Griswold’s zoning rules allow data centers to fit existing regulations as offices, while a described overlay offers flexible master-plan approval but still requires detailed site plans; its full requirements are unclear.
Rating from Connecticut statewide as there are no scored current or future laws outside temporary restrictions for Town of Griswold.
current law · Town of GriswoldDoes not adopt data-center-specific zoning rules; the meeting minutes say data centers were considered allowable as office uses under existing zoning, while proposed changes were only discussed.Griswold Connecticut zoning regulations
What this means
The proposal appears to make approval more flexible: its draft overlay was described as offering “inherent flexibility at a Master Plan level” while still requiring detailed site plans (meeting minutes). The town planner also said data centers could fit existing rules as offices (meeting minutes), so the proposal suggests a useful permitting benefit rather than a major change; the sources do not give the draft’s full rules.
Timing
- Ends
- Aug 10, 2009
The moratorium applied to specified residential subdivision and re-subdivision applications in R-40, R-60, and R-80 districts and expired after August 10, 2009. Its terms could be revised for good cause through a similar public-hearing process.
People behind it
- Mario Tristany
Town Planner who prepared a draft zoning text amendment to address data centers.
- William Sweeney
Attorney representing Gotspace, LLC, who presented a draft overlay-zone regulation and a Technology Park District text amendment.
- Gotspace, LLC
Data-center developer represented by Sweeney; it presented proposed zoning changes to facilitate data-center development.
Restrictions & requirementsHide restrictions & requirements12
A zoning permit is required before a building is erected, moved, or structurally altered, or a land use is established or changed. Uses other than specified residential projects generally require Planning and Zoning Commission review and a site plan. A zoning permit is required
A use not clearly permitted in a district cannot receive a permit unless the Commission determines it is similar to a permitted use; the Commission can instead determine it is not similar. The meeting minutes record the Town Planner’s view that data centers could fit as offices, but also show the developer seeking zoning amendments for additional flexibility. Use status is determined by the Commission
Site plans are reviewed for matters including emergency access, traffic safety and congestion, parking and loading, screening, lighting, landscaping, and compatibility with the neighborhood. These requirements can constrain site layout and design. Site plan evaluation criteria
For development disturbing more than one-half acre cumulatively, a soil erosion and sediment control plan must be submitted; a single-family dwelling outside a subdivision is exempt. For certain road or drainage improvements supporting commercial projects disturbing more than one acre, required permits from other authorities and an affidavit documenting them are prerequisites to a permit. The one-half-acre threshold Additional-permit requirement
In a Business Park district, the district must contain at least 50 contiguous acres, be accessible to an interstate, and have at least 50 feet of frontage on a listed state highway. Impervious coverage is capped at 60%, with a possible Special Exception increase to 80% if stormwater is managed using the specified low-impact-development approach. Public water and sewer are required unless connection is impracticable and approved private systems are provided. Business Park minimum size Coverage limit and exception Utility requirement
Creating an Industrial district requires at least 10 acres and an accompanying site plan. Industrial district requirements
If a proposal requires a Special Exception, a public hearing is required, the Commission applies specified evaluation criteria, and the approval expires after five years unless the work is completed and certified as zoning-compliant. Special Exception hearing Five-year expiration
Newly constructed or enlarged buildings cannot be occupied until a Certificate of Zoning Compliance is issued; incomplete or noncompliant approved work can prevent issuance, subject to the stated performance-guarantee option. Certificate required before occupancy
Land-use applications carry category-based fees, including commercial or industrial site-plan and Special Exception fees, and the Commission may require reimbursement for outside professional reviews. Fees are nonrefundable; unpaid additional expenses can lead to denial or permit revocation. Application fee schedule Additional review costs Fees are nonrefundable
The Commission can require cash bonds or irrevocable letters of credit to assure required erosion controls and completion of improvements; these guarantees must be maintained until the applicable work is complete. Performance guarantee requirement
A zoning permit cannot be issued for a use that creates, or may reasonably be expected to create, dangerous conditions or objectionable noise, smoke, dust, fumes, or water pollution detectable at the property line. Prohibited impacts
Projects in a Special Flood Hazard Area must meet flood-related construction standards, including elevation or flood-proofing requirements; development in a designated floodway is generally prohibited unless an engineer demonstrates no increase in flood levels. Flood-zone construction requirements Floodway restriction
Benefits & exceptionsHide benefits & exceptions5
In a Business Park district, business, corporate, administrative, and professional offices are permitted by right, subject to site-plan, landscaping, architectural, and other applicable requirements. The meeting minutes report that the Town Planner said a land-use attorney had determined data centers could fit the existing rules as “offices.” Permitted office uses; fit in as “offices”
Business Park development generally must use public water and sewer, but where connection is impracticable because of a site’s location, the regulations allow a private sewer system and private wells, subject to health-agency and Town determinations. Private systems if public connections are impracticable
Business Park lot coverage is capped at 60% by default, but the Commission may allow up to 80% by Special Exception if stormwater is managed in an approved system using low-impact-development techniques. Increase lot coverage to 80%
A limited expansion or addition to a previously approved site may receive one-time administrative approval without a public hearing if it meets the zoning rules, requires no qualifying site work, and does not substantially alter the approved use, density, or coverage. Larger or otherwise ineligible changes require Commission review. Administrative approval of certain site-plan changes
A lawful nonconforming use existing when the regulations take effect may continue, providing a measure of protection if later rules make that use nonconforming. Lawfully existing nonconforming uses may continue