Town of Ashford

Anti-Data Center Policies

Ashford allows data centers in its Technology Development Zone only with a special permit and at least 50 acres zoned for that use. Height, site-coverage, and review requirements create hurdles, but do not ban them.

current law · Town of Ashford
Allows computer and data processing centers only by special permit in Ashford’s Technology Development Zone, which must cover at least 50 acres.Ashford Zoning Regulations, Article 4E, § 3(4) and § 4 — Technology Development Zone (Computer and Data Processing Centers)

What this means

The regulations allow data centers in the Technology Development Zone, but only with a special permit and a site of at least 50 acres to be zoned for that use (data processing centers are special-permit uses; minimum of fifty acres). Building-height and site-coverage limits, plus extensive review requirements, create significant hurdles, though they do not amount to a ban.

People behind it

  • Adopted the regulations and is responsible for administering and enforcing them; the regulations may also be amended on the Commission’s initiative.

  • The Commission’s duly authorized agent, responsible for administering and enforcing the regulations.

Restrictions & requirementsHide restrictions & requirements5
  • Computer and data processing centers are expressly listed as special-permit uses in the Technology Development Zone (TD). Uses not specifically listed are prohibited, except uses lawfully established before the regulations’ effective dates. Computer and data processing centers and uses not specifically listed

  • A TD site must be at least 50 acres, and a concept plan is required with an application to change the zoning to TD. Minimum of fifty acres and concept plan

  • TD development is subject to a 35-foot maximum building height, 25% maximum building coverage, 40% maximum impervious-surface coverage, a 60% combined limit for impervious surface and pervious parking, and at least 25% green space. Allowable lot coverage and maximum building height

  • A special permit requires a public hearing and extensive application materials, including site plans and a traffic report; the Commission evaluates the proposal under specified standards and may impose conditions, including limits on hours of operation. All Special Permit applications shall require a public hearing, traffic report, and hours of operation

  • For a special permit, the Commission must require a performance bond covering 100% of the actual costs of specified private site improvements, inspections, and maintenance, plus a 10% contingency; the bond must be posted before the authorized work or activities begin. 100% of the actual costs and prior to commencing the work

Benefits & exceptionsHide benefits & exceptions4
  • Technology Development (TD) zoning expressly allows computer and data processing centers by special permit; a TD zone must be at least 50 acres. Computer and data processing centers

  • For integrated development in the TD zone, contiguous parcels may be consolidated and treated as one lot when calculating building coverage, yards, and permitted uses. Owners must provide recorded rights for access, passage, parking, and loading, and the parcels must follow an integrated development plan. contiguous parcels may be consolidated

  • A special permit fulfills the requirement for a zoning permit, avoiding a separate zoning-permit approval for a data center requiring a special permit. fulfills the requirement for the issuance of a Zoning Permit

  • A zoning change does not require changes to plans or designated use covered by a previously issued zoning permit, special permit, or variance, if a building permit is obtained within one year, substantial construction begins within one year after that permit, and the project is completed within two years after it is issued; otherwise, the approval becomes void. Nothing in these regulations