City of Grand Junction

This restriction takes precedence for the map color while in effect.

Pro-Data Center Policies

Grand Junction has an upcoming pause of up to 365 days on applications for new data centers and expansions; existing centers may operate, and complete applications already accepted continue through review.

Rating from Colorado statewide as there are no scored current or future laws outside temporary restrictions for City of Grand Junction.

future law · City of Grand Junction
Temporarily prohibits Grand Junction from accepting or approving applications for data centers until it adopts data-center rules or the moratorium expires, whichever comes first.Ordinance No. 5345 — Temporary Moratorium on Data Centers (adopted version correction)

What this means

The measure would pause new data-center applications and applications to expand existing centers for up to 365 days, making development and expansion substantially harder during that period. It would not stop existing centers from operating, and applications already accepted as complete would continue through review.

Timing

Ends
On the earliest of 2027-11-23 (inclusive), adoption of Title 21 amendments addressing data centers, or further City Council action ending or modifying the moratorium.

The Council may also take further action to extend the moratorium. The ordinance states the 365-day limit and earlier-ending conditions.

People behind it

  • Introduced and adopted the ordinance establishing the moratorium.

  • Directed to oversee the study and develop recommended code amendments during the moratorium.

  • Directed to carry out the study through the department, in conjunction with the City Attorney.

Show 1 more peopleShow fewer people
  • Named to work with the Community Development Department and City Manager on the study and code amendments.

Restrictions & requirementsHide restrictions & requirements3
  • A temporary moratorium bars the City from accepting, processing, reviewing, acting on, approving, or issuing permits or other applications concerning a data center. The City also may not conduct pre-application or pre-submittal activities. It applies to data centers proposed as a principal use, accessory use, or any component of a development. The moratorium begins November 23, 2026, and ends earlier if the City adopts Title 21 amendments addressing data centers or takes action to end or modify it; otherwise it expires after 365 days, on November 23, 2027. The moratorium applies to any Application concerning a data center

  • The moratorium covers facilities meeting the ordinance’s data-center definition, including those with a projected, designed, or requested electrical load of at least 1 megawatt at full build-out. Qualifying facilities on the same or contiguous parcels under common ownership or control are aggregated. The definition excludes accessory equipment rooms serving the site’s principal use, certain regulated telecommunications facilities, utility facilities classified as “basic,” and facilities below the 1-megawatt threshold. one (1) megawatt or more

  • The moratorium does not apply to applications submitted and accepted as complete before its effective date; those continue under the code in effect when accepted. It also does not apply to data centers lawfully established and operating in the City on the effective date, but applications to expand or enlarge them or increase their electrical load are subject to the moratorium. An Application that was submitted to and accepted by the City as complete

Benefits & exceptionsHide benefits & exceptions3
  • Applications submitted and accepted as complete before the ordinance’s effective date may continue to be processed under the code in effect when accepted. The ordinance does not itself require approval or create a vested property right.

  • A data center lawfully established and operating in the City when the ordinance takes effect may continue operating. Applications to expand it, enlarge it, or increase its electrical load remain subject to the moratorium.

  • The moratorium does not cover computer, server, or network rooms accessory to and serving a lawful principal use on the same site; telecommunications facilities regulated under the cited code provision; a “utility facility, basic”; or facilities below the one-megawatt threshold. Related facilities on the same or contiguous parcels under common ownership or control are aggregated when applying that threshold.

Sources

future law · City of Grand Junction
Prohibits Grand Junction from accepting or processing applications for new data centers with at least 1 megawatt of electrical load until data-center rules are adopted or the 365-day moratorium expires.Ordinance No. 5345 — Temporary Moratorium on Data Centers

What this means

The measure would temporarily block the City from accepting or approving applications for new data centers and expansions for up to a year, creating a major development delay (moratorium period). Existing centers could keep operating, but expanding them would still require an application and be covered by the moratorium (lawfully existing uses).

Timing

Ends
The earlier of 2027-11-23 (inclusive), adoption by the City Council of Title 21 amendments addressing data centers, or further City Council action ending, modifying, or extending the moratorium.

The moratorium begins on 2026-11-23. The City Council may take further action to extend or modify it.

People behind it

  • Introduced the ordinance on first reading and adopted it on second reading. Introduced on first reading

  • Was directed to oversee the study and development of recommended code amendments. study the impacts of data centers

  • Assigned to carry out the study through the department, in conjunction with the City Attorney and other designated departments. through the Community Development Department

Show 1 more peopleShow fewer people
  • Was assigned to work with the City Manager and Community Development Department on the study and recommended code amendments. in conjunction with the City Attorney

Restrictions & requirementsHide restrictions & requirements4
  • During the moratorium, the City may not accept, process, review, act on, approve, or issue any application concerning a covered data center, and may not conduct pre-application or pre-submittal activities for one. This applies whether the center is proposed as a principal use, accessory use, or component of a development. “shall not accept, process, review”

  • The moratorium covers a data center with a projected, designed, or requested electrical load of at least 1 megawatt at full build-out. Facilities on the same or contiguous parcels under common ownership or control are aggregated. The definition excludes accessory computer/server/network rooms serving an established principal use, specified telecommunications facilities, basic utility facilities, and facilities below the load threshold. “one (1) megawatt or more”

  • The moratorium begins November 23, 2026, and lasts up to 365 days, through November 23, 2027, but ends earlier if the City adopts Title 21 amendments addressing data centers or the City Council otherwise ends or modifies it. “three hundred sixty-five (365) days”

  • The measure applies prospectively: applications submitted and accepted as complete before its effective date continue under the prior code. Lawfully established data centers already operating may continue, but an application to expand, enlarge, or increase their electrical load is subject to the moratorium. “An Application that was submitted to and accepted by the City as complete”

Benefits & exceptionsHide benefits & exceptions3
  • A data center lawfully established and operating in the City before the ordinance takes effect may continue operating without being subject to the moratorium. Applications to expand it, enlarge it, or increase its electrical load are still covered by the moratorium. The ordinance does not apply to a data center lawfully established and in operation

  • Applications submitted and accepted as complete before the ordinance takes effect may continue through review under the code in effect when accepted. The ordinance does not itself grant or enlarge vested property rights. An Application that was submitted to and accepted by the City as complete

  • The moratorium ends when the City adopts Title 21 amendments addressing data centers or, at the latest, after 365 days—November 23, 2027—unless the Council takes further action to extend it. until the City Council's adoption of amendments to Title 21