Town of Trumbull
This restriction takes precedence for the map color while in effect.
Pro-Data Center Policies
Trumbull has enacted a two-year pause on establishing or developing new data centers; existing facilities are not affected and can continue operating.
Rating from Connecticut statewide as there are no scored current or future laws outside temporary restrictions for Town of Trumbull.
current law · Town of TrumbullTemporarily prohibits establishing or developing new data centers in Trumbull for two years, while leaving existing centers unaffected.Trumbull Resolution TC31-65 (2026)
What this means
The measure would pause the establishment and development of new data centers for two years, a substantial barrier to new projects. It would not affect data centers already in town, so existing facilities could continue operating.
Timing
- Ends
- 24 months from the ordinance’s effective date
The moratorium applies to new data centers; existing data centers are unaffected. It sunsets twenty-four months from its effective date.
People behind it
- Trumbull Town Council
Approved the two-year moratorium unanimously; no individual sponsor or co-sponsor is identified.
Restrictions & requirementsHide restrictions & requirements1
A two-year moratorium bars establishing or developing new data centers in Trumbull. It takes effect on the ordinance’s effective date and ends 24 months later; data centers already in town are exempt. The moratorium’s scope and sunset
Benefits & exceptionsHide benefits & exceptions1
The two-year moratorium does not apply to data centers already operating in Trumbull, allowing existing facilities to continue operating during the moratorium.