City of Derby

Pro-Data Center Policies

Derby allows data-processing facilities in its Industrial Campus zone, but projects must meet a two-acre minimum lot size, large setbacks, and Commission review and approval.

Rating from Connecticut statewide as there are no scored current or future laws outside temporary restrictions for City of Derby.

current law · City of Derby
Allows data-processing facilities in the Industrial Campus zone, subject to the zone’s development and approval requirements.Derby Zoning Regulations, Chapter 195

What this means

Data processing facilities are allowed in the Industrial Campus zone, so the rules do not ban data centers (permitted principal uses include data processing). But development faces meaningful hurdles, including a two-acre minimum lot, large setbacks, and Commission review and approval (minimum lot area and buffer requirements).

Timing

The amendment history references a “Temporary and Limited Moratorium” on smoke shops and tobacco stores, but the supplied text does not state when it ends. A later amendment lists smoke shops, vape shops, and tobacco stores as prohibited in all zoning districts; the excerpt does not specify a sunset for that prohibition.

People behind it

  • Adopted the zoning regulations and is responsible for administering and enforcing them.

  • Identified as the City’s Zoning Enforcement Officer, responsible for enforcing the regulations.

Restrictions & requirementsHide restrictions & requirements5
  • A facility classified as a data-processing facility is expressly listed as a principal use in the Industrial Campus (I-C) Zone. Uses not specifically permitted are prohibited, limiting where this use may locate under the regulations. data processing and anything that is not specifically permitted is prohibited

  • In the I-C Zone, the listed principal uses are subject to operating limits: mechanical equipment and services must be devoted to research and technical development of manufactured, processed, or compounded products; the use must not produce specified nuisances or harmful waste; and industrial chemicals must be stored in compliance with applicable laws. conditions for permitted principal uses

  • I-C development must meet dimensional limits: at least 2 acres and 200 feet of frontage on a state or city road; 40% maximum building coverage; 100-foot principal-building setbacks from the frontage road and 50-foot setbacks from lot boundaries, increased to 100 feet at residential-zone boundaries; and a maximum of 3 stories or 40 feet, subject to a limited 50-foot allowance for certain buildings combining parking with specified uses. I-C lot and bulk requirements

  • Site-plan approval is required before a zoning permit for covered buildings, uses, enlargements, or alterations; zoning and building permits are also required. The site-plan review includes required plans and may require additional information, and the Commission may require a performance bond for improvements. site plan approval required before a zoning permit and a performance bond may be required

  • An I-C application requires a fee, and the applicant must pay for technical assistance the City deems necessary to review it. fee and technical-assistance costs

Benefits & exceptionsHide benefits & exceptions6
  • The I-C Zone expressly lists data processing as a permitted principal use, giving qualifying data centers a permitted-use pathway. The zone requires at least two acres and generally 200 feet of frontage on a state or city road; it also limits building coverage and height and bars nuisance emissions and on-site sales of goods produced there.

  • For site plans, the Commission must act within 65 days; if it does not, the application is considered approved and the applicant may demand a permit.

  • The Commission may waive specific site-plan submission items for a change of use if it finds, among other things, that the change will not substantially increase traffic or parking needs, create safety hazards, negatively affect the neighborhood, or impair the regulations.

  • Certain existing lots in the I-1 and I-C Zones that cannot meet the ordinary frontage and access rules may use a private roadway, subject to design, emergency-access, and other stated requirements. For I-C uses, the Commission may also allow access from a private road with legal access to a public highway.

  • A lawfully established nonconforming use may continue despite later zoning requirements. This protection is limited: the nonconformity generally cannot be enlarged, and a use discontinued for six months or longer is deemed abandoned and cannot resume.

  • A later regulation or amendment will not affect a building or its designated use when complete plans were legally filed before the change, construction began within 90 days after the building permit, the structural framework was completed within six months, and the building was completed within two years.