DeKalb County
This restriction takes precedence while in effect. The rating below excludes temporary restrictions.
Slightly Pro-Data Center Policies
DeKalb County’s enacted measures, described in the text as proposed, pause approvals for new data centers and expansions in unincorporated areas; duration varies.
Rating from Georgia statewide as there are no scored current or future laws outside temporary restrictions for DeKalb County.
Specific to DeKalb County only.
current law · Unincorporated areasProposes extending the pause on permits and other approvals for new or expanded data centers in unincorporated DeKalb County while officials study their impacts and consider regulations.Georgia DeKalb County Resolution 2025-1694 (2025-2026)
What this means
The proposed extension would stop permits for new data centers and expansions in unincorporated DeKalb County, making new construction and growth substantially harder. It does not say existing centers must stop operating, and the source gives no end date for the extension.
Timing
The measure extends a moratorium on permitting or otherwise authorizing new data centers and expansions of existing data centers in unincorporated DeKalb County. The provided sources do not specify the moratorium’s expiration date or ending condition.
People behind it
- Director of Planning and Sustainability
Proposed extending the moratorium on permitting or authorizing new data centers and expansions of existing data centers in unincorporated DeKalb County.
Restrictions & requirementsHide restrictions & requirements1
A moratorium is extended on permitting or otherwise authorizing any new data center or the expansion of an existing data center in unincorporated DeKalb County. The measure’s stated purpose is to extend this moratorium
Sources
current law · Unincorporated areasExtends the pause on permits or other approvals for new data centers and expansions of existing data centers in unincorporated DeKalb County.Georgia DeKalb County Resolution 2025-1228 (2025)
What this means
The proposed extension would pause permits and other approvals for all new data centers and expansions in unincorporated DeKalb County, making development there substantially harder. It does not say existing centers must stop operating, and the source does not specify how long the extension would last. new data centers or expansions
Timing
The measure extends a moratorium on permitting or authorizing new data centers or expansions of existing data centers in unincorporated DeKalb County, but the provided sources do not state an expiration date or ending condition.
People behind it
- Director of Planning and Sustainability
Applicant responsible for proposing the extension of the data-center moratorium.
Restrictions & requirementsHide restrictions & requirements1
Extends a moratorium in unincorporated DeKalb County on permitting or otherwise authorizing any new data center or the expansion of an existing data center.
Sources
current law · Unincorporated areasTemporarily prohibits permits or other approvals for new data centers and expansions of existing data centers in unincorporated DeKalb County.Georgia DeKalb County Resolution 2025-0996 (2025)
What this means
The measure would pause permits and other approvals for new data centers and expansions in unincorporated DeKalb County for 100 days, delaying projects during that period (“until Oct. 16”). It would not stop existing centers from operating, and its limited duration and geographic scope make it less restrictive than a permanent ban.
Timing
- Ends
- Oct 16, 2025
The moratorium on new data center applications, permits, authorizations, and expansions in unincorporated DeKalb County expires on 2025-10-16.
People behind it
- Commissioner Ted Terry
Listed as the information contact for the proposed moratorium.
- DeKalb County staff
Tasked with studying the impacts of data centers and developing potential regulations during the moratorium.
- DeKalb County Board of Commissioners
Governing body that approved the moratorium and would consider any resulting regulations.
Restrictions & requirementsHide restrictions & requirements1
Imposes a 100-day moratorium, through October 16, 2025, on permitting or otherwise authorizing new data centers or expansions of existing data centers in unincorporated DeKalb County.
Sources
pending · Unincorporated areasProposes extending the moratorium on applications to build or expand data centers in unincorporated DeKalb County through March 30, 2027, while allowing existing lawful data centers to continue operating.Georgia DeKalb County Resolution 2026-1109 (2026)
What this means
If enacted, this would stop the County from accepting applications for new data centers or expansions in unincorporated DeKalb County until March 30, 2027, creating a major development delay. Lawful data centers already operating could continue, so it is not an operating ban. The resolution sets the moratorium to expire March 30, 2027.
