South Central Connecticut Planning Region
For South Central Connecticut Planning Region, see Connecticut’s statewide laws and regulations below. No additional county-specific measures are listed in our research.
Pro-Data Center Policies
Connecticut offers qualifying data centers long-term tax exemptions on property, equipment, services, and electricity, but projects must meet investment thresholds and agree on fees with each host municipality before construction. The state also provides applicant assistance and interagency coordination.
Incentives
Tax benefitsGrants and cash rebates
The proposed bill would provide tax credits, grants and research funding for the development of artificial intelligence data centers.
Tax benefitsGrants and cash rebatesPreferential financing
Retains the existing qualified-data-center tax-agreement framework, including conditional 20- or 30-year terms and the existing financial-transactions-tax provision. Separately raises the general state financial-assistance cap from $10 million to $25 million and changes broader financing programs, which may assist independently eligible projects. These are not unconditional or entirely new data-center benefits.
Tax benefitsFee waivers2
Establishes conditional property and sales/use tax exemptions, including electricity purchases. Higher-investment qualifying centers also receive an exemption from any future state financial-transactions tax or fee. Electricity tax relief is classified as a tax benefit, not a utility-rate incentive.
Creates conditional property and sales/use tax exemptions, including electricity purchases. Higher-investment qualifying centers also receive an exemption from any future state financial-transactions tax or fee. Electricity tax relief is classified as a tax benefit, not a utility-rate incentive.
current law · StatewideRetains the existing qualified-data-center tax-agreement framework, including investment conditions and potential 20- or 30-year terms; the restatement does not create every listed benefit anew.Connecticut Public Act 26-122 / SB 307 (2026)
What this means
The principal data-center change removes the standalone office while preserving DECD applicant assistance and interagency coordination. The incentive agreement framework is retained rather than broadly newly created, so the direct change to development conditions is limited.
People behind it
- Commerce Committee
Introduced the bill.
- Rep. Savet Constantine
Listed as a co-sponsor of SB-307.
- Sen. Tony Hwang
Listed as a co-sponsor of SB-307.
Show 5 more peopleShow fewer people
- Rep. John Santanella
Listed as a co-sponsor of SB-307.
- Rep. Tom Delnicki
Listed as a co-sponsor of SB-307.
- Department of Economic and Community Development
Administers the Connecticut Small Business Boost program and other programs established or revised by the measure.
- Commissioner of Economic and Community Development
Carries out administrative, funding, reporting, permitting, and program-implementation duties under the measure.
- Connecticut Innovations, Incorporated
Administers or collaborates with the Department of Economic and Community Development on specified program components.
Restrictions & requirementsHide restrictions & requirements8
Retained incentive framework (not newly created by PA 26-122): A data center seeking the statutory tax exemption must apply to the Commissioner of Economic and Community Development and enter into an approved agreement demonstrating that it will be used as a qualified data center.
Retained incentive framework (not newly created by PA 26-122): Within five years after the agreement becomes effective, the data center must make a qualified investment of at least $50 million if located in an enterprise zone or federal opportunity zone, or at least $200 million if located elsewhere.
Retained incentive framework (not newly created by PA 26-122): An agreement generally lasts 20 years and must include a five-year qualifying period for meeting the required investment threshold.
Retained incentive framework (not newly created by PA 26-122): A qualified data center must pay an annual administrative fee set by the commissioner, capped at $50,000, during the qualifying period or until the required investment is reached, whichever occurs first.
Retained incentive framework (not newly created by PA 26-122): If the data center makes at least $200 million in a qualifying zone or $400 million elsewhere, the commissioner must extend the agreement term to 30 years.
Retained incentive framework (not newly created by PA 26-122): The agreement must include provisions requiring assessment and payment of otherwise exempt taxes, plus penalties and interest, if the data center fails to meet the agreement or qualified-data-center requirements.
Retained incentive framework (not newly created by PA 26-122): The agreement's requirements apply to subsequent owners, operators, operator affiliates, and colocation tenants for the agreement's remaining term, as long as the facility continues to be used as a qualified data center.
