Town of Ledyard
Pro-Data Center Policies
Ledyard allows data centers in Technology Park Districts, but projects require Commission approval and at least 200 contiguous acres, potentially adding cost and delay.
Rating from Connecticut statewide as there are no scored current or future laws outside temporary restrictions for Town of Ledyard.
current law · Town of LedyardAllows data centers in Technology Park Districts if the Planning and Zoning Commission approves them and their development plans.Ledyard Zoning Regulations, § 8.14 (Technology Park District permitted uses)
What this means
The rules allow data centers in Technology Park Districts, so they are not banned. But developers need Commission approval and at least 200 contiguous acres, which can add significant costs and delays.
Timing
- Ends
- 12 months after its effective date of 2021-12-17
People behind it
- Planning and Zoning Commission
Amends the zoning regulations and reviews applications under them.
- Zoning Official
Enforces the zoning regulations and may act to prevent or remedy violations.
Restrictions & requirementsHide restrictions & requirements10
Data centers are permitted only in a Technology Park District (TPD). Establishing a TPD requires Commission approval of a Master Plan through a zone-change process and public hearing, and the Commission retains legislative discretion. Master Plan and data centers.
A proposed TPD must cover at least 200 contiguous acres, have frontage on an arterial road or direct access to one, and have adequate underground public utilities or be capable of adequate on-site utility service. District eligibility requirements.
After TPD approval, a Site Plan must be approved. The zone-change approval becomes void unless a Site Plan is approved within 24 months; the Commission may grant extensions of no more than 24 additional months. Site Plan deadline and extensions.
The TPD Master Plan must include a traffic analysis and, if needed, a conceptual plan for improvements and mitigation. Traffic Analysis.
The TPD Master Plan sets bulk, dimensional, parking, and loading standards. Parking must be adequate for proposed uses, located on site where feasible, and designed to avoid excessive impervious coverage; stormwater management must address anticipated runoff. TPD parking standards.
TPD development must provide a buffer between developed areas and residential lots used for housing in an outside residential district, including lots directly across a street. The buffer must be at least 25 feet wide; where it is not already vegetated, screening is required, generally with plantings at least six feet high and spaced ten feet apart. Buffer requirements.
New developments must place utilities underground. TPD site lighting must use full-cutoff fixtures directed generally downward. Underground utilities and TPD lighting.
Uses subject to Chapter 9 must meet performance standards limiting dust, offensive odors and fumes, unreasonable noise, vibration, and perceptible glare or radiant heat beyond the property boundary. Performance standards.
Commercial development with more than 10,000 square feet of combined roof, paved parking, and other impervious area is subject to the Town’s stormwater ordinance and review. A soil erosion and sediment control plan is required when cumulative disturbance exceeds one-half acre. Stormwater threshold and disturbance threshold.
Site Plan applications may be reviewed by outside experts or consultants, and the applicant may be charged for that review under the fee schedule. Outside review fees.
Benefits & exceptionsHide benefits & exceptions5
The Technology Park District (TPD) expressly permits data centers. Development must follow an approved Master Plan and receive Site Plan approval. Data centers
A TPD may be established on at least 200 contiguous acres with frontage on, or direct access to, an arterial road and adequate underground public utilities or the ability to provide sufficient on-site facilities. minimum of 200 acres
Power generation facilities are allowed as an accessory use in a TPD, but must be designed to prevent power from being distributed to the electric grid. Power generation facilities
A TPD Master Plan may be implemented through multiple Site Plan applications, allowing development to proceed in phases. may be phased
Once approved, a TPD replaces the property's pre-existing zoning, and future development is governed by the TPD's requirements. The approval becomes void if a TPD Site Plan is not approved within 24 months, though extensions of up to 24 additional months may be granted. will replace all pre-existing zoning