Johnson County
This restriction takes precedence while in effect. The rating below excludes temporary restrictions.
Neutral Data Center Policies
Johnson County has enacted a temporary pause on data-center approvals and building permits in unincorporated areas through August 8, 2027, delaying new projects and expansions.
Rating from Iowa statewide as there are no scored current or future laws outside temporary restrictions for Johnson County.
Specific to Johnson County only.
current law · Unincorporated areasProhibits Johnson County from approving zoning, subdivision, or site-plan applications or issuing building permits for data centers in unincorporated areas until August 8, 2027, unless the county ends the moratorium sooner.Johnson County, Iowa Extension of Temporary Data Center Moratorium (2026)
What this means
The measure would extend a moratorium blocking approvals and building permits for data centers in unincorporated Johnson County until August 8, 2027, making new projects and expansions that need those approvals substantially harder and delaying them. It does not ban data centers permanently or appear to restrict existing operations, but the delay is significant.
Timing
- Ends
- 2027-08-08 at 11:59:59 p.m. Central Time
The moratorium applies to approvals of rezoning, subdivision, or site plan applications and the issuance of building permits related to data centers in unincorporated Johnson County. It may end earlier if the Unified Development Ordinance amendments are completed and the Board determines the issues are satisfactorily resolved, and it may be extended by further Board action.
People behind it
- Johnson County Board of Supervisors
Proposed, adopted, approved, and administered the resolutions and related measures.
- Fixmer-Oraiz
Explicitly moved or seconded adoption of multiple resolutions.
- Sullivan
Explicitly moved or seconded adoption of multiple resolutions.
Show 59 more peopleShow fewer people
- Remington
Explicitly moved or seconded adoption of multiple resolutions.
- Green-Douglass
Explicitly moved or seconded adoption of multiple resolutions.
- Johnson County Planning and Zoning Commission
Reviewed development applications, conducted public hearings, and recommended actions to the Board.
- Johnson County Planning, Development, and Sustainability Department
Prepared proposed fireworks ordinance amendments and drafted data-center regulations.
- Johnson County Auditor
Directed to publish notices, maintain proposed plans, administer filings, and perform election-related duties for multiple measures.
- Julie Persons
Johnson County Auditor responsible for administering and publishing notices and election-related materials.
- Johnson County Engineer
Designated as Title VI Coordinator and responsible for road, bridge, traffic-count, weight-limit, and construction-project administration.
- Paul Wittau
County Engineer authorized to execute contracts for specified secondary-road projects.
- County Engineer
Designated as the County’s Title VI Coordinator and assigned compliance, complaint, training, and agency-coordination duties.
- County Zoning Administrator
Authorized to issue permits and approve fireworks permits under the applicable resolutions.
- Finance Director
Authorized to make the budgeted interfund transfers established by the FY27 resolutions.
- Johnson County Commissioner of Elections
Appointed to conduct the Lisbon–Mount Vernon emergency medical services district election.
- Board Office Executive Director
Directed to transmit the construction evaluation resolution to the Iowa Department of Natural Resources.
- Snyder & Associates
Appointed to prepare the preliminary plat and engineer’s report for the Lisbon–Mount Vernon emergency medical services district.
- City of Iowa City
Selected as project partner and proposed recipient and operator of 1102 Hollywood Boulevard for affordable veteran housing.
- Metropolitan Planning Organization of Johnson County
Conducted and supplied the updated 2026 traffic-count study used by the County.
- M-C Holdings LLC
Filed a platting application considered in the development-resolution process.
- Patience, LLC
Filed a platting application considered in the development-resolution process.
- Irakliy G Surguladze
Filed a platting application considered in the development-resolution process.
- Jerry E. Wear
Filed a zoning and platting application with Vicki D. Wear.
- Vicki D. Wear
Filed a zoning and platting application with Jerry E. Wear.
