City of Loveland
This restriction takes precedence for the map color while in effect.
Neutral Data Center Policies
Loveland temporarily pauses new applications for data centers using at least 10 megawatts or industrial-scale cooling, while zoning rules limit some locations and require screening for certain buildings.
current law · City of LovelandAllows data centers in most zones, but requires screening in certain zones and prohibits them in two downtown areas.Loveland Unified Development Code (Title 18), § 18.02.04.10.A — Data Center Use Standards
What this means
The measure allows data centers in several zones, but adds a screening requirement for some street-facing buildings and bars them from two areas of the Downtown zone (data center standards). These are limited restrictions, so the overall effect is minor.
People behind it
- City staff
Worked to craft the Unified Development Code that the ordinance adopted.
- Planning Commission
Unanimously recommended approval of the Unified Development Code to City Council.
- City Council
Introduced and adopted the ordinance.
Show 1 more peopleShow fewer people
- City Clerk
Was responsible for publishing the required public notice and the ordinance after adoption.
Restrictions & requirementsHide restrictions & requirements2
In the DT zone, data centers are prohibited in the Fourth Street Character Area and the Neighborhood Transition Character Area (“the use is not allowed”).
In B, MAC, E, and I zones, a data center’s building elevation must be screened from adjoining streets with a type C bufferyard when the elevation is visible from the street and has less than 15 percent windows and doors (“less than 15 percent windows and doors”).
Benefits & exceptionsHide benefits & exceptions1
Data centers are allowed, subject to all other applicable UDC standards. In B, MAC, E, and I zones, elevations visible from adjoining streets must have a type C bufferyard if they contain less than 15% windows and doors; in the DT zone, data centers are prohibited in the Fourth Street and Neighborhood Transition Character Areas. Data center standards
Sources
current law · City of LovelandTemporarily halts Loveland from processing new land-use applications for data centers that require at least 10 megawatts of electricity or use industrial-scale cooling, until new rules are adopted or nine months pass.Resolution R-48-2026 — A Resolution Imposing a Suspension Upon the City’s Processing of New Land Use Applications for Certain Types of Data Centers
What this means
It would temporarily block new applications for data centers that use 10 megawatts or more or industrial-scale cooling, making it substantially harder to build or expand them. The pause would end when new rules are adopted or after nine months, whichever comes first; it does not bar existing operations or routine maintenance.
Timing
- Ends
- When City Council approves, adopts, and finalizes comprehensive data center regulations, or nine months from the resolution’s effective date, whichever occurs first.
The City Council may terminate the suspension sooner.
People behind it
- Councilmember Rothberg
Invoked the Rule of Four to direct the drafting and scheduling of the resolution.
- City Manager
Directed by the resolution to evaluate resource demand, utility impacts, economic effects, zoning, emissions, and sustainability standards during the suspension.
Restrictions & requirementsHide restrictions & requirements1
The City suspends acceptance, processing, approval, permitting, rezoning, and site plan review of new land-use applications for data centers primarily used to store, process, or transmit digital data that project an electrical demand of 10 megawatts or more, or use industrial-scale cooling infrastructure. The suspension begins on the resolution’s effective date and ends when comprehensive data center regulations are finalized or after nine months, whichever comes first, unless the City Council ends it sooner. Applicants may still participate in concept review, but at their own risk. Exceptions include routine maintenance, accessory enterprise server rooms, government-owned emergency infrastructure, applications technically complete before the effective date, and projects with statutory, code-based, or common-law vested property rights.
Benefits & exceptionsHide benefits & exceptions8
The suspension covers facilities projecting electrical demand of 10 megawatts or more or using industrial-scale cooling infrastructure. A data center meeting neither condition is outside this suspension and may pursue the ordinary approval process.
Applications deemed technically complete before the resolution’s effective date are exempt from the suspension.
Projects with statutory, UDC, or common law vested property rights are exempt from the suspension.
Routine maintenance activities are exempt.
Enterprise server rooms accessory to a primary business are exempt.
Government-owned emergency infrastructure is exempt.
Applicants may still engage with City staff and participate in the concept review process during the suspension, but do so at their own risk.
The suspension ends when comprehensive data-center regulations are finalized or after nine months, whichever comes first, and the City Council may end it sooner.