Retained incentive framework (not newly created by PA 26-122): The 30-year financial-transactions-tax exemption is available only to a qualified data center, its operator or affiliate, and its colocation tenants after the applicable higher investment threshold is met: $200 million in a qualifying zone or $400 million elsewhere.
Benefits & exceptionsHide benefits & exceptions7
Retained incentive framework (not newly created by PA 26-122): Qualified data centers may enter into agreements with the Department of Economic and Community Development for the tax exemptions provided under the data-center program. To qualify, they must make an investment of at least $50 million within five years in an enterprise or federal opportunity zone, or $200 million elsewhere. The agreement generally lasts 20 years and may require an annual administrative fee of up to $50,000 during the qualifying period. The agreement requirements
Retained incentive framework (not newly created by PA 26-122): The tax-exemption agreement for a qualified data center must apply to subsequent owners, operators, operator affiliates, and colocation tenants, provided the facility continues to be used as a qualified data center. Applicable to any subsequent owner
Retained incentive framework (not newly created by PA 26-122): The commissioner must extend the agreement from 20 years to 30 years if the qualified data center reaches an investment of at least $200 million in an enterprise or federal opportunity zone, or $400 million elsewhere. Extend to thirty years
Retained incentive framework (not newly created by PA 26-122): A qualified data center that meets the higher investment threshold, along with its operator, operator affiliate, and colocation tenants, is exempt from state financial-transactions taxes or fees on trades of stocks, bonds, derivatives, and other financial products for 30 years from completion of facility construction. Exempt from any financial transactions tax or fee
Administrative change in PA 26-122: The Department of Economic and Community Development must act as a liaison for data-center applicants and qualified data centers with other state agencies, provide assistance from the preapplication phase through post-operation, and seek coordinated, efficient, and timely agency responses. Serve as the liaison
Restated permit-ombudsman process: A data-center project that meets the statutory eligibility criteria, such as creating at least 100 jobs, locating in an enterprise zone, being in a brownfield, or satisfying other listed economic-development criteria, may use the state permit-ombudsman process for expedited permit review. The process cannot waive environmental statutory or regulatory requirements or change substantive permitting standards. Expediting review of permit applications
Broader economic-development change: The act raises the general limit on financial assistance that state economic-development agencies may award to an applicant or business project during a two-year period from $10 million to $25 million, unless a General Assembly act specifically authorizes the assistance. This can permit larger state financial assistance packages for qualifying data-center projects. More than a total of twenty-five million dollars
Sources
current law · StatewideProvides qualifying data centers with long-term tax exemptions if they meet investment thresholds, while requiring owners to negotiate a fee agreement with the host municipality before construction.Connecticut General Statutes § 32-286 — Qualified Data Centers
What this means
The measure offers major long-term tax savings on data center property, equipment, services, and electricity for projects meeting investment thresholds (tax exemptions). Owners must meet those thresholds and negotiate a fee agreement with each host municipality before construction, so the benefits come with conditions (host municipality agreement).
People behind it
- Matthew Ritter
Listed as an introducer of H.B. No. 6514, the qualified data center incentives bill.
- Martin M. Looney
Listed as an introducer of H.B. No. 6514, the qualified data center incentives bill.
- Jason Rojas
Listed as an introducer of H.B. No. 6514, the qualified data center incentives bill.
Show 9 more peopleShow fewer people
- Bob Duff
Listed as an introducer of H.B. No. 6514, the qualified data center incentives bill.
- Eleni Kavros DeGraw
Listed as a co-sponsor of H.B. No. 6514.
- Christine Conley
Listed as a co-sponsor of H.B. No. 6514.
- Heather S. Somers
Listed as a co-sponsor of H.B. No. 6514.
- Connecticut Department of Economic and Community Development
Identified in the 2026 act title as making recommendations for commerce-statute revisions; administers the data center incentive program and processes applications.