- Jeffrey Swan
Filed applications on behalf of Blue Stem Properties, L.L.C.
- Blue Stem Properties, L.L.C.
Applicant for zoning and platting approvals.
- Kathy M. Shebetka
Filed a platting application considered in the development-resolution process.
- Jed Schnoor
Submitted the Belvedere site-plan application.
- Belvedere, Inc.
Applicant and property owner for the Commerce Court Addition site plan.
- T.J. Trudeau
Submitted the site-plan application for E-C IA Investments LLC.
- E-C IA Investments LLC
Applicant and owner for the JoCo 380 Business Park site plan.
- Michael Accola
Submitted the site-plan application for 2626 Ders Drive NW.
- TWS Buildings, LLC
Submitted the site-plan application for 4995 Waterway Lane SW.
- Blake Hershberger Enterprises
Submitted the site-plan application for Lots 5 and 6 of JoCo 50 Subdivision.
- Carex Properties LLC
Submitted the site-plan application for 3182 IWV Road SW.
- James Arkema
Submitted the application to amend the Johnson County Future Land Use Map.
- Hickory Haven Properties, L.L.C.
Submitted zoning and platting applications.
- Steve Rohret
Submitted a zoning application considered in the development-resolution process.
- Elizabeth Kling
Submitted applications on behalf of the Estate of James M. Yoder.
- Estate of James M. Yoder
Property applicant for zoning and platting approvals submitted through Elizabeth Kling.
- Prairie Coneflower Ranch, LLC
Submitted a platting application considered in the development-resolution process.
- Oberman Farms
Submitted a platting application, signed by Sue Strause Klinger & Associates P.C.
- Sue Strause Klinger & Associates P.C.
Signed and submitted the Oberman Farms platting application.
- James Calef
Submitted the application for Calef Second Subdivision.
- Aaron Swartzentruber
Submitted the Swartzentruber Acres platting application with Jessica Swartzentruber.
- Jessica Swartzentruber
Submitted the Swartzentruber Acres platting application with Aaron Swartzentruber.
- Lynn J. Novotny
Submitted a platting application with Cynthia R. Novotny.
- Cynthia R. Novotny
Submitted a platting application with Lynn J. Novotny.
- Kevin W. Agan Monson
Submitted a platting application with Julie Agan Monson.
- Julie Agan Monson
Submitted a platting application with Kevin W. Agan Monson.
- Brandon Pratt
Submitted zoning and platting applications.
- Robert W. Howe
Submitted the Howe Woods platting application.
- Todd Scott
Submitted a zoning application on behalf of River Products Company Inc.
- River Products Company Inc.
Applicant for the zoning application submitted through Todd Scott.
- Taylor Getting
Submitted zoning and platting applications.
- Luke Mayhew
Submitted a zoning application considered in the development-resolution process.
- Mark Slabaugh
Submitted a platting application considered in the development-resolution process.
- Richard Loan
Submitted a zoning and platting application.
- Jeffrey B. Adams
Submitted the petition to vacate the preliminary and final plat of Kings Estate.
- Dean Stockman
Submitted a platting application considered in the development-resolution process.
- Lisbon–Mount Vernon Ambulance Service
Initiated the petition process for the benefited emergency medical services district.
- Jacob Lindauer
Ambulance Service Director identified as the petitioner for the Lisbon–Mount Vernon emergency medical services district.
Restrictions & requirementsHide restrictions & requirements1
Extends an immediate moratorium in unincorporated Johnson County on approving rezoning, subdivision, or site-plan applications and issuing building permits for the siting or construction of data centers. The moratorium expires at 11:59:59 p.m. Central Time on August 8, 2027, unless extended, but the Board may end it earlier after completing related Unified Development Ordinance amendments and resolving the relevant issues.
