Grant County
This restriction takes precedence while in effect. The rating below excludes temporary restrictions.
Mixed Data Center Policies
Grant County’s enacted measures describe temporary data-center pauses—one up to a year, though its account also calls it proposed; another bars new permits in unincorporated areas for up to two years.
Rating from Indiana statewide as there are no scored current or future laws outside temporary restrictions for Grant County.
Specific to Grant County only.
current law · County measureProposes a temporary pause of up to one year on data centers in Grant County, pending consideration by local lawmakers.Indiana Area Plan Commission Resolution supporting data-center moratorium (2026)
What this means
If enacted, the proposed moratorium could temporarily stop new data center development in Grant County for up to a year, making building or expanding substantially harder during that period (up to one year or until a local ordinance is adopted). The source says the resolution still needed to be sent to county and local lawmakers for consideration, so it is not already law.
Timing
- Ends
- Up to one year or until a local ordinance is adopted
The data-center moratorium ends after up to one year or when a local ordinance is adopted; a separate action is required to lift it. The battery-energy-storage moratorium was supported, but its expiration or extension conditions are not specified.
People behind it
- Grant County Area Plan Commission
Approved motions supporting the proposed data-center and battery-energy-storage-system moratoria and forwarded the resolutions for consideration as ordinances.
Restrictions & requirementsHide restrictions & requirements1
A proposed moratorium on data centers would last up to one year or until a local ordinance is adopted, and a separate action would be required to lift the moratorium.
Sources
current law · Unincorporated areasProhibits data center development in unincorporated Grant County until March 16, 2028, or until new zoning rules are adopted, whichever comes first; Marion is excluded.Indiana Ordinance 4-2026 (2026)
What this means
The measure would stop new data-center permits in unincorporated Grant County for up to two years, making building or expanding projects there substantially harder. It is limited to unincorporated areas, so it is not a countywide ban on data centers.
Timing
- Ends
- 2028-03-16, or when the county adopts a zoning amendment or new zoning ordinance governing data centers, whichever comes first
The data-center moratorium applies only to unincorporated Grant County. A separate code provision concerning suspension resolutions sets a maximum duration of six months; how it relates to this moratorium is unclear.
People behind it
- Ron Stewart
Introduced the idea of a moratorium to fellow commissioners and moved the proposal for a 24-month moratorium.
- Shane Middlesworth
Seconded the motion for the 24-month moratorium.
- Martin Harker
Drafted and explained the moratorium ordinance.
Show 4 more peopleShow fewer people
- Marty Barker
Reportedly drafted the moratorium ordinance.
- Board of Commissioners
Approved and passed the moratorium ordinance.
- APC
Was assigned responsibility for writing a data center ordinance under the moratorium.
- Grant County plan commission’s data center subcommittee
Drafted the zoning amendment governing data centers.
Restrictions & requirementsHide restrictions & requirements10
A 24-month moratorium bars data-center development and improvement-location permits on unincorporated land, through March 16, 2028, or until the county adopts a data-center zoning amendment, whichever comes first. It does not apply within Marion or other incorporated jurisdictions. Moratorium details
A data center must be an authorized use in its zoning district: uses marked “X” are permitted, uses marked “S” require a Board of Zoning Appeals special exception, and blank entries are not allowed. The Director classifies unlisted uses based on similarity to listed uses and consistency with the district’s intent. Authorized-use classifications
A special exception requires a public hearing and findings that the use is allowed in the district, meets applicable requirements, and will not substantially and permanently injure neighboring property. Special-exception review
Construction requires a valid building permit before work begins. Applications must include scaled plans and specifications and generally a scaled plot plan; a state design release and other information may also be required. Building permit required
Construction must comply with adopted building rules and applicable codes and is subject to inspections. A reinspection fee may apply if work is not ready for inspection, and must be paid before a certificate of occupancy is issued. Reinspection fees
A data-center structure may not be occupied until a certificate of occupancy has been issued. Certificate of occupancy
Contractors and subcontractors performing construction or demolition in the county’s participating jurisdictional area must register annually and pay a fee. Property owners and tenants working on their own property are exempt. Contractor registration
Structures generally may not be erected within 75 feet of the meander or high-water line of a county-maintained ditch, stream, or other water body. Fences and structures required for a public utility are exceptions. Stream setback
Outdoor lighting must avoid disabling or nuisance glare; directional fixtures may not shine directly into neighboring residence windows, roadways, or the sky. Outdoor-lighting requirements
Land filling outside a flood hazard area must meet federal, state, and local requirements. Discharging liquid or solid waste into public waters is prohibited except as permitted by those requirements. Environmental standards
Benefits & exceptionsHide benefits & exceptions3
A qualifying project may seek planned-unit-development (PUD) approval for development flexibility and integrated planning intended to reduce the burden on existing streets and utilities. Approval requires consistency with the County Comprehensive Plan and no undue detrimental influence on surrounding properties.
Tax increment financing (TIF) can direct taxes on assessed value above a district’s base value to the redevelopment commission for infrastructure in the district or to repay infrastructure debt. For the interchange area, the base date was set at January 1, 2025, but the tax-capture plan still needs remaining approvals; the west-side map was not approved as presented. Taxes on value above the base
An economic development area can be established without finding that the land is blighted, lowering an eligibility hurdle for tools such as TIF. The county’s resolutions began a multi-step approval process, and the west-side map was not approved as presented. Requires no finding that the ground is blighted