Harvey County

This restriction takes precedence while in effect. The rating below excludes temporary restrictions.

Mixed Data Center Policies

Harvey County has enacted a measure barring applications for and construction of data centers in unincorporated areas until January 1, 2029; it does not clearly stop existing operations and exempts personal, noncommercial systems.

Rating from Kansas statewide as there are no scored current or future laws outside temporary restrictions for Harvey County.

Specific to Harvey County only.

current law · Unincorporated areas
Prohibits establishing, building, operating, or expanding data centers in unincorporated Harvey County and pauses related permit applications until January 1, 2029, unless ended sooner.Harvey County Resolution 2026-4 (2026)

What this means

The measure would pause applications and prohibit establishing or building data centers in unincorporated Harvey County until January 1, 2029, making new projects and expansions substantially harder. It does not clearly require existing data centers to stop operating, and it exempts personal, noncommercial systems.

Timing

Ends
Jan 1, 2029

The moratorium applies to data centers and related activities in the unincorporated areas of Harvey County and remains in effect until January 1, 2029. It may be extended, terminated earlier, or amended by a subsequent resolution.

People behind it

  • Adopted Resolution 2026-04 establishing the data-center moratorium and directing its administration and review.

  • Moved to adopt Resolution 2026-4.

  • Seconded the motion to adopt Resolution 2026-4.

Show 3 more peopleShow fewer people
  • Planning, Zoning & Environmental Director who presented the resolution for consideration.

  • Directed to suspend acceptance and processing of data-center applications and permits and assist with regulatory review and updates.

  • Directed to suspend action on data-center applications and assist with reviewing and updating the Comprehensive Plan and Unified Development Code.

Restrictions & requirementsHide restrictions & requirements4
  • In the unincorporated areas of Harvey County, the Planning and Zoning Department and Planning Commission must suspend accepting or acting on applications and permits for data center operation, development, erection, construction, or related activities. This includes building, site-plan, architectural-review, variance, floodplain-development, conditional-use, grading, rezoning, and occupancy applications or permits. The departments are directed to suspend accepting or acting upon any application or permit

  • The establishment of any data center, including related activities, is suspended and prohibited in the unincorporated areas of Harvey County while the resolution remains in effect. The establishment of any Data Center including related activities

  • The moratorium does not apply to individual data-processing or data-storage systems used by a property owner for personal or private purposes, provided they are not part of a commercial enterprise. not intended to be of a commercial enterprise

  • The moratorium takes effect after adoption and publication in the official county newspaper and remains in effect until January 1, 2029, unless the County Commission later extends, ends early, or amends it by resolution. shall remain in effect until Jan. 1, 2029