City of Troy
Anti-Data Center Policies
Troy allows data centers only in I-2 industrial zones with a special-use permit, large setbacks, and noise limits. Detailed plans and studies, plus a road-maintenance agreement, add hurdles to building or expanding facilities.
current law · City of TroyRequires data centers to obtain a special-use permit, locate in industrial zones, and meet rules for setbacks, noise, landscaping, lighting, environmental reviews, and road repairs.Ohio Troy Ordinance 2025-46 (2025)
What this means
The measure would allow data centers, but only in I-2 industrial zones and with a special-use permit, plus large setbacks and noise limits (permitted only in I-2). It also requires extensive plans and studies and a road-maintenance agreement, creating significant hurdles for building or expanding facilities (submittal requirements).
People behind it
- Planning Commission
Reviewed and recommended adoption of the data-center regulations (recommended adoption).
- City Council of the City of Troy
Adopted the ordinance establishing the data-center regulations (adopted by the City Council).
Restrictions & requirementsHide restrictions & requirements13
Data centers may be located only in the I-2 General Industry district and require a special use permit. The permit review considers impacts such as nearby uses, traffic, utilities, noise, site design, and signage. The district and permit requirement
The ordinance requires minimum setbacks: 100 feet from a public right-of-way, 50 feet for building side and rear yards, and 200 feet from any district where residential dwellings are permitted. Setback standards
Building height must comply with the I-2 district rules; additional height considerations and setbacks may be imposed as a special-use-permit condition. Buildings and visible accessory structures must also meet specified design and screening standards. Height and design requirements
Setback areas are subject to landscaping requirements, including a six-foot minimum berm where it can fit, native planting and restoration, and at least one tree per 400 square feet of screening area, subject to specified alternative-plan approval. Landscaping and tree-density requirements
Fences may not exceed 12 feet; security fencing in setback areas cannot use barbed or razor wire. A masonry or decorative-concrete sound wall may be used around utility areas or for noise mitigation, but cannot exceed 24 feet. Fence and sound-wall limits
Visible mechanical equipment and major equipment such as cooling towers and generators must be screened; public-facing service and loading areas require opaque screening at least eight feet high. Equipment and loading-area screening
Stationary noise is limited to 60 dB by day and 55 dB at night next to residential land uses, and 70 dB at any time next to nonresidential uses. Discrete-tone or impulsive noise lowers the applicable limit by 5 dB; both together lower it by 10 dB. The ordinance requires a pre-construction sound study, mitigation if operations exceed limits, and allows the city to obtain or require a follow-up study within six months after a building’s certificate of occupancy. Noise limits and follow-up study
Parking and circulation must comply with city standards; gated parking must prevent queues from reaching public streets and be located behind the building. Parking is prohibited on public streets and access roads. Parking restrictions
Lighting is subject to limits on shielding and upward light output; accent lighting must be directed downward, and freestanding fixtures within 300 feet of a property line cannot exceed 18 feet. Nighttime strobe lighting is limited to red safety lighting. Lighting restrictions
Applicants must submit a broad set of materials, including ownership and survey documents, environmental-review results, applicable historic-preservation and noise-compliance information, site and screening plans, utility-interconnection evidence, an operations and maintenance plan, proof of insurance, and a preliminary emergency-services plan. An executed agricultural-impact-mitigation agreement is also required. Application submittal requirements
The application fee is calculated using the city’s commercial permit fee schedule: 0.0045 multiplied by project square footage and construction cost per square foot. Fee formula
Before construction, the developer must execute a road maintenance agreement with the city and affected township or road district. It must address road-condition assessments, repairs or upgrades, construction-period maintenance, and financial security for restoration. Road agreement requirements
The facility must demonstrate compliance with applicable federal and state safety standards, including those administered by OSHA, NFPA, UL, and the Illinois Commerce Commission. Federal and state compliance requirement
Benefits & exceptionsHide benefits & exceptions7
Data centers may be built in the I-2 General Industry district with a special use permit, subject to the ordinance’s requirements. “permitted only in the I-2 General Industry zoning district”
The city may allow additional building height if the project provides additional setbacks and the added height is approved as a special-use-permit condition. “additional height considerations with additional setbacks”
The Planning Commission may approve alternative noise-mitigation measures if they are shown to be equivalent or superior to the specified measures. “equivalent to or superior”
Noise limits may be adjusted based on City staff recommendations informed by pre-construction noise studies. “Noise levels may be adjusted”
The Zoning Administrator may approve an alternative landscaping plan for projects using low-impact development practices or pursuing specified sustainability or green-building certifications. “may approve alternative compliance landscape plans”
Roof-mounted equipment need not be screened when it is not visible to the public and complies with noise regulations; solar systems also need not be screened where screening would limit their function or access to sunlight. “additional exceptions for equipment that is not visible”
The Planning Commission may consider and approve alternative fence designs through a Building, Site, and Operational Plan submittal, even if they do not meet the usual fence standards. “alternative fence design”