City of Dacono
This restriction takes precedence for the map color while in effect.
Anti-Data Center Policies
Dacono has enacted a temporary freeze on most applications to build or expand data centers until August 31, 2027; complete applications filed before it are exempt, and existing centers may continue operating.
Rating from Weld County as there are no scored current or future laws outside temporary restrictions for City of Dacono.
current law · City of DaconoProhibits Dacono from accepting or approving applications for data centers with an IT load of at least 500 kW until August 31, 2027.Ordinance No. 1023 – Emergency Ordinance Imposing Temporary Moratorium on Data Centers
What this means
If enacted, the measure would stop the City from accepting or acting on most applications to build or expand a data center until August 31, 2027, a roughly one-year freeze (applications would not be acted upon). It would not shut down existing data centers, and complete applications filed before the freeze are excepted, but the delay is a major barrier to new development.
Timing
- Ends
- Aug 31, 2027
The temporary moratorium terminates on this date unless sooner repealed; no extension condition is stated. shall terminate as of August 31, 2027 unless sooner repealed
Restrictions & requirementsHide restrictions & requirements3
Until August 31, 2027, the City may not receive, review, approve, or otherwise act on applications for building permits, new business licenses, or land-use or other approvals—including zoning, subdivision, special-use, and site-plan applications—for developing, constructing, or operating a data center. The moratorium also covers expanded data-center uses. The moratorium’s application restrictions and end date
The measure defines data centers broadly as facilities primarily used for centralized digital-data storage, management, processing, or transmission, with high-density computing equipment, specialized electrical and cooling systems, and backup power over 500 kW; facilities with an IT equipment load of 500 kW or greater also qualify. The definition and 500 kW thresholds
The moratorium does not affect applications that were complete before its effective date. A person with such an application may ask the City Council for an exemption, which the Council may grant if it finds applying the moratorium would be legally invalid. The prior-application exception and exemption process
Benefits & exceptionsHide benefits & exceptions2
Complete building-permit, business-license, or land-use applications filed before the moratorium took effect are not subject to its restrictions (complete applications filed prior to the effective date).
A person with a complete application submitted before the moratorium took effect may ask the City Council for an exemption by explaining why applying the moratorium would be legally invalid; the Council may grant it if it finds the application would be legally invalid under the facts presented (request for an exemption).