Loading map…

City of Troy

Anti-Data Center Policies

Troy allows data centers only in I-2 industrial zones with a special-use permit, large setbacks, and noise limits. Detailed plans and studies, plus a road-maintenance agreement, add hurdles to building or expanding facilities.

current law · City of Troy
Requires data centers to obtain a special-use permit, locate in industrial zones, and meet rules for setbacks, noise, landscaping, lighting, environmental reviews, and road repairs.Ohio Troy Ordinance 2025-46 (2025)

What this means

The measure would allow data centers, but only in I-2 industrial zones and with a special-use permit, plus large setbacks and noise limits (permitted only in I-2). It also requires extensive plans and studies and a road-maintenance agreement, creating significant hurdles for building or expanding facilities (submittal requirements).

People behind it

  • Reviewed and recommended adoption of the data-center regulations (recommended adoption).

  • Adopted the ordinance establishing the data-center regulations (adopted by the City Council).

Restrictions & requirementsHide restrictions & requirements13
  • Data centers may be located only in the I-2 General Industry district and require a special use permit. The permit review considers impacts such as nearby uses, traffic, utilities, noise, site design, and signage. The district and permit requirement

  • The ordinance requires minimum setbacks: 100 feet from a public right-of-way, 50 feet for building side and rear yards, and 200 feet from any district where residential dwellings are permitted. Setback standards

  • Building height must comply with the I-2 district rules; additional height considerations and setbacks may be imposed as a special-use-permit condition. Buildings and visible accessory structures must also meet specified design and screening standards. Height and design requirements

  • Setback areas are subject to landscaping requirements, including a six-foot minimum berm where it can fit, native planting and restoration, and at least one tree per 400 square feet of screening area, subject to specified alternative-plan approval. Landscaping and tree-density requirements

  • Fences may not exceed 12 feet; security fencing in setback areas cannot use barbed or razor wire. A masonry or decorative-concrete sound wall may be used around utility areas or for noise mitigation, but cannot exceed 24 feet. Fence and sound-wall limits

  • Visible mechanical equipment and major equipment such as cooling towers and generators must be screened; public-facing service and loading areas require opaque screening at least eight feet high. Equipment and loading-area screening

  • Stationary noise is limited to 60 dB by day and 55 dB at night next to residential land uses, and 70 dB at any time next to nonresidential uses. Discrete-tone or impulsive noise lowers the applicable limit by 5 dB; both together lower it by 10 dB. The ordinance requires a pre-construction sound study, mitigation if operations exceed limits, and allows the city to obtain or require a follow-up study within six months after a building’s certificate of occupancy. Noise limits and follow-up study

  • Parking and circulation must comply with city standards; gated parking must prevent queues from reaching public streets and be located behind the building. Parking is prohibited on public streets and access roads. Parking restrictions

  • Lighting is subject to limits on shielding and upward light output; accent lighting must be directed downward, and freestanding fixtures within 300 feet of a property line cannot exceed 18 feet. Nighttime strobe lighting is limited to red safety lighting. Lighting restrictions

  • Applicants must submit a broad set of materials, including ownership and survey documents, environmental-review results, applicable historic-preservation and noise-compliance information, site and screening plans, utility-interconnection evidence, an operations and maintenance plan, proof of insurance, and a preliminary emergency-services plan. An executed agricultural-impact-mitigation agreement is also required. Application submittal requirements

  • The application fee is calculated using the city’s commercial permit fee schedule: 0.0045 multiplied by project square footage and construction cost per square foot. Fee formula

  • Before construction, the developer must execute a road maintenance agreement with the city and affected township or road district. It must address road-condition assessments, repairs or upgrades, construction-period maintenance, and financial security for restoration. Road agreement requirements

  • The facility must demonstrate compliance with applicable federal and state safety standards, including those administered by OSHA, NFPA, UL, and the Illinois Commerce Commission. Federal and state compliance requirement

Benefits & exceptionsHide benefits & exceptions7
  • Data centers may be built in the I-2 General Industry district with a special use permit, subject to the ordinance’s requirements. “permitted only in the I-2 General Industry zoning district”

  • The city may allow additional building height if the project provides additional setbacks and the added height is approved as a special-use-permit condition. “additional height considerations with additional setbacks”

  • The Planning Commission may approve alternative noise-mitigation measures if they are shown to be equivalent or superior to the specified measures. “equivalent to or superior”

  • Noise limits may be adjusted based on City staff recommendations informed by pre-construction noise studies. “Noise levels may be adjusted”

  • The Zoning Administrator may approve an alternative landscaping plan for projects using low-impact development practices or pursuing specified sustainability or green-building certifications. “may approve alternative compliance landscape plans”

  • Roof-mounted equipment need not be screened when it is not visible to the public and complies with noise regulations; solar systems also need not be screened where screening would limit their function or access to sunlight. “additional exceptions for equipment that is not visible”

  • The Planning Commission may consider and approve alternative fence designs through a Building, Site, and Operational Plan submittal, even if they do not meet the usual fence standards. “alternative fence design”