Timing
- Ends
- Mar 30, 2027
The moratorium expires at 11:59 p.m. on 2027-03-30, unless shortened or extended by official action of the DeKalb County Governing Authority. Lawful operation of existing data centers may continue.
People behind it
- Mereda Davis Johnson
District 5 commissioner and listed information contact for the resolution.
- Robert Patrick
District 1 commissioner and listed information contact for the resolution.
- DeKalb County Board of Commissioners
Governing body responsible for adopting the resolution and extending the moratorium.
Show 7 more peopleShow fewer people
- Lorraine Cochran-Johnson
Chief Executive Officer directed to initiate reviews by affected County departments.
- Planning & Sustainability Department
County department directed to continue studying data centers and developing potential regulations.
- Public Safety
County department identified for review of potential impacts from proposed data-center regulations.
- Watershed Management
County department identified to review water-use and sewer-capacity protocols and other impacts.
- Transportation
County department identified for review of potential impacts from proposed data-center regulations.
- Roads and Drainage
County department identified for review of potential impacts from proposed data-center regulations.
- Public Health
County department identified for review of potential impacts from proposed data-center regulations.
Restrictions & requirementsHide restrictions & requirements2
A complete moratorium in unincorporated DeKalb County prohibits acceptance of applications for establishing new data centers or expanding existing ones, including applications for special land-use permits, rezonings, land-disturbance permits, building permits, business licenses, and certificates of occupancy, until March 30, 2027.
Until March 30, 2027, the County may not grant or deny licenses or permits related to establishing or expanding data centers, including special land-use permits, rezonings, land-disturbance permits, building permits, business licenses, and certificates of occupancy.
Benefits & exceptionsHide benefits & exceptions1
Existing data centers operating lawfully on the date of enactment may continue operating during the moratorium; this protection applies only to facilities operating lawfully when the resolution is enacted.
Sources
Specific to DeKalb County only.
pending · County measureUrges the county administration to study more types of data centers and classify them by category—not just size—in future regulations.Georgia DeKalb County Resolution 2026-1273 (2026)
What this means
This resolution would not itself restrict or benefit data center construction or operations; it asks the county to expand its studies and use categories in any future rules. It describes that work as a request to expand ongoing studies, so any practical effects would depend on later action.
People behind it
- Board of Commissioners - District 7
Requested and introduced the measure.
- Chief Executive Officer or delegate
Authorized to execute necessary documents if the resolution is approved.
Restrictions & requirementsHide restrictions & requirements22
A moratorium extended by the Board of Commissioners bars acceptance of applications related to establishing data centers; the provided text does not specify an end date. extended a moratorium on the acceptance of applications
Minor data centers up to 2,000 square feet are allowed in Office-Institutional districts only as an accessory use; other minor data centers up to 20,000 square feet and 1 to 5 MWh are allowed outright only in Light Industrial or Heavy Industrial districts. Minor data centers are permitted
Major data centers in Light Industrial and Heavy Industrial districts require a special land use permit, and major data centers between 20,000 and 100,000 square feet in Office-Institutional districts also require a special land use permit. All major data centers are permitted
A data center must provide a 75-foot transitional buffer when adjoining nonindustrial property and a wall or fence at least 7 feet high between the uses. minimum transitional buffer of 75’
Facilities must provide a 10-foot-wide landscaped buffer, a wall or fence at least 7 feet high, and canopy trees at a rate of one tree per 30 feet. 10-foot-wide landscaped buffer
New data center development is prohibited within 3,960 feet, or three-fourths of a mile, of another data center development. No new data center development
No more than four total major data centers may be located within a 2-mile, or 10,650-foot, radius. no more than 4 total major data centers
Data centers are prohibited when any part of the property line is within 2,640 feet of a high-capacity transit stop. Data centers are not allowed
