Anti-Data Center Policies
Lafayette’s enacted moratorium temporarily halts approvals for new or expanded data centers, while future rules would require special approval and impose size and distance limits.
future law · City of LafayetteRequires data centers to be enclosed, no larger than 150,000 square feet, at least 1,000 feet from residential areas, and able to show they have enough power and water; those in flood-risk areas must follow floodplain rules.Lafayette Land Use Code, adopted September 2026 (Ordinance No. 12, Series 2026) — data-center definition
What this means
Data centers are allowed, but they need special-use approval and face a 150,000-square-foot size cap and 1,000-foot separation rules, making it significantly harder to build or expand them. Extra construction requirements may also apply in flood-risk areas.
People behind it
- Councilor Adam Gianola
Introduced the ordinance.
- City of Lafayette
Rewrote and refined the Land Use Code for implementation.
- City Council of the City of Lafayette
Adopted and enacted the ordinance and approved the Land Use Code and Zoning Map.
Show 5 more peopleShow fewer people
- City staff
Authorized to make approved technical and non-substantive revisions to the Land Use Code before its effective date.
- City Attorney's Office
Consults on technical revisions and approves them as technical and non-substantive.
- Planning Director
Administers the Land Use Code.
- Floodplain Administrator
Administers floodplain standards, including permit decisions and floodplain records.
- Director
Administers oil and gas provisions, including permit and application reviews, inspections, and enforcement.
Restrictions & requirementsHide restrictions & requirements19
In zoning districts where the use table marks data centers “S,” they require Special Use Review and may be denied or conditioned under the applicable criteria.
Special Use Review requires a neighborhood meeting, Planning Commission review and recommendation, and a public hearing and City Council decision. Public notice must be mailed, posted, and published at least 10 days before the hearing.
New nonresidential buildings over 10,000 square feet require a Major Site Plan and public hearing. A data center and its site plan may be reviewed together, but each requires separate approval.
A data center may not exceed 150,000 square feet of gross floor area and must be entirely inside an enclosed building.
If a data center shares a property line with a residential use or Neighborhood zoning district, no structure or equipment may be within 1,000 feet of that shared property line.
Façades visible from a public right-of-way must have windows, doors, or similar features covering at least 30% of the façade, and building materials or design must vary at least every 150 horizontal feet.
Applicants must provide written verification from the electric utility that sufficient power capacity exists and an engineer-prepared water-demand analysis demonstrating adequate municipal water capacity for operations and fire suppression.
Data center activities must comply with the City’s noise rules and may not create a public nuisance that interferes with nearby properties’ use and enjoyment.
The parking schedule requires one vehicle space per 1,000 square feet of data-center gross floor area, subject to the code’s parking alternatives and adjustment procedures.
Applicants must pay applicable City fees, including public-hearing fees where required; the applicant may also be charged for outside-consultant review before a decision or hearing is scheduled.
Commercial and industrial development must dedicate 12% of gross lot area for public land purposes. If the City Council finds there is insufficient suitable land, it may require cash in lieu or other property instead.
Development applicants must provide additional water rights, storage, and distribution facilities under the City’s water code to serve the proposed development.
Development in a mapped flood hazard area requires a floodplain development permit, application plans, and specified elevation information, and must satisfy applicable flood-related review criteria.
In a Special Flood Hazard Area, new construction and substantial improvements must be anchored against flood forces, use flood-resistant materials and construction methods, and protect electrical, plumbing, and other service equipment from floodwaters.
Where Base Flood Elevation data exists, nonresidential buildings must elevate the lowest floor and service facilities to one foot above that elevation or be floodproofed to that height; a Colorado-registered professional engineer or architect must review and certify the floodproofing design.
In shallow-flooding AO/AH zones, nonresidential buildings must elevate the lowest floor and service facilities to at least one foot above the mapped flood depth, or three feet above adjacent grade if no depth is specified; floodproofing is an alternative.
Development, including fill, is prohibited in a designated regulatory floodway unless a licensed Colorado professional engineer’s hydrologic and hydraulic analysis demonstrates no increase in base-flood levels. An increase requires a FEMA conditional map revision and floodway revision.
For property removed from the floodplain by a FEMA Letter of Map Revision Based on Fill, permits for new structures or additions must still meet applicable standards and use elevation or floodproofing requirements measured against the base-flood elevation that existed before the fill.
Subdivision proposals and other development exceeding 50 lots or five acres, whichever is smaller, must generate Base Flood Elevation data if it is not otherwise available. Subdivision proposals must also provide adequate drainage and locate and construct utilities to minimize or eliminate flood damage.