- Commissioner of Economic and Community Development
Reviews applications, approves and enters incentive agreements, and oversees the program.
- Commissioner of Revenue Services
Provides tax-exemption certificates and may collect taxes, penalties, and interest when an incentive agreement is terminated.
- Host municipalities
Negotiate fee agreements with qualified data center owners and may address noncompliance under those agreements.
- Chief elected official of the municipality
Notifies a qualified data center of a municipality’s determination that a host municipality fee agreement is not being met.
Restrictions & requirementsHide restrictions & requirements6
To qualify for the tax-exemption agreement, a data center must make a qualified investment within five years: at least $50 million in an enterprise or federal opportunity zone, or $200 million elsewhere. Only eligible, nonduplicative costs count, and costs for property outside the facility are excluded. The investment must be made by the fifth anniversary.
The owner must enter into a negotiated host municipality fee agreement before construction, rehabilitation, renovation, or repair begins. An agreement is required for each facility and, if a facility crosses municipal boundaries, with each municipality; it must address payment of otherwise-exempt property taxes and possible penalties and interest. No construction may commence without an agreement.
The data center must pay an annual fee set by the commissioner, capped at $50,000, during the five-year qualifying period or until it reaches the required investment, whichever comes first. The annual fee may not exceed fifty thousand dollars.
The tax-incentive agreement generally lasts 20 years, and its provisions continue to apply to subsequent owners, operators or their affiliates, and colocation tenants for the agreement’s remaining term, provided the facility continues to be used as a qualified data center. The agreement shall be applicable to any subsequent owner.
If the municipality finds the host-fee agreement is not being followed, the data center has 180 days after notice to cure the noncompliance. If it does not, the agreement may be terminated and the data center or property owner becomes liable for the previously exempt property taxes from the date of noncompliance. The qualified data center shall cure such noncompliance.
If the state terminates the tax-incentive agreement for noncompliance, the host municipality fee agreement also terminates, and applicable sales and use taxes, penalties, and interest may become due; the state may collect them and place a lien on the data center’s real estate. The commissioner terminates an agreement.
Benefits & exceptionsHide benefits & exceptions7
Owners, operators, and colocation tenants may apply for tax-incentive agreements if the facility will be a qualified data center and meets the five-year investment minimum: $50 million in an enterprise or federal opportunity zone, or $200 million elsewhere. Agreements generally last 20 years, and the data center pays an annual administrative fee of up to $50,000 during the qualifying period or until it reaches the investment minimum, whichever comes first. The five-year investment thresholds
Qualifying data centers receive sales and use tax exemptions for eligible data-center equipment, specified services used to develop or operate the facility, and all electricity used by the data center. The exemption also applies to the data center’s contractors and subcontractors. The equipment, services and electricity exemption
The agreement provides a property-tax exemption for real property, buildings, structures, and qualifying enterprise information technology equipment at the data center. The owner must first enter a negotiated host-municipality fee agreement; facilities in contiguous municipalities require agreements with each municipality. The property-tax exemption
During the agreement term, the exemptions can cover additional data-center buildings and equipment, as well as additional equipment, services, and electricity acquired later. Property-tax exemption may also cover an additional facility acquired by the owner, provided it has a host-municipality fee agreement. Additional buildings, equipment and facilities
The agreement must be extended to 30 years if investment reaches $200 million in an enterprise or opportunity zone, or $400 million elsewhere. The 30-year extension thresholds
A data center meeting those higher investment thresholds, along with its operator or affiliate and colocation tenants, is exempt for 30 years from any state financial-transactions tax or fee imposed on trades of stocks, bonds, derivatives, or other financial products. The financial-transactions tax exemption
The Department of Economic and Community Development must act as a liaison, assist applicants and data centers from preapplication through post-operation, and seek coordinated and timely responses from state agencies. The 2026 act assigns these duties to the department rather than a separate office. The department’s data-center assistance duties
Sources
current law · StatewideCreates long-term tax incentives for qualifying data centers that meet investment thresholds and requires owners to make fee agreements with host municipalities before construction begins.Connecticut H6514 (2021)
What this means
The measure offers long-term property, sales, and electricity tax exemptions to qualifying data centers, making development and operation substantially cheaper. The benefits require large investments and a negotiated agreement with the host municipality, so they are significant but not unconditional.
