City of Edgewater

This restriction takes precedence for the map color while in effect.

Strongly Anti-Data Center Policies

Edgewater bars new or expanded covered data centers for 12 months unless the restriction ends sooner; existing facilities may operate but cannot expand their main data-processing use.

current law · City of Edgewater
Places a proposed charter amendment prohibiting data centers on the ballot for voter consideration.City of Edgewater Charter Amendment No. 4 — Prohibition on New Data Centers

What this means

If adopted, the proposal would prohibit data centers, making building or operating them unavailable within its scope. The document gives no exceptions or offsetting benefits; it lists a “Prohibition of Data Centers” as a proposed charter revision.

People behind it

  • Reviewed the City Charter and developed proposed charter revisions for City Council consideration.

  • Appointed the Charter Review Committee and reviewed and approved the proposed ballot language.

  • Department identified for the agenda item.

Restrictions & requirementsHide restrictions & requirements1
  • A proposed Charter revision would prohibit data centers; the document does not specify the scope, exceptions, or effective period of the prohibition.

Sources

current law · City of Edgewater
Prohibits Edgewater from accepting or approving applications for new or expanded data centers and similar large-scale computing facilities for 12 months, with limited exemptions for existing and previously approved facilities.Ordinance 2026-O-21 – Permanent Moratorium on Data Centers and Other High-Energy Data Processing Facilities

What this means

The measure would block the City from accepting or approving applications to establish or expand covered data centers, creating a major barrier to new construction and growth (approval ban). The restriction is set to last 12 months unless ended sooner; existing facilities could keep operating, but could not expand their main data-processing use (12-month term).

Timing

Ends
twelve (12) months following its effective date

The City Council may terminate the moratorium sooner if it determines that appropriate land development regulations have been adopted or that the moratorium is no longer necessary.

People behind it

  • Directed Staff to bring forward the ordinance and approved it; the agenda summary says Council gave consensus for Staff to bring it forward. Council gave consensus

  • Directed to bring forward the proposed ordinance following Council’s consensus. for Staff to bring forward an ordinance

  • Identified as the department for the measure in the agenda item. DEPARTMENT: City Clerk

Restrictions & requirementsHide restrictions & requirements1
  • For 12 months after the ordinance’s effective date, the City suspends accepting, processing, reviewing, approving, or issuing City approvals needed to establish or expand a covered facility, including development orders and permits, rezonings, utility capacity reservations, and concurrency determinations. It applies to applications without final approval before the effective date. The Council may end the moratorium sooner; exceptions include facilities with a previously issued valid building permit, existing lawful facilities without a proposed expansion of the principal data-processing use, accessory facilities, specified governmental facilities, and development with vested rights. The City shall permanently suspend the moratorium shall remain in effect for twelve (12) months

Benefits & exceptionsHide benefits & exceptions6
  • A covered facility with a valid building permit issued before the ordinance takes effect is exempt from the moratorium. valid building permit has been issued prior

  • Existing lawfully operating facilities may continue operating, provided they do not propose an expansion of the principal data-processing use. no expansion of the principal data processing use is proposed

  • Computer rooms, network equipment, or data-processing facilities that are clearly accessory and incidental to another lawful principal use are exempt. clearly accessory and incidental

  • Municipal, county, state, or federal facilities necessary for emergency communications, public safety, or governmental operations are exempt. necessary for emergency communications

  • Development with vested rights under applicable Florida law is exempt. obtained vested rights

  • The moratorium does not apply to applications that received final approval before the ordinance takes effect. have not received final approval prior