Benefits & exceptionsHide benefits & exceptions1
Data centers are recognized as an allowed use in the MH-Heavy Industrial zoning district, subject to approval of a site plan and issuance of building permits. This authorization is limited by the temporary moratorium, which pauses approvals and permit issuance for data centers in unincorporated Johnson County until 11:59 p.m. on August 8, 2027, unless the Board ends or extends the moratorium earlier.
Sources
current law · Unincorporated areasProhibits Johnson County from approving data center rezoning, subdivision, site plans, or building permits in unincorporated areas until November 8, 2026, unless the moratorium ends earlier or is extended.Johnson County, Iowa Resolution No. 11-06-25-01—Temporary Data Center Moratorium (2025)
What this means
The measure would pause approvals and building permits for data centers in unincorporated Johnson County until November 8, 2026, making it very difficult to start or expand a project during that period (temporary moratorium). The proposed zoning rules would allow data centers in certain districts, but add substantial requirements, including large setbacks, noise limits, closed-loop cooling, and power and fire-safety reviews (all Data Centers are subject to these conditions).
Timing
- Ends
- 2026-11-08 at 23:59 Central Time
The temporary moratorium on approvals and building permits for data centers in unincorporated Johnson County expires at 11:59 p.m. Central Time on 2026-11-08, unless extended by further Board action. The Board may also end it earlier after completing the Unified Development Ordinance amendments and satisfactorily resolving the related issues.
People behind it
- Johnson County Board of Supervisors
County legislative body responsible for considering and adopting the Unified Development Ordinance amendment.
- Johnson County Planning and Zoning Commission
County planning body identified as responsible for considering the proposed Unified Development Ordinance changes.
- Johnson County Planning, Development and Sustainability staff
Staff responsible for recommending an alternate variance-language amendment to the proposed ordinance.
Restrictions & requirementsHide restrictions & requirements17
A temporary moratorium prohibits approval of rezoning, subdivision, and site-plan applications, and issuance of building permits, for data centers in unincorporated Johnson County. It took effect immediately and expires at 11:59 p.m. Central Time on November 8, 2026, unless extended or ended earlier by the Board. temporary moratorium
Data centers with a total use area of one acre or less are only conditionally permitted in the Agricultural district, while data centers larger than one acre are allowed as primary uses only in the Light Industrial and Heavy Industrial districts. one%20acre%20or%20less
Non-adjacent data-center areas within one-half mile may be treated as a cumulative use area, potentially moving a project into the larger-than-one-acre approval category. considered cumulative
Data-center operations in the Agricultural district require Site Plan Review approved by the Zoning Administrator before a building permit may be obtained. prior to obtaining a building permit
Under the existing approval framework described in the Board minutes, data centers in the Heavy Industrial district require Board consideration and action on a site plan, in addition to associated building permits. subject to consideration and action of a Site Plan
All data-center production equipment must be enclosed in structures that comply with the Building Code, placed on permanent foundations, and converted to real property for tax purposes. enclosed with a structure
Data-center structures must be set back at least 200 feet from property lines and 500 feet from occupied structures. two hundred feet
Before a building permit is issued, the applicant must obtain written verification from the proposed power provider that maximum electrical demand has been calculated and that the utility equipment and infrastructure can safely handle the demand during peak hours. written verification from their proposed power provider
Any electricity generated on site for a data center must come from renewable power-generation sources. generated by renewable power generation sources
On-site power and communication lines must be placed underground to the extent feasible and permitted by the utility; connections at the utility right-of-way and certain interconnection equipment may remain above ground. placed underground to the extent feasible
Data centers must meet property-line noise limits that vary by receiving zoning district and time of day, including 60 dBA daytime and 50 dBA nighttime in specified residential districts. Applicants must provide sound measurements from comparable facilities, and additional measurements may be required after complaints. noise levels as measured at the property line