People behind it
- Rep. Matthew Ritter
Introducer of House Bill 6514
- Sen. Martin M. Looney
Introducer of House Bill 6514
- Rep. Jason Rojas
Introducer of House Bill 6514
Show 7 more peopleShow fewer people
- Sen. Bob Duff
Introducer of House Bill 6514
- Rep. Eleni Kavros DeGraw
Co-sponsor of House Bill 6514
- Rep. Christine Conley
Co-sponsor of House Bill 6514
- Sen. Heather S. Somers
Co-sponsor of House Bill 6514
- Commissioner of Economic and Community Development
Administers the qualified data center incentive agreements and related program
- Commissioner of Revenue Services
Administers the tax exemption certificates and collection of taxes, penalties, and interest under the measure
- Office of Data Infrastructure Administration and Security
Established to coordinate and support applicants, qualified data centers, and state agencies
Restrictions & requirementsHide restrictions & requirements5
Before construction, rehabilitation, renovation, or repair begins, the owner must negotiate a host-municipality fee agreement; agreements are required for each host municipality and each additional facility. The owner has entered into a negotiated host municipality fee agreement
Access to the tax-incentive agreement requires DECD approval and a qualified investment within five years: at least $50 million in an enterprise or federal opportunity zone, or $200 million elsewhere. at least fifty million dollars
The DECD agreement must require an annual fee, set by the commissioner at no more than $50,000, during the qualifying period or until the investment threshold is reached, whichever comes first. not to exceed fifty thousand dollars
A municipality may notify the data center of noncompliance with its fee agreement; the center has 180 days to cure, after which the agreement may be terminated and property taxes, penalties, and interest may become due on previously exempt property. not later than one hundred eighty days
DECD may terminate its agreement if the agreement or data center requirements are not met; termination ends the municipality fee agreement and can make exempted state taxes, penalties, and interest payable. requirements of such agreement or of a qualified data center are not being met
Benefits & exceptionsHide benefits & exceptions5
A DECD agreement can provide sales and use tax exemptions for qualifying data-center equipment, related taxable services, and electricity used by the center. Covered equipment includes computing, power, cooling, water-conservation, networking, monitoring, security, and modular-center equipment. The applicant must meet the investment requirement within five years: at least $50 million in an enterprise or federal opportunity zone, or $200 million elsewhere. The agreement generally lasts 20 years, extended to 30 years at higher investment levels. The exemption covers qualified equipment, services, and electricity.
A DECD agreement can exempt real property, buildings, and structures at a qualified data center, as well as enterprise information technology equipment, from the state property tax. The exemption also covers qualifying additional buildings and equipment acquired during the agreement; additional facilities require a host municipality fee agreement. The exemption applies to real property and enterprise information technology equipment.
For centers meeting the higher investment thresholds—$200 million in an enterprise or federal opportunity zone, or $400 million elsewhere—the measure exempts the center, its operator or operator affiliate, and colocation tenants from any state financial-transactions tax or fee on specified financial products. The exemption lasts 30 years from facility completion. The exemption applies for a period of thirty years.
The Office of Data Infrastructure Administration and Security must assist applicants and data centers from preapplication through post-operation, liaise with state agencies, and seek coordinated, efficient, and timely responses. The office shall provide assistance.
The agreement’s provisions continue to apply to a subsequent owner, the operator or its affiliate, and colocation tenants while the facility remains a qualified data center, helping preserve the agreement’s terms through changes in ownership or operation. The provisions of the agreement shall be applicable.
