Neutral Data Center Policies

Palo Alto County’s enacted moratorium bars data center applications and construction, including conversions, in unincorporated areas until July 8, 2027, or sooner if a regulating ordinance passes.

Rating from Iowa statewide as there are no scored current or future laws outside temporary restrictions for Palo Alto County.

Specific to Palo Alto County only.

current law · Unincorporated areas
Prohibits new data center applications, construction, installations, and conversions in unincorporated Palo Alto County until July 8, 2027, or until the county adopts data center regulations, whichever comes first.Palo Alto County Board of Supervisors Resolution No. 7-8-2026

What this means

The measure would stop the county from accepting or approving data center applications and prohibit construction, including converting existing buildings, in unincorporated Palo Alto County. The moratorium would last until July 8, 2027, or until a regulating ordinance is passed sooner, making this a severe but temporary restriction.

Timing

Ends
2027-07-08, or earlier upon passage of an ordinance regulating data centers

The Board may extend the moratorium as permitted by law if substantial deficiencies remain in the comprehensive review and additional time is necessary to complete the work and protect the public.

People behind it

  • Moved to introduce and approve Resolution No. 7-7-2026 concerning the transfer of funds; seconded the motion to introduce and approve Resolution No. 7-8-2026 concerning the data-center moratorium.

  • Seconded the motion to introduce and approve Resolution No. 7-7-2026 concerning the transfer of funds.

  • Moved to introduce and approve Resolution No. 7-8-2026 concerning the data-center moratorium.

Show 4 more peopleShow fewer people
  • County Attorney who presented the resolution establishing the data-center moratorium.

  • Governmental body that introduced, approved, and adopted the resolutions.

  • County Auditor authorized to administer the funds transfer, correct the books, and notify the County Treasurer.

  • Directed to review data-center regulations, develop recommendations, and support the moratorium’s implementation.

Restrictions & requirementsHide restrictions & requirements3
  • A temporary moratorium immediately prohibits the acceptance, processing, consideration, and approval of any zoning, subdivision, site-plan, conditional-use, building-permit, rezoning, or other development application for any type or class of data center in the unincorporated areas of Palo Alto County. It lasts until July 8, 2027, or until an ordinance regulating data centers is enacted, whichever occurs first, and may be extended as permitted by law.

  • No data center facilities or related appurtenances may be constructed or installed in the unincorporated areas during the moratorium, including renovation of existing structures for use as data centers.

  • The restrictions apply broadly to facilities used for centralized digital-data storage, management, processing, or transmission, as well as facilities involving high-density servers, specialized cooling, related digital infrastructure, or energy-storage systems. The definition expressly includes enterprise, colocation, hyperscale, server-farm, cloud-computing, and similar facilities.