Applicants must show that the local fire department can reasonably service the site, clear combustible vegetation within 25 feet of data-center structures, obtain approval of emergency-operations procedures before operations begin, provide those procedures to emergency officials, and maintain them on site. the site can be reasonably serviced
The site operator must offer or provide annual fire-safety and emergency-response training for five years after construction, and thereafter if requested by the local Emergency Management Agency, no more than once annually. annual basis for five years
Data-center equipment must use a closed-loop cooling system. closed-loop cooling system
A proposed Tier 2 Battery Energy Storage System must be permitted under the Unified Development Ordinance's separate Tier 2 battery-storage regulations. permitted in accordance with Chapter 8:1.24.F
Data centers must comply with the County's downcast-lighting rules, all Environmental Standards in Chapter 8:3, and all other applicable federal, state, and local regulations. all Environmental Standards in Chapter 8:3
The maximum height for primary and accessory structures in both the Light Industrial and Heavy Industrial districts is set at 50 feet, limiting the height of data-center structures in those districts. 50 feet
Benefits & exceptionsHide benefits & exceptions6
Data centers with a total use area of more than one acre are allowed as primary uses in the ML Light Industrial and MH Heavy Industrial districts, providing a direct zoning path without a conditional-use approval. (allowed as primary uses in the ML Light Industrial and MH Heavy Industrial districts)
Data centers with a total use area of one acre or less are conditionally permitted in the Agricultural district, creating a permitting route for smaller facilities. (Data Centers with a total use area of one acre or less are conditionally permitted in the A - Agricultural district)
For data centers in the Agricultural district, site-plan review is handled by the Zoning Administrator before a building permit, rather than by the Board of Supervisors. (Operations in the A-Agricultural district shall require a Site Plan Review approved by the Zoning Administrator)
The amendment expressly adds data centers as a permitted primary use in the ML Light Industrial district and replaces the MH district's cryptocurrency-mining-specific listing with the broader Data Centers category, allowing a wider range of data-processing facilities. (Data Centers)
The ordinance raises the maximum height for primary and accessory structures in both the ML and MH districts to 50 feet, allowing taller data-center buildings or equipment enclosures. (50 feet)
The data-center definition expressly includes High Density Computing Facilities, including commercial cryptocurrency-mining operations and processing, preserving eligibility for those types of facilities under the broader data-center rules. (including but not limited to commercial cryptocurrency mining operations and processing)
Sources
current law · Unincorporated areasPauses data-center rezoning, subdivision, site-plan approvals, and building permits in unincorporated Johnson County until November 8, 2026, while the county considers new rules.Johnson County, Iowa Omnibus UDO Amendment—Data Center Provisions (2025)
What this means
The moratorium would temporarily block approvals and building permits for data centers in unincorporated Johnson County until November 8, 2026. Although the proposed zoning changes provide a path to build, they impose substantial conditions, so the temporary halt is the stronger near-term effect.
Timing
- Ends
- 2026-11-08 at 11:59 p.m. Central Time
The temporary moratorium expires at the stated time unless extended by further action of the Board of Supervisors. The Board may also end it earlier after completing the Unified Development Ordinance amendments and resolving the relevant issues.
People behind it
- Mandi Remington
Introduced the motion to approve Resolution No. 11-06-25-01, establishing the data-center moratorium.
- Lisa Green-Douglass
Seconded the motion to approve Resolution No. 11-06-25-01, establishing the data-center moratorium.
- Johnson County Board of Supervisors
Adopted Resolution No. 11-06-25-01 establishing the temporary data-center moratorium and is the body responsible for considering the related Unified Development Ordinance amendments.
Restrictions & requirementsHide restrictions & requirements16
A temporary moratorium immediately bars approval of rezoning, subdivision, or site-plan applications and the issuance of building permits for data-center siting or construction in unincorporated Johnson County until 11:59 p.m. on November 8, 2026, unless ended earlier or extended by the Board of Supervisors.
Data centers with a total use area of one acre or less are conditionally permitted only in the A–Agricultural district, and operations there require Zoning Administrator site-plan approval before a building permit may be issued.
