Story County
This restriction takes precedence while in effect. The rating below excludes temporary restrictions.
Neutral Data Center Policies
Story County’s enacted pause blocks new data-center applications and permits in unincorporated areas until March 31, 2027, making development harder; it does not require existing centers to stop operating. Separate operating rules were removed from Ordinance 330.
Rating from Iowa statewide as there are no scored current or future laws outside temporary restrictions for Story County.
Specific to Story County only.
current law · Unincorporated areasExcludes the proposed data-center zoning rules from Ordinance 330, while a separate county resolution pauses data-center applications and permits through March 31, 2027.Story County Ordinance No. 330 (2026)
What this means
The Board removed the proposed data-center rules from Ordinance 330, so those extra operating requirements would not take effect under this ordinance (data-center standards removed). But a separate resolution extends a pause on data-center applications and permits until on or before March 31, 2027, which makes building or expanding substantially harder in the meantime (moratorium expiration).
Timing
- Ends
- on or before 2027-03-31
Resolution #26-69 extends the moratorium on accepting applications or issuing permits for digital asset mining, cryptocurrency operations, and data processing centers in unincorporated Story County while regulations are developed. The moratorium expires on or before 2027-03-31. Ordinance No. 330 separately regulates battery/energy storage systems; the moratorium resolution does not expressly include battery storage.
People behind it
- Story County Planning and Development
Applicant and county department responsible for proposing and administering the text amendment.
- Leanne Harter
Director of Story County Planning and Development and staff project manager who prepared, presented, and recommended Ordinance No. 330.
Restrictions & requirementsHide restrictions & requirements1
Temporary moratorium on accepting applications for, or issuing permits to, digital asset mining operations, cryptocurrency operations, and/or data processing centers in unincorporated Story County. The moratorium expires on or before March 31, 2027.
Sources
current law · Unincorporated areasProhibits Story County from accepting applications or issuing permits for data processing centers in unincorporated areas through March 31, 2027.Story County Resolution #26-69 (2026)
What this means
The measure would block new data-center applications and permits in unincorporated Story County until March 31, 2027, making new development substantially harder during that period (no applications or permits). It does not say existing data centers must stop operating, and it applies only to unincorporated areas.
Timing
- Ends
- Mar 31, 2027
The temporary moratorium applies to digital asset mining, cryptocurrency operations, and data processing centers on properties in unincorporated Story County. It expires on or before 2027-03-31.
People behind it
- Story County Board of Supervisors
Adopted Resolution #26-69 establishing the temporary moratorium.
- Leanne Harter
Prepared the resolution and, as Director of Planning and Development, reported on and administered the moratorium proposal.
- Story County Planning and Development Department
Developed the proposed regulations and was directed to develop and bring forward the temporary moratorium.
Show 5 more peopleShow fewer people
- Story County Attorney’s Office
Consulted with the Planning and Development Department in developing the temporary moratorium.
- Latifah Faisal
Moved approval of Resolution #26-69.
- Linda Murken
Seconded the motion to approve Resolution #26-69.
- Chairperson, Board of Supervisors
Authorized and directed to certify the resolution for recording.
- County Auditor
Authorized and directed to certify the resolution for recording.
Restrictions & requirementsHide restrictions & requirements1
A temporary moratorium prohibits Story County from accepting applications for or issuing permits for data processing centers on properties in unincorporated Story County, effective upon passage on March 17, 2026, through March 31, 2027.
Sources
expired · Unincorporated areasProhibits Story County from accepting applications or issuing permits for data centers in unincorporated areas through March 31, 2026.Story County Resolution #26-39 (2025)
What this means
The measure would pause accepting applications and issuing permits for data centers in unincorporated Story County until March 31, 2026 (moratorium effective until March 31, 2026). That blocks new development in the affected area while the pause is in force, though its short duration and limited geographic scope keep it from being a permanent ban.
Timing
- Ends
- Mar 31, 2026
The resolution extends the moratorium on accepting applications and issuing permits for digital asset mining, cryptocurrency operations, data processing centers, and battery/energy storage solutions in unincorporated Story County through 2026-03-31. The extension was authorized if additional time was needed to complete the County's review and recommendation process.
People behind it
- Leanne Harter
Prepared Resolution 26-39.
- Story County Planning and Development Department
Requested the additional time and facilitated the review and approval process.
- Story County Board of Supervisors
Adopted and approved the resolution extending the moratorium through March 31, 2026.
Show 2 more peopleShow fewer people
- Chairperson, Board of Supervisors
Authorized to certify the resolution for recording.
- County Auditor
Authorized and directed to certify the resolution for recording.
Restrictions & requirementsHide restrictions & requirements1
A temporary moratorium bars Story County from accepting applications or issuing permits specifically for data processing centers on properties in unincorporated Story County. The moratorium took effect upon adoption on November 25, 2025, and remains in effect through March 31, 2026.
Sources
expired · Unincorporated areasProhibits Story County from accepting applications or issuing permits for data processing centers in unincorporated areas through December 31, 2025, with a possible extension to March 31, 2026.Story County Resolution #25-97 (2025)
What this means
If enacted, the measure would block new permit applications and permits for data processing centers in unincorporated Story County until December 31, 2025, with a possible extension through March 31, 2026 (moratorium terms). It would not itself stop existing data centers from operating, but it would create a major temporary barrier to building or expanding them in the affected area.
Timing
- Ends
- Dec 31, 2025
The moratorium applies to applications and permits for digital asset mining, cryptocurrency operations, data processing centers, and battery/energy storage solutions in unincorporated Story County. It may be extended one time by Board resolution through 2026-03-31.
People behind it
- Leanne Harter
Story County Planning and Development Director who prepared the memorandum and proposed the temporary moratorium for Board consideration.
- Story County Planning and Development Department
County department that developed and administered the proposed moratorium and related land-development-regulation review.
- Latifah Faisal
Story County supervisor who moved approval of Resolution #25-97.
Show 2 more peopleShow fewer people
- Linda Murken
Story County supervisor who seconded approval of Resolution #25-97 and presided over its adoption.
- Story County Board of Supervisors
Governing body that adopted and enacted Resolution #25-97.
Restrictions & requirementsHide restrictions & requirements1
A temporary moratorium prohibits Story County from accepting applications or granting permits for data processing centers on properties in unincorporated Story County. It took effect upon adoption on June 17, 2025, and lasts through December 31, 2025, with a possible one-time extension by Board resolution through March 31, 2026.
Sources
Data provided by Regbase · Cookie preferences · Report missing data