City of Rifle
Pro-Data Center Policies
Colorado receives a default rating of 2 because our research identifies no current or future statewide data-center-specific laws or regulations that would prevent you from building a data center. Local rules and general permitting requirements may still apply.
Rating and summary from Colorado statewide as there are no scored current or future laws outside temporary restrictions for City of Rifle.
pending · City of RifleProposes requiring data centers in industrial zones to obtain a conditional use permit and meet added requirements for setbacks, noise, water use, lighting, and environmental impacts.Proposed Rifle Municipal Code amendments for bulk consumer resource centers, including data centers
What this means
This does not ban data centers, but limits them to conditional-use approval in the LI and I districts and requires extensive studies and public review (conditional-use permit). The 1,500-foot setback from homes or other sensitive places, along with the added studies and review costs, could make suitable sites and approvals harder to secure (1,500 Feet).
Restrictions & requirementsHide restrictions & requirements9
The use schedule lists Data Centers as “*” in the CS and TC districts and “C” in the LI and I districts. The supplied text does not explain the asterisk, so its effect is unclear. Data Center (4)
A Data Center, as a subset of a Bulk Resource Consumer (BRC), requires a conditional use permit. The Planning Commission holds a public hearing and recommends approval, denial, or approval with conditions; City Council makes the final decision. The BRC definition covers uses meeting any of its resource-demand, utility-upgrade, or permit-review criteria. Server rooms for government entities, hospitals, and schools are excepted from Article XX’s requirements. Data Center facilities server rooms
Applicants must provide the required analyses and studies, which the City reviews and verifies at the applicant’s expense. The listed subjects include electrical supply and rate impacts, water and cooling, noise, thermal effects, fiscal and economic impacts, housing and construction-period housing mitigation, emergency operations, decommissioning, environmental waste, and air quality. reviewed and verified by the City
In LI and I districts, the listed siting standards require a 200-foot setback from property lines and rights-of-way, a 1,500-foot setback from residences or sensitive receptors, and a maximum building height of 50 feet. The City may alter one or more design and siting requirements if it determines the section’s goals would be better served. Minimum Setback Requirements
Noise limits apply both at sensitive-receptor property lines and at the BRC property line, with separate daytime and nighttime dBA and dBC limits. Thermal limits are a maximum 2°F increase at the BRC property line and less than a 1°F increase at a sensitive-receptor property line. NOISE REQUIREMENTS THERMAL IMPACT REQUIREMENTS
Lighting must use fully shielded, full-cutoff, downward-directed fixtures, with no direct uplight except approved emergency lighting. Light trespass is limited to 0.1 foot-candle at nearby residences or sensitive-receptor property lines and 0.2 foot-candle at adjacent industrial or commercial property lines. Nonessential lighting must use controls, and lighting not needed for operations, emergency access, or security must be dimmed or turned off from at least 9 p.m. to 4 a.m. A photometric plan and post-installation field verification are required. Lighting and visual impact
BRCs must provide proof that the project meets applicable federal, state, and county standards and regulations. provide proof
The application requires a land-use form and compliance narrative, applicable permit applications and fees, legal-access documentation, scaled site and elevation plans with supporting professional documents, before-and-after visual simulations, and forms for applicable permits and approvals. The City may request additional information needed to determine compliance. Submittal requirements
BRC applications require standard notice, enhanced notice within one-half mile, and a public meeting within City limits before formal hearings. A developer-held public meeting requires enhanced notice within 2.5 miles. Public notification
Benefits & exceptionsHide benefits & exceptions5
Data centers may be considered for approval as conditional uses in the LI and I industrial districts; they are not listed for those districts as permitted outright. The use schedule lists data centers as conditional in LI and I.
The City may alter one or more design or siting requirements when it determines the goals of the section would be better served. This allows flexibility, but does not guarantee a waiver. The City may alter these requirements.
The stated purpose includes managing BRC development without unreasonably discriminating against providers of functionally equivalent services. This is a policy goal, not an express exemption from the approval standards. Without unreasonably discriminating.
Applications may include the forms needed for associated City approvals so departments can review and process them concurrently. The listed permits and approvals still apply as required. For concurrent review and processing.
The BRC requirements do not apply to server rooms for government entities, hospitals, or schools. This is a limited exemption for those facilities, not a general exemption for data centers. Server rooms for government entities, hospitals, schools.