Sources
failed · StatewideWould eliminate state tax exemptions for qualified data centers.Connecticut SB 79 (2024)
What this means
If enacted, the proposal would remove tax breaks for qualified data centers, including sales and use tax exemptions, increasing project costs. It does not propose a ban or address every part of the incentive program, so the added burden is meaningful but limited.
People behind it
- Sen. Flexer
Identified as the bill's introducer.
- Connecticut Department of Economic and Community Development
Administers the Data Center Tax Incentive Program addressed by the measure.
- Office of Data Infrastructure Administration and Security
Administers and provides information about the data center tax incentive program.
Restrictions & requirementsHide restrictions & requirements5
The bill eliminates qualified data centers’ exemptions from the taxes imposed under chapters 203 and 219, increasing the taxes and costs associated with building or operating a data center. The bill eliminates the exemptions
To qualify for the data center tax incentive, a facility must make a minimum investment of $50 million if located in an enterprise or opportunity zone, or $200 million if located elsewhere. Qualified Investments
The required investment must be made by the fifth year of the facility’s agreement with the Department of Economic and Community Development. the required investment will be made by the fifth year
Data center owners and developers must enter into a tax incentive agreement with the Department of Economic and Community Development, generally for a 20-year term. enter into tax incentive agreements with DECD
Before beginning a capital project, the owner or developer must enter into a host fee agreement with the municipality where the data center will be located. must enter into fee agreements with the municipalities
Sources
failed · StatewideWould require AI data centers to use at least 50% renewable energy, adopt energy-storage and water-saving measures, and report their energy use, water use, and emissions, while providing development incentives.Connecticut HB 5076 (2025)
What this means
The proposal would require AI data centers to use at least 50% renewable energy, add energy storage and grid infrastructure, conserve water, and report energy, water, and emissions—requirements that could add meaningful costs. Tax credits, grants, and research funding could offset some of that burden, but the proposal gives no details on their size or availability. The bill’s requirements and proposed incentives
People behind it
- Christopher Rosario
Introduced the proposed bill; state representative for the 128th District.
Restrictions & requirementsHide restrictions & requirements4
Artificial intelligence data centers must obtain at least 50% of their energy consumption from renewable sources.
Artificial intelligence data centers must use energy-storage systems and modern grid infrastructure.
Artificial intelligence data centers must implement water-conservation measures.
Artificial intelligence data centers must report their energy consumption, water consumption, and emissions annually.
Benefits & exceptionsHide benefits & exceptions4
Provides tax credits for the development of artificial intelligence data centers.
Provides grants for the development of artificial intelligence data centers.
Provides research funding for the development of artificial intelligence data centers.
Requires artificial intelligence data centers to utilize energy storage systems and modern grid infrastructure, supporting their operation; the measure does not specify funding or other assistance for that infrastructure.
Sources
failed · StatewideRequires the state to study energy-efficiency standards for AI data centers, including renewable energy, demand-response options, and limits on diesel backup generators, and report its findings by February 1, 2026.Connecticut SB 1292 (2025)
What this means
The substitute bill requires DEEP to study possible efficiency standards, renewable energy, demand response, and limits on diesel generators, but it does not impose those requirements on data centers now (the study’s topics). The study could lead to future rules, but this measure itself creates no meaningful barrier or benefit to building or operating data centers.
People behind it
- Energy and Technology Committee
Sponsor of the bill and committee that introduced it.
- Rep. Mary M. Mushinsky
Co-sponsor of the bill.
- Commissioner of Energy and Environmental Protection
Responsible for conducting the study and submitting its report.
Show 2 more peopleShow fewer people
- Public Utilities Regulatory Authority
Designated to consult on the study.
- Commissioner of Economic and Community Development
Designated to consult on the study.
Sources
failed · StatewideWould have required state agencies to study the energy and environmental impacts of large data centers connected directly to power plants rated at 50 megawatts or more; the bill did not become law.Connecticut 2024 amendment to HB 5469, An Act Concerning Data Centers
What this means
The measure requires agencies to study certain large data centers and report their findings, but it does not add approval requirements or restrict construction or operation. The study applies to centers directly connected to a power plant rated at least 50 megawatts (study scope).