The specified distance restrictions must be measured from the applicable ramp right-of-way or street corner along the intersecting street right-of-way to the nearest property line. Distance shall be measured
At least 30 percent of the ground-level width of each building's front façade must consist of fenestration, with windows using architectural glazing or being transparent. minimum of thirty percent
Visible non-primary façades may not use listed materials such as aluminum siding, exposed metal panels, corrugated steel, vinyl siding, plywood, pressed wood products, synthetic stucco, or unfinished concrete block, and at least 10 percent of the façade area must use architectural glazing or be transparent. shall not be constructed of aluminum siding
A property with more than one data center is treated as a data center campus and must use unified landscape and architectural elements under campus-style development standards. considered as a data center campus
Substations, electrical yards, mechanical yards, and other exposed equipment must be placed in the rear yard and screened from adjacent public streets or parks. located in the rear yard
Sound levels may not exceed 80 decibels in industrial areas or 70 decibels in commercial areas. Maximum permissible sound levels
Generator testing is limited to weekdays from 5:00 p.m. to 8:00 p.m. and may not exceed two hours per day. Generator testing will only be allowed
Except for testing or commissioning, generators may be used only for backup or emergency purposes. generator use is limited to backup/emergency use only
A noise impact assessment is required during permitting when specified commercial, arterial-street, residential, or conservation-zoned properties are within 300 feet of the proposed data center's property line. A Noise Impact Assessment shall be required
Substations must be at least 50 feet from the street right-of-way, screened from ground-level view from adjoining property or public streets, and cannot be used to store vehicles or service equipment. at least fifty (50) feet from the street right-of-way
In Light Industrial and Heavy Industrial districts, substations adjacent to property not zoned Light Industrial or Heavy Industrial must have a 10-foot-wide evergreen landscape buffer around the screened area. ten-foot-wide evergreen landscape buffer
Cooling, ventilation, and other equipment must be enclosed or screened with a barrier to reduce noise, and public-street-facing equipment must be visually screened. must be enclosed or have a barrier
All cooling and ventilation equipment within the property boundaries must operate on a closed-loop system. operate on a closed-loop system
Applicants must submit a letter from the utility provider verifying compliance with the provider's policies, procedures, and guidelines. submit a letter from the utility provider
Benefits & exceptionsHide benefits & exceptions6
Minor data centers up to 2,000 square feet may operate as an accessory use on parcels zoned Office-Institutional (O-I).
Minor data centers up to 20,000 square feet with loads between 1 and 5 MWh are permitted outright in Light Industrial (M) and Heavy Industrial (M-2) districts, without a special land use permit.
Major data centers are allowed in M and M-2 districts with a special land use permit.
Major data centers between 20,000 and 100,000 square feet are allowed in O-I districts with a special land use permit.
Substations associated with data centers are expressly allowed in O-I, M, and M-2 districts, subject to setback, screening, and equipment-storage conditions.
Generator testing is permitted on weekdays between 5:00 p.m. and 8:00 p.m., for no more than two hours per day.
Sources
pending · County measureRequests county staff to update the proposed data-center regulations; it does not itself impose new requirements on data centers.Georgia DeKalb County Resolution 2026-0341 (2026)
What this means
The resolution asks county staff to update a proposed data-center text amendment, but does not itself change rules for building or operating data centers. Its effect would depend on what the separate amendment eventually says; the resolution’s stated purpose is to update the recommended substitute.
People behind it
- Commissioner Edward C. “Ted” Terry
Identified as the information contact and the Super District 6 commissioner who proposed the amendments and moved approval of the resolution.
- DeKalb County Board of Commissioners
The legislative body issuing and requesting the resolution concerning updates to the data center regulations.
- DeKalb County Administration and Planning Department
The county departments requested to update the recommended substitute for Text Amendment 2025-0972.
