Oldham County
Anti-Data Center Policies
Oldham County’s enacted ordinance limits data centers to 10 megawatts and 110,000 square feet and requires large setbacks from homes and schools, making development difficult but not banning every project.
current law · County measureLimits data centers to 10 megawatts and 110,000 square feet, with required setbacks from homes and schools and expanded public-notice requirements.Oldham County Data Center Regulations Ordinance (adopted October 6, 2026)
What this means
The measure would sharply limit data centers to 10 megawatts and 110,000 square feet, with large and hyperscale facilities effectively excluded (“limit all data center developments”). It also requires large setbacks from homes and schools, and the county executive said no current site would fit, making development substantially harder without banning every possible project (“no place in this county”).
People behind it
- Oldham County Planning and Zoning Commission
Recommended approval of the data-center regulations in June.
- Oldham County Fiscal Court
Approved the ordinance establishing the regulations.
Restrictions & requirementsHide restrictions & requirements5
Caps data-center power capacity at 10 megawatts. maximum power capacity of 10 megawatts
Limits data-center facilities to 110,000 square feet. capping total square footage
Requires setbacks of 1,000 feet from residential property and 1,500 feet from adjoining school properties. 1,000-foot setback
Removes the large and hyperscale data-center categories; the judge-executive said the rules effectively prevent hyperscale centers in the county for now. effectively bans hyperscale data centers
Adds expanded notification requirements for data-center proposals. expanded notification requirements
Benefits & exceptionsHide benefits & exceptions1
The medium-data-center definition says a facility must meet “one or more” listed criteria, rather than all of them. Residents warned this wording could let a project exceed one threshold if it meets another; the article does not establish how the county will interpret it.
Sources
current law · County measureWould establish a new section of Oldham County’s zoning ordinance specifically governing data centers.Oldham County Proposed Section 250-340: Data Center Regulations (2026)
People behind it
- Oldham County Fiscal Court
Identified as responsible for Ordinance KOC 26-920-7, which proposes creating Section 250-340 of the Oldham County Comprehensive Zoning Ordinance for data centers.
- David Voegele
Named as Oldham County Judge-Executive in the public notice for Ordinance KOC 26-920-7.
- City of Crestwood
Identified as the governmental entity issuing Ordinance No. 5, Series 2026, concerning amendments and additions to the Oldham County Comprehensive Zoning Ordinance.
Show 1 more peopleShow fewer people
- Mayor Jim Kramer
Named as the mayor issuing the City of Crestwood notice for Ordinance No. 5, Series 2026.
Sources
Specific to Oldham County only.
expired · County measurePauses all data center development in Oldham County for 150 days while officials develop data center rules.Oldham County Ordinance KOC 25-910-508 (2025)
What this means
The measure would pause data center development for 150 days, with no exceptions, including applications already filed (pause on all data center development). That would significantly delay building or expanding facilities, though the pause is temporary and the sources do not say it would stop existing centers from operating.
Timing
- Ends
- 150 days after adoption
The measure pauses all data center development for 150 days, without exceptions. No extension condition is stated.
People behind it
- Stephanie Hawkins
Made the motion to approve the 150-day data center moratorium without exemptions.
- Kevin Woosley
Seconded the motion and proposed amendments to the moratorium.
Restrictions & requirementsHide restrictions & requirements2
Imposes a 150-day moratorium on all data center development in Oldham County.
Applies the moratorium to previously filed data center applications, preventing them from progressing during the 150-day period.
Sources
Data provided by Regbase · Cookie preferences · Report missing data