People behind it
- Energy and Technology Committee
Introduced the bill and reported it joint favorable.
- Sen. Needleman
Offered Senate Amendment Schedule A, LCO No. 5469, which replaced the bill's original provisions.
- Rep. Aundre Bumgardner
Co-sponsored the bill.
Show 7 more peopleShow fewer people
- Rep. Holly H. Cheeseman
Co-sponsored the bill.
- Rep. Devin R. Carney
Co-sponsored the bill.
- Department of Energy and Environmental Protection
Assigned, with the Department of Economic and Community Development, to study the specified impacts of large data centers and report the results.
- Department of Economic and Community Development
Assigned, with the Department of Energy and Environmental Protection, to study the specified impacts of large data centers and report the results.
- Public Utilities Regulatory Authority
Required to consult on the study under the amended measure.
- Office of Consumer Counsel
Required to consult on the study under the amended measure.
- Regional independent system operator
Required to consult on the study under the amended measure.
Sources
failed · StatewideRequires state agencies to study how large data centers directly connected to power plants of at least 50 megawatts could affect grid reliability, clean-energy goals, and energy affordability and supply.Connecticut SB 299 (2024)
What this means
The measure would require a study of large data centers’ effects on electric-grid reliability, but it does not make the study a condition for construction or operation (initiate an uncontested proceeding). It could inform future policy, but creates no direct restrictions, costs, or benefits for data center developers.
People behind it
- Energy and Technology Committee
Introduced SB-299.
- Sen. Needleman
Offered amendment LCO 5469, which replaced the bill’s original text.
- Rep. Aundre Bumgardner
Listed as a co-sponsor of SB-299.
Show 5 more peopleShow fewer people
- Rep. Holly H. Cheeseman
Listed as a co-sponsor of SB-299.
- Rep. Devin R. Carney
Listed as a co-sponsor of SB-299.
- Public Utilities Regulatory Authority
The original bill assigned it to initiate a proceeding evaluating data centers’ impact on electric distribution system reliability; the amendment instead named it as a consultant.
- Department of Energy and Environmental Protection
The amendment assigned it, jointly with the Department of Economic and Community Development, to study specified impacts of certain large data centers.
- Department of Economic and Community Development
The amendment assigned it, jointly with the Department of Energy and Environmental Protection, to study specified impacts of certain large data centers.
Sources
failed · StatewideWould have barred new data-center tax-incentive applications starting July 1, 2026, but the bill did not pass.Connecticut SB 245 (2026)
What this means
The bill would stop new data center applicants from receiving the specified tax exemptions after July 1, 2026, raising costs for some future projects (applications could not be accepted after that date). It would not ban construction or add rules on operating data centers, so the impact is a meaningful financial hurdle rather than a broad restriction.
People behind it
- Energy and Technology Committee
Identified as the bill’s sponsor and introducing committee.
- Rep. Steven Winter
Listed as a co-sponsor.
- Rep. Bill Buckbee
Listed as a co-sponsor.
Show 5 more peopleShow fewer people
- Rep. Nick Gauthier
Listed as a co-sponsor.
- Sen. Martha Marx
Listed as a co-sponsor.
- Rep. Nicholas Menapace
Listed as a co-sponsor on the bill status page.
- Rep. Kara Rochelle
Listed as a co-sponsor on the bill status page.
- Rep. Josh Elliott
Listed as a co-sponsor on the bill status page.
Restrictions & requirementsHide restrictions & requirements1
Effective July 1, 2026, the state may not accept new applications for agreements granting qualified data centers exemptions from taxes under chapters 203 and 219, ending access to those incentives for new applicants. No such application may be accepted on or after July 1, 2026.
Benefits & exceptionsHide benefits & exceptions1
Allows prospective owners, operators, or colocation tenants of qualified data centers to apply for exemptions from taxes under chapters 203 and 219, but only if the application is accepted before July 1, 2026. The bill’s application deadline.