Sources
Specific to DeKalb County only.
failed · County measureWould have established countywide zoning, siting, noise, water-use, energy, and application rules for data centers, but the county denied the proposal, so it did not become law.Georgia DeKalb County Ordinance 2025-0972 (2025)
What this means
If enacted, the countywide proposal would make new data centers and expansions significantly harder: major and campus projects would need special permits, meet strict location and setback rules, and submit extensive impact plans (proposed countywide standards). Some smaller centers could still be built by right in industrial zones, so it would not be a full ban.
People behind it
- Director of Planning and Sustainability
Identified as the applicant proposing the countywide text amendment to establish data-center definitions, regulatory guidelines, and development standards.
- DeKalb County Planning & Sustainability Department
Responsible for researching, defining, and drafting the proposed amendment and administering the related planning process.
Restrictions & requirementsHide restrictions & requirements27
The proposed amendment would prohibit all data centers in Activity Centers.
Accessory data centers would be allowed only in specified O-I, OIT, NS, C-1, C-2, O-D, M, and M-2 zoning districts, and an accessory data center could occupy no more than 10 percent of a building's total floor area.
Minor and medium data centers would be permitted by right as primary uses only in Light Industrial (M) and Heavy Industrial (M-2) districts.
Minor and medium data centers in O-I or O-D districts would require a Special Land Use Permit, regardless of the future land-use designation.
Major and campus data centers would be limited to M or M-2 districts on parcels designated Light Industrial or Heavy Industrial in the future land-use plan, and would require a Special Land Use Permit.
A data center campus would be limited to a maximum improved area of 1,000,000 square feet.
Data centers in M or M-2 districts would generally be prohibited within 750 feet of a residentially or mixed-use-zoned parcel and within 500 feet of a DeKalb County park or trail. The Board of Commissioners could reduce these distances through an approved Special Land Use Permit; where an interstate, state highway, or major arterial abuts the site, the residential setback could be reduced to 300 feet along that frontage.
Major and campus data centers would be prohibited if any property line is within 2,640 feet, or one-half mile, of a high-capacity transit stop.
Major and campus data centers would have to maintain a 100-foot transitional buffer along property lines abutting nonindustrial property, plus a 20-foot landscaped buffer, an at least eight-foot-high wall, and specified canopy-tree plantings where applicable.
Data center buildings in M or M-2 districts would generally be limited to 75 feet in height, and rooftop mechanical equipment would be limited to 30 feet. A project using renewable energy to offset at least 45 percent of total energy use could increase building height to a maximum of 150 feet, subject to transitional height-plane rules.
Medium, major, and campus data centers within 300 feet of a publicly accessible road or right-of-way would have to provide ground-level fenestration covering at least 30 percent of the front facade; side and rear facades would require decorative treatment covering at least 10 percent.
The amendment would prohibit specified facade materials, including aluminum siding, corrugated steel, vinyl siding, plywood, pressed wood products, synthetic stucco, and unfinished concrete block.
Cooling and ventilation equipment would have to use a closed-loop system or other water-reducing equipment approved by the Department of Watershed Management; the defined closed-loop system could not use evaporative cooling.
Substations, electrical yards, mechanical yards, and other exposed equipment could not be placed between the primary data center building and a public road or right-of-way and would have to be screened from adjacent streets, trails, and parks.
Substations associated with data centers would be allowed only in M and M-2 districts, would have to be at least 50 feet from a public right-of-way, would require an eight-foot decorative brick-faced wall, and could not share the site with vehicle storage or service equipment.
Non-street and non-pedestrian lighting would have to use Dark Sky design, cause no spillover onto surrounding properties or streets, and use permanently black-finished lights and poles.
Data center sound levels could not exceed 65 decibels during the daytime or 55 decibels during the nighttime, measured at the property line using both A-weighted and C-weighted frequencies.
