Chatham County
This restriction takes precedence while in effect. The rating below excludes temporary restrictions.
Slightly Pro-Data Center Policies
Chatham County has enacted a temporary pause on applications for data centers of 10 MW or more and large warehouse conversions, lasting 155 days with a possible 60-day extension; existing facilities can generally keep operating.
Rating from Georgia statewide as there are no scored current or future laws outside temporary restrictions for Chatham County.
Specific to Chatham County only.
current law · Unincorporated areasTemporarily halts new data centers with at least 10 megawatts of capacity and conversions of warehouses or large industrial buildings of 200,000 square feet or more into data centers in unincorporated Chatham County.Chatham County, Georgia Ordinance Creating Temporary Moratorium on Large-Scale Data Centers (2026)
What this means
The measure would temporarily block applications for new or expanded data centers of 10 MW or more, and conversions of large warehouses to data center use, for 155 days, with a possible 60-day extension. It does not generally stop existing facilities from operating, but the pause would substantially delay covered projects while the county studies future rules.
Timing
- Ends
- 155 calendar days from the Effective Date
The moratorium applies to large-scale data-center development and covered warehouse or large-industrial-building conversions in unincorporated Chatham County. It may be extended once by up to 60 calendar days if the required comprehensive study is incomplete and the moratorium remains reasonably necessary; the total duration cannot exceed 215 calendar days. Applications for other uses remain eligible for processing.
People behind it
- Dean Kicklighter
Chatham County District 7 Commissioner who publicly proposed a county moratorium on large-scale data centers.
- Chatham County Board of Commissioners
Legislative body that adopted the moratorium ordinance.
- County Manager
Official authorized to administer the ordinance’s exception process, vested-rights determinations, and anti-evasion determinations.
Show 1 more peopleShow fewer people
- County Clerk
Official responsible for maintaining the public record of any tolling period and the moratorium’s adjusted expiration date.
Restrictions & requirementsHide restrictions & requirements8
Imposes a 155-calendar-day moratorium, applying in all zoning districts in unincorporated Chatham County, on covered data-center development and conversions.
During the moratorium, the County may not accept, process, or approve applications to construct a new data center or expand an existing facility to an electrical capacity of 10 megawatts or greater.
During the moratorium, the County may not accept, process, or approve applications to convert any warehouse or large industrial building of 200,000 square feet or more into a data center, regardless of the facility’s electrical capacity.
Applications covered by the moratorium that were pending when it took effect must be held in abeyance until the moratorium expires or ends earlier, although their filing dates are preserved.
Projects may not be structured, divided, phased, or otherwise arranged to evade the thresholds; related facilities may be treated as one project when they share ownership or control, are within 1,000 feet, share infrastructure, were planned or financed together, or have an aggregate capacity of at least 10 megawatts.
The moratorium may be extended once for up to 60 additional calendar days if the required study is incomplete and the continued moratorium remains necessary; the total duration may not exceed 215 calendar days.
Exceptions require a written application and clear and convincing evidence of all specified conditions, including financially secured infrastructure improvements, compliance with existing standards, proof that denial would eliminate all economically viable property use, consistency with public health and safety, and— for conversions—professional-engineer certification of structural and mechanical adequacy.
The vested-rights exceptions are limited to projects with qualifying permits or certain preexisting conversion agreements made before the effective date, substantial good-faith expenditures, and a written claim filed within 30 calendar days.
Benefits & exceptionsHide benefits & exceptions9
Data centers with an electrical capacity below 10 megawatts are exempt from the moratorium and may be developed or expanded, subject to otherwise applicable regulations.
Existing data centers below 10 megawatts may continue operating and may perform routine maintenance, repairs, interior modifications, and equipment replacements, provided the work does not increase capacity to 10 megawatts or more.
Data center operations already lawfully existing in a warehouse or large industrial building may continue operating if they do not expand their floor area or electrical capacity.
A limited exception may be granted by the County Manager when the applicant provides binding, financially secured commitments to fully mitigate infrastructure impacts, complies with applicable standards, proves that denial would deprive the property of all economically viable use, and demonstrates consistency with public health, safety, and welfare requirements.
Applicants denied an exception may appeal to the Board of Commissioners within 30 calendar days, with a public hearing required within 45 days.
Projects with a valid building permit issued before the effective date and substantial good-faith expenditures made in reliance on that permit are protected from the moratorium.
Warehouse or large industrial building conversions with a pre-effective-date building permit or change-of-occupancy permit and substantial reliance expenditures are protected from the moratorium.
A conversion of an occupied warehouse or large industrial building is protected if, before the effective date, the owner or operator executed a binding lease termination agreement, development agreement, or conversion contract and made substantial expenditures in reliance on it and on the prior zoning rules.
The moratorium is temporary: it lasts 155 days, may be extended only once for up to 60 additional days, and cannot exceed 215 days in total.
Sources