Benefits & exceptionsHide benefits & exceptions8
Data centers are eligible for Special Use Review, providing an approval pathway subject to review rather than being prohibited. Data center
A Planned Unit Development (PUD) may modify specific standards in a base zoning district, offering project flexibility. It requires at least 10 contiguous acres and qualifying community benefits, and cannot change allowed or prohibited uses in a conventional district or modify form-based district standards. A PUD may be used to make changes to specific standards
Data centers have a parking standard of one space per 1,000 square feet of gross floor area, and qualifying parking alternatives may reduce minimum requirements subject to applicable limits and criteria. Data center
For qualifying property annexed and zoned Developing Resource (DR) without municipal water or sewer, park-dedication and water-rights fees and certain other fees may be deferred until the property is zoned for development. Required payments or dedications must be addressed before rezoning, and a signed agreement is required at annexation. may not be subject to requirements for park dedication
For redevelopment or infill, a Site-Specific Adjustment can limit application of new or increased standards: changes below 10% do not require compliance with those standards; changes from 10% to 74.9% require roughly proportionate compliance; changes of 75% or more require full compliance. Less than 10%
Certain existing approvals remain effective until they expire, are revoked, or are forfeited. Complete applications submitted before February 1, 2027 may qualify for review under prior regulations, subject to the transition rules for the application type. Approved applications and permits shall remain effective
An eligible approved site-specific development plan can establish a vested property right for three years, unless the City Council and developer agree in writing to a longer period. The plan must be an eligible plan type, and the owner must request a hearing after completing other required approval stages and before a building permit is issued. valid for a period of three years
A lawful nonconforming use may continue subject to the code's limits. For example, it may extend through a conforming structure only without structural alteration or additional dwelling or nonresidential units or uses; discontinuing a use for one year may end its nonconforming status. Nonconformities may continue to be used and occupied
Sources
current law · City of LafayetteTemporarily prohibits Lafayette from accepting, processing, or approving applications and building permits for data centers and related uses for 18 months.Lafayette Ordinance No. 21, Series 2026 — 18-month data center moratorium
What this means
If enacted, the 18-month pause on accepting, processing, or approving data-center development and building-permit applications would make new construction and expansion much harder during that period (the moratorium’s scope and duration). It does not directly ban operating existing data centers, but the temporary halt to approvals is a severe restriction.
Timing
- Ends
- 18 months from the ordinance’s effective date; the exact effective date is not stated.
The notice describes an 18-month moratorium, but does not establish its start date. Its FAQ says the period runs from the effective date or adoption, as specified by the city. The moratorium is for 18 months from the ordinance effective date.
People behind it
- Crystal Gallegos
Named as the ordinance’s introducer: Introduced by Councilor Crystal Gallegos.
- Lafayette City Council
Directed staff to prepare draft moratoria for consideration and later passed the Lafayette measure: directed staff to return with draft 18-month moratoria.
Restrictions & requirementsHide restrictions & requirements2
Lafayette: An 18-month moratorium bars accepting, processing, or approving land-use applications and building permits for developing or constructing data centers and related land uses. The notice does not specify an exception. The ordinance imposes an 18-month moratorium.
Brighton: A one-year temporary ban applies to new data-center applications. The source does not describe its scope or exceptions in further detail. Brighton’s temporary ban will be in place for one year.
Sources
current law · City of LafayetteProhibits Lafayette from accepting, reviewing, or approving applications to build or expand data centers for up to 18 months while the city develops regulations.Lafayette Ordinance No. 22, Series 2026 — 18-month data center moratorium
What this means
The measure would pause acceptance and review of applications to build or expand data centers for up to 18 months, creating a major delay for new projects. It would not stop existing facilities from operating or routine maintenance, and the pause could end sooner if new rules are adopted (the moratorium expires after 18 months or when regulations are adopted).
Timing
- Ends
- 2028-04-30, or when the appropriate regulations are adopted, whichever occurs first.
The City Council may extend the moratorium by ordinance if necessary to preserve or promote public health, safety, and welfare; it may also be repealed sooner.
People behind it
- Crystal Gallegos
Introduced Ordinance No. 21, the 18-month data-center moratorium, as identified in the ordinance.
- City staff
Recommended adoption of the moratorium and were directed to study and prepare a regulatory framework, as stated in the staff recommendation.
Restrictions & requirementsHide restrictions & requirements1
The ordinance bars the City from accepting, processing, reviewing, or approving applications for new data center facilities; the staff memo also describes the moratorium as covering expansions. It covers planning applications, building and engineering permits, and other related development applications. A data center includes a facility primarily for storing, processing, or transmitting digital data—including high-density computing, server farms, and AI training or inference—or one using industrial-scale cooling. The moratorium lasts 18 months, expiring April 30, 2028, or sooner if appropriate regulations are adopted. Exceptions include routine maintenance at existing facilities, accessory enterprise server rooms, government-owned emergency infrastructure, and applications deemed technically complete before the ordinance takes effect. (moratorium and covered applications, duration and exceptions)
Benefits & exceptionsHide benefits & exceptions4
Routine maintenance at existing data centers is exempt from the moratorium, and applications for minor site changes that do not expand or intensify operations are not covered. Existing facilities and minor changes
Applications deemed technically complete before the ordinance takes effect are exempt, allowing those projects to continue through review. Technically complete applications
Onsite enterprise server rooms accessory to a primary business that is not a data center are exempt from the moratorium. Onsite enterprise server rooms
Government-owned emergency infrastructure is exempt from the moratorium. Government-owned emergency infrastructure