately sloped and planted for stability, and supplemented with appropriately spaced Class A evergreen trees along either side. minimum of six feet above

  • Permitting requires stamped landscape plans by a licensed landscape architect or landscape horticulturalist. After installation, the parish must receive a signed completion certification; failure to maintain the required visual buffer is a zoning violation. stamped landscape plans

  • Ground-mounted and roof-mounted operating and cooling equipment, including backup generators, must be screened from public roadways and the specified nearby sensitive uses to minimize visual and noise impacts. The ordinance lists enclosures, buildings, solid fences or walls, and landscape buffering as screening methods. shall be screened

  • When the stated adjacency conditions apply, data-center noise may not exceed 55 dBA at a property line adjacent to residential or noise-sensitive areas. shall not exceed fifty-five

  • Testing backup power generators and similar equipment is limited to weekdays, between 7:00 a.m. and 6:00 p.m. limited to weekdays

Benefits & exceptionsHide benefits & exceptions3
  • Data centers without onsite primary energy generation supplying continuous power during normal operations are permitted in M-1, subject to the supplemental regulations. [M-1 permitted use](https://mcclibraryfunctions.azurewebsites.us/api/ordinanceDownload/11599/1433382/pdf?forceDownload=true#:~:text=Data%20Centers%20(without%20onsite%20primary%20energy%20generating%20facilities)

  • Data centers with onsite primary energy generation supplying continuous power during normal operations are permitted in M-2; their generating facilities and associated equipment must also meet M-2 special provisions. [M-2 permitted use](https://mcclibraryfunctions.azurewebsites.us/api/ordinanceDownload/11599/1433382/pdf?forceDownload=true#:~:text=Data%20Centers%20(with%20onsite%20primary%20energy%20generating%20facilities)

  • M-1 data centers may have emergency, backup, or redundant generation capable of independently powering the facility during a power loss or disruption, provided it complies with the section’s requirements. Backup generation allowed in M-1

Sources