The Data Center Divide

Woodbury County

This restriction takes precedence while in effect. The rating below excludes temporary restrictions.

Neutral Data Center Policies

Woodbury County has enacted a 12-month pause on applications to build or expand data centers in unincorporated areas. Existing centers may keep operating, and routine repairs and upgrades that do not expand them are exempt.

Rating from Iowa statewide as there are no scored current or future laws outside temporary restrictions for Woodbury County.

Specific to Woodbury County only.

current law · Unincorporated areas
Prohibits new data-center development applications in unincorporated Woodbury County for 12 months, while allowing existing facilities and routine maintenance.Woodbury County Resolution No. 14064 (2026)

What this means

For 12 months, the measure would block applications to build or expand data centers in unincorporated Woodbury County, creating a major development delay (the moratorium lasts twelve months). Existing facilities could keep operating, and routine repairs and non-expansion upgrades are exempt.

Timing

Ends
twelve (12) months from the date of adoption

The moratorium applies to unincorporated Woodbury County and may be earlier rescinded or extended by subsequent Board resolution.

People behind it

  • Adopted and approved the twelve-month moratorium resolution.

  • Moved approval of the moratorium resolution, chaired the Board, and signed the resolution as chairman.

  • Seconded the motion to approve the moratorium resolution.

Show 3 more peopleShow fewer people
  • Directed to review zoning-permitting procedures for industrial data centers and prepare recommendations for the Board.

  • County staff department directed to conduct the data-center zoning review and develop proposed regulatory standards.

  • Directed to advise on the legal and regulatory implications of proposed zoning changes.

Restrictions & requirementsHide restrictions & requirements1
  • For 12 months from adoption, the County prohibits accepting, processing, considering, or approving any zoning, subdivision, site-plan, conditional-use, building-permit, rezoning, or other development application for any type or class of data center in unincorporated Woodbury County. The prohibition applies broadly to facilities involving centralized digital-data storage, processing, or transmission, including enterprise, colocation, hyperscale, server-farm, and cloud-computing facilities. It does not apply to legally operating existing facilities, applications with all required final approvals before the resolution took effect, or routine maintenance, repairs, or non-expansion upgrades to existing lawful facilities.

Benefits & exceptionsHide benefits & exceptions3
  • Legally established data centers already in operation are exempt from the moratorium and may continue operating.

  • Applications that received all required final approvals before the resolution took effect are exempt from the moratorium and may proceed.

  • Existing lawful data centers may undergo routine maintenance, repairs, and upgrades, provided the work does not expand the facility or establish a new data-center use.