Generators would have to meet at least EPA Tier 4 emission standards, be fully enclosed in sound-attenuation walls, be tested no more than 10 hours per month and only from 9:00 a.m. to 5:00 p.m., and have their testing documented in an annual compliance report. Except for testing or commissioning, generator use would be limited to backup or emergency use and could not continue for more than 72 consecutive hours.
Before a Special Land Use Permit application, the applicant would have to confirm in writing that it was working with the applicable utility provider; before a land-disturbance permit, it would have to provide written confirmation that the power provider agreed to provide service.
Every new data center application, including applications not requiring a Special Land Use Permit, would have to include a noise impact assessment measured 500 feet from the property line and demonstrate mitigation sufficient to meet the applicable 65-decibel daytime and 55-decibel nighttime limits.
Every new data center application would have to include a water-consumption and sustainability plan addressing total water demand, cooling, drought and scarcity risks, public-service impacts, conservation measures, alternative sources or storage, and advanced low-water or water-free cooling.
Every new data center application would have to include an energy-consumption and sustainability plan addressing preconstruction and projected operating loads, peak demand, transmission impacts, renewable-energy measures offsetting at least 10 percent of total power use, electronic-equipment recycling, decommissioning, and other resource-reduction practices.
Applications would have to include a Dark Sky lighting plan, transmission-line impact assessment, tree-preservation and reforestation plan, stormwater-management plan, and detailed sewer plan addressing flows, capacity, treatment, discharge permits, closure and disposal, and water-use-effectiveness metrics.
The County could require additional information from Watershed Management, Fire Rescue, Public Works, Code Compliance, or Planning and Sustainability before an application was deemed complete.
Owners or operators would have to submit an annual compliance report by January 1 documenting changes to and continued compliance with required assessments and zoning conditions.
Any building expansion or height increase of an existing data center would require a Special Land Use Permit.
Data centers would have to comply with the County's off-street parking requirements.
Benefits & exceptionsHide benefits & exceptions11
Accessory data centers may operate in O-I, OIT, NS, C-1, C-2, O-D, M, and M-2 districts, provided they occupy no more than 10% of the building’s total floor area. Accessory data centers
Minor and medium data centers may be established as primary uses by right in Light Industrial (M) and Heavy Industrial (M-2) districts, without a Special Land Use Permit. permitted as a primary use by-right
Minor and medium data centers may be located in O-I and O-D districts through the Special Land Use Permit process, creating an approval path in those districts. shall require approval of a Special Land Use Permit
Major and campus data centers may be developed in M and M-2 districts on parcels designated Light Industrial or Heavy Industrial in the future land-use plan, subject to a Special Land Use Permit. Major data centers and campus data centers shall only be permitted
A data center campus may consist of one or multiple buildings developed in one or multiple phases, with a maximum improved area of 1,000,000 square feet. one or multiple buildings built across one or multiple phases
The Board of Commissioners may reduce the required buffers from mixed-use or residential parcels, parks, and trails as part of an approved Special Land Use Permit. may be reduced by the Board of Commissioners
Medium, major, or campus data centers using renewable energy to offset at least 45% of total energy use may increase building height to as much as 150 feet, subject to transitional height-plane requirements. increase the height of a building to a maximum of one hundred fifty
Associated substations are expressly allowed in M and M-2 districts, subject to setbacks, screening, and restrictions on collocating vehicle storage or service equipment. Substations associated with the operation of a data center shall only be permitted
Minor data centers are exempt from the amendment’s additional screening requirements beyond those already required by Chapter 27, and medium data centers are also exempt from those additional requirements, reducing added site-screening obligations for those categories. shall not apply to minor or medium data centers
The ordinance permits backup or emergency generator operation, including generator testing and commissioning, subject to Tier 4 emissions standards, testing limits, enclosure requirements, and a 72-hour maximum for consecutive operation. generator use is limited to backup/emergency use only
Renewable-energy equipment and green infrastructure are exempt from the ordinance’s rooftop mechanical-equipment screening requirement. No screening shall be required for renewable energy infrastructure equipment