Sources
failed · StatewideWould have required data centers with peak demand of at least 50 megawatts to meet new electricity-supply and ratepayer-protection requirements, but the bill did not become law.Connecticut HB 5469 (2026)
What this means
If enacted, the measure would make large data centers harder to build or operate by requiring covered suppliers to arrange new or added generation for the full expected load, plus a reserve margin, and by allowing long-term financial guarantees to protect other electricity customers (generation and reserve requirement; financial guarantees). These are substantial hurdles for projects with peak demand of 50 megawatts or more, though regulators could waive some requirements, so this is a significant barrier rather than a ban.
People behind it
- Energy and Technology Committee
Introduced the bill and was identified as its sponsor.
Restrictions & requirementsHide restrictions & requirements8
Beginning July 1, 2026, a provider serving a customer with peak demand of at least 50 MW through a behind-the-meter or other qualifying colocated arrangement would need a PURA colocated-supplier license. license to serve as a colocated electric supplier
Obtaining that license would require demonstrating technical, managerial, and financial capability, providing a bond or other security, filing an application and fee, and undergoing PURA review; an interested party could request a public hearing. technical, managerial and financial capability
A colocated supplier generally would have to provide 100% of the data center’s anticipated load, plus a PURA-set reserve margin, from generation entering service on or after July 1, 2026, or from qualifying incremental capacity added to an existing resource. PURA could waive some or all of this requirement only under specified ratepayer and energy-planning criteria. not less than one hundred per cent of the anticipated electric load
A colocated supplier would have to file annual reports describing its generation and the customer’s load, and comply with the state’s renewable portfolio requirements. For generation sources entering service on or after December 31, 2030, PURA could require additional renewable energy certificates if supported by the Integrated Resources Plan. File an annual report with the authority
Colocated suppliers would generally be subject to electric-supplier operating requirements, including applicable environmental, reliability, emergency-cooperation, and other licensing conditions. PURA could waive any of the specified conditions for colocated suppliers. the authority may, in the authority’s discretion, waive any of the requirements
For large-load customers interconnecting to the grid after October 1, 2026, a tariff would generally require generation covering 100% of anticipated load plus a PURA-set reserve margin, from a source entering service on or after July 1, 2026, that has not previously cleared an ISO-NE capacity auction. PURA could waive this generation requirement for a customer demonstrating sufficient demand flexibility; the tariff requirement excludes customers served by colocated suppliers. not less than one hundred per cent of the anticipated electric load
Under the grid-connected customer tariff, a new large-load customer would need financial guarantees to pay for at least 85% of its requested service for at least 10 years, plus deposits or other security sufficient to protect ratepayers if the project closes or uses less electricity than anticipated. not less than eighty-five per cent
A new large-load customer subject to the tariff would have to show that its project is unique and not duplicative of another large-load project, and identify the project’s interdependencies. project proposed by such customer is unique and not duplicative
Benefits & exceptionsHide benefits & exceptions4
The bill would recognize behind-the-meter and fully off-grid supplier-customer arrangements as “colocated electric suppliers” and create a PURA licensing route for providing power through them. Operation would still require a license. The definition covers behind-the-meter or unconnected arrangements
PURA could waive any of the standard electric-supplier licensing conditions for a colocated supplier, and could waive or modify specified penalties and payment requirements for renewable-portfolio-standard noncompliance. These are discretionary waivers, not automatic exemptions. PURA may waive licensing requirements
PURA could waive a colocated supplier’s requirement to provide new or incrementally expanded generation for 100% of the customer’s anticipated load plus a reserve margin, if the waiver is in ratepayers’ best interest and consistent with the state’s energy plans. The bill authorizes a conditional waiver
A grid-connected large-load customer not served by a colocated supplier could seek a waiver of the new-generation requirement by demonstrating enough demand flexibility to eliminate the need for that generation. PURA may waive the requirement based on demand flexibility
Sources