Gordon County

This restriction takes precedence while in effect. The rating below excludes temporary restrictions.

Slightly Pro-Data Center Policies

Gordon County’s temporary moratorium delays new data-center development through January 29, 2027, while the county works on ordinances; it is not described as a permanent ban or a restriction on existing operations.

Rating from Georgia statewide as there are no scored current or future laws outside temporary restrictions for Gordon County.

Specific to Gordon County only.

current law · County measure
Extends a temporary moratorium on data centers in Gordon County through January 29, 2027, while officials develop proposed regulations.Gordon County Data Center Moratorium (2026)

What this means

The county extended its temporary data-center moratorium through January 29, 2027, delaying new data-center development while it works on ordinances. The sources do not describe a permanent ban or restrictions on existing operations.

Timing

Ends
Jan 29, 2027

The temporary moratoriums on data centers and anaerobic digestion facilities were extended through this date while the County develops draft ordinances.

People behind it

  • Adopted and extended the temporary moratoriums on data centers and anaerobic digestion facilities and continued developing related ordinances.

  • Board Chair who presented the temporary moratorium resolutions for consideration.

  • Commissioner who moved to approve the data-center moratorium in February, March, and July 2026.

Show 3 more peopleShow fewer people
  • Vice-Chair who seconded approval of the data-center moratorium extensions in February, March, and May 2026 and the anaerobic-digestion moratorium extension in May 2026.

  • Commissioner who moved to approve the data-center and anaerobic-digestion moratorium extensions in May 2026 and seconded the July 2026 data-center and anaerobic-digestion extensions.

  • Commissioner who seconded the July 2026 data-center and anaerobic-digestion moratorium extensions.

Restrictions & requirementsHide restrictions & requirements1
  • A temporary moratorium relating to data centers was imposed for 60 days through April 4, 2026, extended through June 15, 2026, and later extended through January 29, 2027, creating a time-limited barrier to data-center development during those periods.