Data centers with a total use area greater than one acre are allowed as primary uses only in the ML–Light Industrial and MH–Heavy Industrial districts.
The data-center use area includes all associated fences, structures, stormwater facilities, parking, landscaping, and other related areas; at the Zoning Administrator’s discretion, non-adjacent areas within one-half mile may be counted together when determining whether conditional-use or rezoning approval is required.
All data-center production equipment, including computers and servers, must be enclosed in structures that comply with the Building Code, be placed on permanent foundations, and be converted to real property for property-tax assessment.
Data-center structures must be at least 200 feet from all property lines and 500 feet from occupied structures.
Before a building permit is issued, the applicant must provide written verification from the proposed power provider that maximum electrical consumption has been calculated and that utility-supply equipment and related infrastructure can safely accommodate the use during peak demand.
Any electricity generated onsite for a data center must come from renewable power-generation sources.
Onsite power and communication lines must be installed underground to the extent feasible and allowed by the servicing utility; lines connecting onsite systems to offsite structures must also be buried to that extent.
Data-center operating noise may not exceed the specified property-line limits: 60 dBA during daytime and 50 dBA at night for A, AR, SF, R, RM, RC, and RMH receiving districts; 65 dBA at all listed times for C, CH, Ag-T, and C-Ag; and 70 dBA at all listed times for ML, MH, RR, SWDRR, RE, ERP, and P.
At permitting, the applicant must provide operating sound-pressure measurements from comparable data-center locations to demonstrate compliance with the noise limits; if a complaint is made, the Zoning Administrator may require the owner to commission property-line measurements for the operating facility.
The applicant must obtain a determination from the local fire department that the site can be reasonably serviced, keep areas within 25 feet of data-center structures free of combustible vegetation and growth, and obtain Zoning Administrator approval of emergency-operations procedures before operations begin.
Emergency-operations procedures must be provided to the local fire department and Johnson County Emergency Management, kept onsite for personnel and responders, and the operator must offer or provide fire-safety and emergency-response training annually for five years after construction, with later training offered if requested no more than once annually.
Data-center equipment must use a closed-loop cooling system.
A proposed Tier 2 Battery Energy Storage System must be permitted under the ordinance’s separate Battery Energy Storage System requirements.
Data centers must comply with the ordinance’s downcast-lighting requirements and all environmental standards in Chapter 8:3.
Benefits & exceptionsHide benefits & exceptions6
Data centers are expressly allowed in multiple zoning contexts: systems with a total use area of one acre or less are conditionally permitted in the A Agricultural district, while data centers larger than one acre are allowed as primary uses in the ML Light Industrial and MH Heavy Industrial districts. The one-acre limit may also apply to data centers listed in Article 8:1.6.C. (Data Centers with a total use area of one (1) acre or less)
For data centers in the Agricultural district, approval requires Site Plan Review by the Zoning Administrator before a building permit, rather than a separate rezoning approval, when the use area is one acre or less. (Operations in the A-Agricultural district shall require a Site Plan Review)
The amendment establishes a maximum height of 50 feet in the applicable data-center zoning tables, allowing taller facilities than would be permitted under a lower height limit. (50 feet)
A Tier 2 Battery Energy Storage System proposed as part of a data center may be permitted under the UDO's existing battery-energy-storage regulations, allowing the facility to include qualifying energy-storage equipment. (the proposed BESS shall be permitted)
The power and communications provisions allow on-site lines to be placed underground only to the extent feasible and permitted by the utility, and expressly allow the main utility connection and new interconnection equipment to be above ground. This provides flexibility for connecting a data center to the electrical and communications systems. (may be located above ground)
The amendment establishes numerical operating-noise limits for data centers, including 60 dBA during daytime and 50 dBA at night when the receiving property is in specified residential districts, with higher limits for commercial, agricultural, industrial, and other listed districts. (7:00 am – 9:59 pm)